Winthrop Resources v. Eaton Hydraulics

CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 11, 2004
Docket03-1790
StatusPublished

This text of Winthrop Resources v. Eaton Hydraulics (Winthrop Resources v. Eaton Hydraulics) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winthrop Resources v. Eaton Hydraulics, (8th Cir. 2004).

Opinion

United States Court of Appeals FOR THE EIGHTH CIRCUIT ___________

No. 03-1790 ___________

Winthrop Resources Corporation, * a Minnesota corporation, * * Appellee, * Appeal from the United States * District Court for the v. * District of Minnesota. * Eaton Hydraulics, Inc., formerly * known as Vickers, Inc., a * Delaware corporation, * * Appellant. * ___________

Submitted: October 23, 2003

Filed: March 11, 2004 ___________

Before RILEY, HEANEY, and SMITH, Circuit Judges. ___________

SMITH, Circuit Judge. Eaton Hydraulics, Inc. ("Eaton"),1 appeals the district court's2 summary judgment issued in favor of Winthrop Resources Corporation ("Winthrop") in Winthrop's breach-of-contract claim. The district court determined that Eaton breached the contract and owes $4,365,437.64 in damages, costs, disbursements, and attorney's fees. We affirm.

I. Background Winthrop leases computer systems and other technology equipment to corporate customers. After Winthrop's customers select their equipment, Winthrop then purchases and leases the equipment to the customers. In June 1997, Eaton and Winthrop entered into a master lease agreement.3 The agreement provided that Winthrop would purchase almost $9 million of computer equipment that Eaton selected. The parties also signed nine lease schedules (001R, 002R, A01, A02, A03, B01, B02, C01 and C02) issued pursuant to the master lease agreement.4 Each lease schedule identified particular pieces of equipment leased by Eaton, and each incorporated the terms of the master lease by reference. Each lease schedule listed the monthly amount Eaton agreed to pay for the use of Winthrop's equipment. By

1 Vickers, Inc. originally entered into the lease agreements with Winthrop. Eaton subsequently acquired Vickers. Eaton acknowledges that it is bound by the lease agreements with Winthrop. For ease of discussion, we refer only to Eaton in this appeal. 2 The Honorable David S. Doty, United States District Judge for the District of Minnesota. 3 The lease provided that Minnesota law would govern all disputes. 4 The master lease agreement and the lease schedules are collectively referred to as the "Lease" unless otherwise noted.

-2- executing the Lease, both Winthrop and Eaton expressly agreed that each provision was binding and enforceable.5

Winthrop sued Eaton on April 13, 2001, alleging that Eaton breached the Lease. Specifically, Winthrop claimed that Eaton failed to meet numerous payment obligations, failed to properly maintain the equipment during possession, failed to properly package the equipment upon return, and impermissibly sold pieces of equipment in violation of the Lease terms. Eaton counterclaimed that Winthrop breached the implied covenant of good faith and fair dealing, committed fraud, breached the contract, and violated various provisions of Minnesota law.

Winthrop moved for summary judgment on its claims and moved to dismiss Eaton's counterclaims. In its motion, Winthrop requested damages in the amount of $4,222,024.67, plus costs, disbursements, and attorney's fees. Winthrop provided affidavits and supporting documents detailing Eaton's various Lease breaches. Winthrop submitted its damage calculation pursuant to section 18 of the Lease setting forth past-due Lease charges, past-due taxes and late fees, and the greater of: (i) the accelerated rent remaining due, or (ii) the Casualty Loss Value ("CLV") for each lease schedule.6

5 When Eaton acquired Vickers, Eaton sent its standard lease agreement to Winthrop and asked Winthrop to substitute Eaton's standard form for the Lease that Vickers and Winthrop negotiated and signed. Winthrop declined the proposed substitution; however, Winthrop included Eaton's proposed substitution lease in its brief and appendix to compare the language of the proposed lease to the language of the controlling Lease. 6 The "past due" component of Winthrop's damages calculation was the sum of: (i) past-due Lease charges incurred during the initial terms of lease schedules 002R, A02, A03, B01, B02, C01 and C02; (ii) past due Lease charges incurred during the extension terms of lease schedules 001R and A01; (iii) past-due taxes and late fees. The "greater of accelerated rent or Casualty Loss Value" component of Winthrop's damages calculation was the sum of: (i) the CLVs of lease schedules

-3- In its counterclaim, Eaton asserted that: (i) Winthrop failed to give notice and opportunity to cure the payment defaults; (ii) it had procured Manufacturer's Maintenance Agreements ("MSMAs") on the equipment and that Winthrop purchased the MSMAs; (iii) Winthrop breached first; (iv) the CLV was an unenforceable penalty; (v) the CLV did not apply to equipment on "terminated" lease schedules. Applying Minnesota law, the district court rejected Eaton's arguments as insufficient to avoid liability and damages under the plain terms of the Lease.

On April 23, 2002, the district court granted Winthrop's motion for summary judgment. The district court found that Eaton breached the Lease and that the CLV damages provision was enforceable. The district court noted that Eaton did not dispute that it had breached the Lease. The court also noted that Eaton did not dispute Winthrop's damages calculation.

Winthrop subsequently filed a motion pursuant to Federal Rules of Civil Procedure 58 and 59(e) requesting clarification of the damages award in the summary judgment and dismissal order. The district court awarded judgment on April 23, 2002, in the amount of $4,365,437.64, which included Winthrop's costs and attorney's fees, less mitigation, because Eaton failed to challenge Winthrop's calculation of damages.

On May 8, 2002, Eaton moved pursuant to Federal Rule of Civil Procedure 59(e) to alter or amend the judgment. Eaton argued that the expert reports it submitted after the summary-judgment hearing demonstrated the unreasonableness of the CLV provision. Eaton also argued–for the first time–that: (i) Winthrop failed to prove that its claimed damages were reasonable; (ii) it could not maintain MSMAs on the equipment because MSMAs did not exist for this equipment; (iii) Eaton properly terminated lease schedules A02 and C01.

001R, 002R, A01, A03, B01, B02 and C02, and (ii) the accelerated rents due for lease schedules C01 and A02.

-4- On December 10, 2002, the district court denied Eaton's Rule 59(e) motion. The district court determined that Eaton failed to submit any newly-discovered evidence, failed to show reversible error, and failed to present any facts or law overlooked by the court. Following this decision, Winthrop moved for entry of judgment on damages, and on February 21, 2003, the district court entered an amended judgment including damages in the amount of $4,365,437.64.

Eaton timely filed a notice of appeal from all of the district court's orders. However, in this appeal, Eaton challenges only the grant of summary judgment and the order clarifying the damages award.

II. Standard of Review Rule 56(c) provides that a motion for summary judgment shall be granted only if "there is no genuine issue as to any material fact and . . . the moving party is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(c). We review de novo a grant of summary judgment, applying the same standard as the district court. Evergreen Inv., LLC v. FCL Graphics, Inc., 334 F.3d 750

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Green Tree Acceptance, Inc. v. John W. Wheeler
832 F.2d 116 (Eighth Circuit, 1987)
Donna Krenik v. County of Le Sueur
47 F.3d 953 (Eighth Circuit, 1995)
Barry v. Barry
78 F.3d 375 (Eighth Circuit, 1996)
Enterprise Bank v. Magna Bank of Missouri
92 F.3d 743 (Eighth Circuit, 1996)
Medtronic, Inc. v. U.S. Xpress, Inc.
341 F.3d 798 (Eighth Circuit, 2003)
Bellboy Seafood Corp. v. Nathanson
410 N.W.2d 349 (Court of Appeals of Minnesota, 1987)
PacifiCorp Capital, Inc. v. Tano, Inc.
877 F. Supp. 180 (S.D. New York, 1995)
City of Virginia v. Northland Office Properties Ltd. Partnership
465 N.W.2d 424 (Court of Appeals of Minnesota, 1991)
Dean Van Horn Consulting Associates, Inc. v. Wold
367 N.W.2d 556 (Court of Appeals of Minnesota, 1985)
Carl Bolander & Sons Inc. v. United Stockyards Corp.
215 N.W.2d 473 (Supreme Court of Minnesota, 1974)
Matter of Turners Crossroad Development Co.
277 N.W.2d 364 (Supreme Court of Minnesota, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Winthrop Resources v. Eaton Hydraulics, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winthrop-resources-v-eaton-hydraulics-ca8-2004.