Winning Estates, LLC v. Lexington Conservation Commission

15 Mass. L. Rptr. 51
CourtMassachusetts Superior Court
DecidedJuly 11, 2002
DocketNo. 010541
StatusPublished

This text of 15 Mass. L. Rptr. 51 (Winning Estates, LLC v. Lexington Conservation Commission) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winning Estates, LLC v. Lexington Conservation Commission, 15 Mass. L. Rptr. 51 (Mass. Ct. App. 2002).

Opinion

Gershengorn, J.

This case arises out of a suit by Winning Estates (“the plaintiffs”) against the Lexington Conservation Commission (“the Commission”) resulting from the denial of the plaintiffs’ purposed subdivision plans by the Commission.

The plaintiffs filed this action in the nature of certiorari pursuant to G.L.c. 249, §4, seeking review by this Court of the Commission’s actions on the record. The parties now cross move for judgment on the pleadings under Mass.R.Civ.Pro. 12(c). For the following reasons, the Commission’s motion is ALLOWED.

FACTS

In May of 1999, the plaintiffs filed Notices with the Commission for the proposed development of a four-lot subdivision which spans an 8.22 acre parcel of land in Lexington. The parcel of land is divided by a large area of wetlands through which an intermittent stream flows. The plaintiffs’ proposed subdivision plan required the filling of portions of the wetlands as well as intrusions upon the buffer zone around the wetlands. Because the parcel in question contains an imposition upon wetlands, the plaintiffs’ proposed plan must follow Lexington’s General By-Laws for Wetland Protection, most specifically, Rule 5(C)(1) (“the By-law”).1

The Commission argues that the plaintiffs’ reading of the By-law is incorrect and has led the plaintiffs to falsely conclude that the plan is within the bounds of the By-law. The Commission further argues that this Court cannot substitute the Commission’s reading of the Commission’s own By-law with that of the Court’s unless there is a finding of an arbitrary and capricious action on the part of the Commission.

The plaintiffs argue that their reading of the By-law is correct and that based on their reading, the calculations made by the plaintiffs show the subdivision plan to be within the By-law. The plaintiffs conclude that the Commission acted arbitrarily and ■ capriciously by denying a subdivision plan which is within the bounds of the By-law as read by the plaintiffs.

DISCUSSION

I. Standard of Review

When reviewing an action in the nature of certiorari under G.L.c. 249, §4, this Court is limited to correcting “substantial errors of law apparent on the record adversely affecting material rights.” Commissioner of Rev. v. Lawrence, 379 Mass. 205, 208 (1979). The standard under which this Court reviews an action varies “according to the nature of the action for which review is sought.” Forsyth Sch. for Dental Hygienists v. Board of Registration in Dentistry, 404 Mass. 211, 217 (1989). The plaintiffs argue that the Commission’s decision to deny the subdivision plan was speculative and without support. Therefore, this Court applies the arbitrary and capricious standard. FIC Homes of Blackstone, Inc. v. Conservation Comm’n of Blackstone, 41 Mass.App.Ct. 681, 684 (1996). “A decision is not arbitrary and capricious unless there Is no ground which ‘reasonable men might deem proper’ to support it.” Leoplodstadt, Inc. v. Comm’r of the Div. of Health Care Fin. & Policy, 436 Mass. 80, 91 (2002), citing T.D.J. Development Corp. v. Conservation Comm’n of North Andover, 36 Mass.App.Ct. 124, 128 (1994), quoting Cotter v. Chelsea, 329 Mass. 314, 318 (1952). The plaintiffs bear the burden of demonstrating that the Commission’s decision was not reasonably related to the preservation and protection of interests covered by the wetland provision in the

[52]*52By-law. See T.D.J., supra, at 129, citing Forsyth, supra at 217-18.

II. The Wetland Bylaw

The parties agree that the controversy can be distilled into the Court’s reading of the By-law. The plaintiffs argue that the Commission has interpreted the By-law incorrectly and this error led to an erroneous calculation which in turn resulted in the denial of the subdivision plan. The Commission argues that the language of the By-law is clear. The Commission further contends that even in the absence of such clear language this Court must adopt the Commission’s interpretation absent evidence of arbitrary and capricious decision making. This Court finds that the Commission is correct in both arguments.

The plaintiffs first argue that where the By-law requires that a construction activity cannot disturb more than fifty percent (50%) of the 100-foot buffer zone, the By-law is referring to all of the buffer zone on a particular lot. The Commission, however, argues that this 50% calculation refers only to the contiguous buffer zone not the entire buffer zone in question. The By-law states in pertinent part:

Of contiguous land within the 100-foot buffer zone, construction activities can disturb no more than 50% or the amount not presently supporting a natural community, whichever is greater.

(Emphasis added.)

It is clear to the Court that the By-law refers only to the contiguous buffer zone as is evidenced by the clear language of the By-law. The plaintiffs’ interpretation is not supported by the plain language of the disputed By-law.

Even if the plaintiffs had a strong argument that the language of the By-law was open to interpretation in a manner favorable to the plaintiffs, Massachusetts case law does not allow this Court to substitute its reading of a by-law written and interpreted by the Commission if that interpretation is not arbitrary or capricious. The Commission is entitled to substantial deference as a body which is authorized by statute and by the local by-laws to determine wetlands protection. This Court must give “due weight to the [Commission’s] experience, technical competence, and specialized knowledge.” See Dahoney v. Director of Division of Employment Security, 377 Mass. 333, 337 (1979).

Casting a deferential eye on the evidence before it, this Court finds that not only is the language of the By-law as interpreted by the Commission clear, but the plaintiffs have failed in their burden to demonstrate that the Commission’s reading of the By-law is not reasonably related to the preservation of the wetlands or that a reasonable person could not find grounds to support the Commission’s reading of the By-law. See Forsyth, supra at 217-18. See also Cotter, supra at 318.

III. Disturbance to the Buffer Zone

The plaintiffs next argue that even if their interpretation of the By-law is not correct this Court should adopt the plaintiffs’ calculations regarding the amount of disturbance to the buffer zone. This Court finds it impossible to do so. First, the plaintiffs are unable to demonstrate to this Court how and from where the plaintiffs arrived at their numbers regarding buffer zone disturbance. All the plaintiffs offer this Court is an assertion that engineers developed the numbers and therefore those numbers should be credited by this Court. This Court cannot determine the credibility of the plaintiffs’ engineers without a description of where the numbers came from and the method used to attain them.

The Commission, on the other hand, has provided this Court with a detailed description of the formula used by it to determine the amount of disturbance to the buffer zone. The Commission employed a tool called a planimeter used by architects to accurately measure irregularly shaped areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cotter v. City of Chelsea
108 N.E.2d 47 (Massachusetts Supreme Judicial Court, 1952)
Dohoney v. Director of the Division of Employment Security
386 N.E.2d 10 (Massachusetts Supreme Judicial Court, 1979)
Forsyth School for Dental Hygienists v. Board of Registration in Dentistry
534 N.E.2d 773 (Massachusetts Supreme Judicial Court, 1989)
T.D.J. Development Corp. v. Conservation Commission
629 N.E.2d 328 (Massachusetts Appeals Court, 1994)
Commissioner of Revenue v. Lawrence
396 N.E.2d 992 (Massachusetts Supreme Judicial Court, 1979)
Leopoldstadt, Inc. v. Commissioner of the Division of Health Care Finance & Policy
436 Mass. 80 (Massachusetts Supreme Judicial Court, 2002)
Lisbon v. Contributory Retirement Appeal Board
670 N.E.2d 392 (Massachusetts Appeals Court, 1996)
FIC Homes of Blackstone, Inc. v. Conservation Commission
673 N.E.2d 61 (Massachusetts Appeals Court, 1996)
Hotchkiss v. State Racing Commission
701 N.E.2d 642 (Massachusetts Appeals Court, 1998)
Conservation Commission v. Pacheco
733 N.E.2d 127 (Massachusetts Appeals Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
15 Mass. L. Rptr. 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winning-estates-llc-v-lexington-conservation-commission-masssuperct-2002.