Rice, P. J.,

In June, 1905, the plaintiff entered into a contract with the defendant to make certain alterations and repairs to the defendant’s buildings for $1,625. Later in the month, after this work was under way, a second contract was entered into by them for additional alterations, and for a change in the alterations contemplated in the first contract. There is no dispute as to the making of these two contracts, or as to the plaintiff’s performance, or as to the price to be paid under the first, or as to the fact that the additional sum to be paid under the second contract was agreed upon, but there is a dispute as to what the agreed sum was. The plaintiff alleged in his statement of claim and gave evidence that it was $2,900, thus making his entire claim, apart from extras which are not in dispute, $4,525. The defendant testified that the agreed price was $1,275, or, to be more exact, that the second contract was that all of the alterations were to be made for $2,900. It is enough to say, without obscuring the statement by unnecessary recital of dates and amounts, that the verdict of the jury implies a finding that the plaintiff agreed to make the alterations contemplated by the two contracts for $2,900. What occurred after these contracts were made and were partly performed is to be considered in the light of this established fact.

This being the contract between the parties, and the greater part of the alterations having been made, the defendant on July 11, requested the plaintiff to give an agreement to be filed in the prothonotary’s office that would protect his property against mechanics’ liens. This in substance is the plaintiff’s testimony adduced by his own counsel, in the presentation of his case in chief, and in his direct examination. The defendant’s version is that he told the plaintiff he had .been negotiating for a loan and the parties had inquired of him whether he had a “release of liens,” and that thereupon the plaintiff said: “That is all right; we can easily fix that up; we will go to Mr. Rothenberger.” Thereupon they went to Mr. Rothenberger, the architect, and requested him to prepare a contract against mechanics’ liens. He was given no instruc[502]*502tions as to the terms or the price, and nothing was said upon this subject by either of the parties. Rothenberger, who was called as a witness by the plaintiff, testified upon cross-examination that he was asked to prepare a contract against mechanics’ liens, and was not asked to prepare anything else. This testimony was not contradicted. Without going further into detail as to the preparation of the paper, we are warranted in saying that the testimony furnishes no ground for inference that the parties intended to make a new agreement as to price or as to the alterations of the building in the place of the existing one, but that all of the evidence leads to the conclusion that their intention and their instructions to Rothenberger were to prepare a paper for their execution, which would protect the defendant’s property against mechanics’ liens, and that this was the sole purpose they intended the paper to accomplish. Mr. Rothenberger could not attend to the matter immediately, but later prepared a typewritten paper, dated July 12, purporting to be an agreement for making the alterations in the defendant’s buildings, and containing a formal stipulation against liens. In the clause relating to the amount to be paid for the alterations appeared the words “a sum of money stipulated in a separate contract,” and in the clause relating to the time of completion appeared the words, "time stipulated in a separate contract.” On July 12 the plaintiff called for the paper, and by his direction, the defendant not being present and not having been consulted, Rothenberger drew a line through the above-quoted words, and in the first of these clauses interlined with a pen the words and figures "the sum of four thousand five hundred and twenty-five ($4,525.00) dollars” and in the second clause substituted in the same manner the words and figures “ 15th day of September, 1905.” The plaintiff then took the paper to the defendant, and after it was executed took it to the court house for filing. The testimony as to what occurred at the time of execution is not in conflict except as to one particular. The defendant testified that he did not read the paper, while the testimony of the pláintiff and his witnesses tends to show that he, at least, "leafed it over,” and had an opportunity to read it. But the [503]*503plaintiff admits that he did not call'the defendant’s attention to the alterations in the paper, and there is no testimony that anything was said as to the price or as to any other matter, which, apart from the paper itself, would tend to show that the parties intended to substitute it for the contracts under which the work was being done. On the contrary, the defendant’s testimony is that when the plaintiff produced the paper for his execution he said: “Here is the release of liens I got; sign it.” This testimony is not contradicted. Taking the plaintiff at his word, there was.no change of intention on his part as to the purpose for which the paper was to be used, and it is evident that there was none on the defendant’s part.

It is to be observed that the plaintiff in his statement of claim sets up the two parol contracts of June as entering into his cause of action, and says that “after the greater part of said work had been completed and most of said materials furnished for the alterations of said buildings .... a written article of agreement was entered into,” reciting the terms and attaching a copy of the paper of July 12. There is no averment that this was intended to abrogate or to be a substitute for the contracts under, which the work had been entered upon and carried so far toward completion. It is further to be noticed that the subjects investigated upon the trial, namely, the making and the terms of the two June contracts, the purpose for which the paper of July 12 was prepared, the instructions to the scrivener, the interlineations in the paper and its execution, were thrown open to the defendant’s parol testimony relating thereto, by the parol testimony of the plaintiff and his witnesses, given upon the same subjects, in the presentation of his case in chief. Notwithstanding this manner of presenting his case in his pleadings and evidence, the plaintiff contends that the paper of July 12 is conclusive upon the question of consideration. We cannot concur in that conclusion. That paper, on its face, does not purport to be an agreement as to past transactions. In order to connect it' with them parol evidence, was necessary. The plaintiff appreciated this, and,presented his case accordingly; but as so presented the principle was applicable that when matters of fact, de[504]*504pending on oral testimony, are connected with and necessary to a proper understanding of written evidence, the court is not bound to consider and give effect to the latter as though it stood alone; an admixture of oral and written evidence draws the whole to the jury: Home Building and Loan Association v. Kilpatrick, 140 Pa. 405; Chicago Cottage Organ Co. v. McManigal, 8 Pa. Superior Ct. 632; Wetherill Bros. v. Erwin & Wagener Co., 12 Pa. Superior Ct. 259.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atglen Borough v. Pennsylvania Public Utility Commission
174 Pa. Super. 149 (Superior Court of Pennsylvania, 1953)
Campbell v. Rhoads
10 Pa. D. & C. 136 (Lancaster County Court of Common Pleas, 1927)
Bone v. Detroit National Fire Insurance
104 A. 742 (Supreme Court of Pennsylvania, 1918)
Haney v. Moorehead
61 Pa. Super. 187 (Superior Court of Pennsylvania, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
36 Pa. Super. 496, 1908 Pa. Super. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winters-v-schmitz-pasuperct-1908.