Wingert v. Snouffer

134 Iowa 97
CourtSupreme Court of Iowa
DecidedSeptember 25, 1906
StatusPublished
Cited by20 cases

This text of 134 Iowa 97 (Wingert v. Snouffer) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wingert v. Snouffer, 134 Iowa 97 (iowa 1906).

Opinion

Bishop, J.

’In December, 1902, a contract was entered into between the city of Tipton and Snouffer & Ford, [99]*99of the city of Cedar Rapids, by the terms of which the latter were to prepare for curbing and paving, and to curb and pave, certain streets in said city. The contract provides among other things that Snouffer & Ford, who are designated as the contractors, shall furnish all materials, labor, etc., to execute and complete the work in the best possible manner, and according to plans and specifications. That they shall employ only competent foremen, experienced mechanics, and laborers, etc. A further provision declares that the work shall be done under the supervision of a committee of the city council, consisting of three members, designated as a Committee on Public Works,” and this committee is authorized to appoint an inspector, whose duty it shall be to point out to the contractors any neglect or disregard of the specifications. It is said, however, that the right of final acceptance shall not be affected by such inspection. Further — ■

All materials furnished and work done will be inspected by the engineer (employed by the city), and if not in accordance with these specifications and the contract, they will be rejected, and shall be immediately removed and other work done and materials furnished in accordance therewith. . . . The contractor shall furnish all necessary facilities, should it he advisable to make any examination of the work already completed. If any be found defective in any respect, they shall defray the expense of such examination, and of satisfactory reconstruction. . . . The engineer shall have the right to reject, at any time previous to the final settlement with the contractors, any work or materials which may be found to be faulty. . . .No deviation from the plans and specifications will be allowed except by written authority of the engineer.

With respect to the materials to he used, and the manner of doing the work, the following provisions appear in the contract:

The subgrade of the roadway shall be of the depth of the paving, including foundation, after having been thor[100]*100oughly compacted and secured from further settlement by flooding, ramming or rolling, etc. When graded and shaped in proper form, the street shall be thoroughly rolled with a steam roller until the subfoundation is compacted to the satisfaction of the committee. Any depression thereafter discovered shall be filled and the surface rerolled. On the subgrade shall be laid a foundation of cement concrete to a uniform thickness of four inches. In making the concrete an approved brand of Portland cement shall be used. The sand shall be clean, sharp river sand. The crushed stone shall be of the best quality of limestone. The cement, sand, and stone shall be thoroughly mixed in proportions as follows: One part cement, three parts sand, and seven parts stone. The concrete shall be dej>osited in a layer on the roadway in such quantity that after being rammed in place it shall be of the required thickness, true, and smooth, and five inches below and parallel with the top of the finished pavement. Upon the concrete foundation shall be placed a layer of clean sharp sand, free from loam and all foreign matter to a depth of two inches. Upon such sand layer, brick shall be laid, and the surface of the pavement shall then be thoroughly compacted by ramming or rolling so as to leave the street to the required crown and grade.

It is provided that upon the completion of the improvement a final estimate of the work done and materials furnished will be made immediately after the city engineer has satisfied himself by tests, examinations, or otherwise, that the work has been and is finally and fully completed in perfect accordance with the contract and specifications. Payments will be made on the completion of the contract and the acceptance of the work by the city council in assessment certificates based on assessments against abutting property to the extent that such assessments may be lawfully made; the balance to be paid in warrants drawn on the improvement fund of the city.

In their petition the plaintiffs set forth the contract in question, and they allege that the contractors claim to have completed the work contemplated thereby. It is -then alleged that the materials used and the work done were not [101]*101in compliance with the contract, and that the pavement is inferior and worthless. Specifically, they charge that the sub-grade wás not prepared in accordance with the specifications; that an inferior quality of cement, sand, and stone was used for the concrete work; that as to the foundation there was a failure to use the required quality and quantity of materials prescribed, and a failure to properly mix and prepare such materials as were used; that the sand used for a layer or cushion was inferior in quality and deficient in quantity; that there was a failure to construct the paving to conform to the grade of the street, thereby leaving the surface uneven and irregular. It is then said that a.t a meeting of the city council, the committee on public works by two of its members, acting either negligently or in collusion with the contractors, reported the work contemplated by the contract as completed, and as satisfactory in every way and in accordance with the terms of the contract; that at such meeting the city engineer also reported the work as complete and in accordance with the plans and specifications, and submitted a plat and assessment list embracing the names of the abuting property owners, including plaintiffs, liable to assessment, and the amount to be assessed to each. Further, that upon the coming in of such reports the council passed a resolution approving the report of the committee, and accepting the improvement as satisfactory, and by a further resolution directed notice to be given of the time when objections would be heard and assessments levied. And it is said that such notice was given, and an assessment levied in accordance with the report of the engineer, and that, unless restrained, assessment certificates will be issued.

The defendants Snouffer & Ford answered the petition, denying all the allegations of fraud and failure on their part. In a cross-petition against the defendant city and its officers, they allege the completion of the work according to contract, and the approval and acceptance thereof by the city, and pray for an order requiring payment to be made in [102]*102manner and form as provided in the contract. The defendant city answered plaintiffs’ petition, admitting the truth of the allegations of fraud and failure as. charged against defendants Snouffer & Ford;, denying that any assessment had been levied; and asserting that it was opposed to accepting the work in question as satisfactorily completed, and opposed to the levy of any assessment on account of said work. The city also answered the cross-petition of defendants Snouffer & Ford, denying that the work in question was ever approved and accepted by it; denying that the work was done and completed by said defendants in accordance with the terms of their contract; asserting that, on the contrary, the work was inferior both in material and workmanship; denying that any sum had become due to said defendants. It was in this situation that the motion of defendants Snouffer & Ford to dissolve the temporary injunction was presented to the court, and the ruling entered sustaining such motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Chariton v. JC Blunk Construction Company
112 N.W.2d 829 (Supreme Court of Iowa, 1962)
Jordan v. Beeson
280 N.W. 625 (Supreme Court of Iowa, 1938)
Sioux City v. Western Asphalt Paving Corp.
271 N.W. 624 (Supreme Court of Iowa, 1936)
Kelleher v. Joint Drainage District No. 18
249 N.W. 401 (Supreme Court of Iowa, 1933)
Peoples Savings Bank v. McCarthy
222 N.W. 372 (Supreme Court of Iowa, 1928)
Cardell v. City of Perry
207 N.W. 775 (Supreme Court of Iowa, 1926)
Western Asphalt Paving Corp. v. City of Marshalltown
214 N.W. 687 (Supreme Court of Iowa, 1926)
Anthon State Bank v. Bernard
198 Iowa 1345 (Supreme Court of Iowa, 1924)
Ryan v. New England Mutual Life Insurance
108 S.E. 182 (Supreme Court of South Carolina, 1921)
Thos. Cusack Co. v. Myers
189 Iowa 190 (Supreme Court of Iowa, 1920)
Lade v. Board of Supervisors
183 Iowa 1026 (Supreme Court of Iowa, 1918)
Atkinson v. City of Webster City
177 Iowa 659 (Supreme Court of Iowa, 1916)
Becker v. Baker
174 Iowa 97 (Supreme Court of Iowa, 1916)
In re Appeal of Apple
161 Iowa 314 (Supreme Court of Iowa, 1913)
Snouffer v. City of Tipton
161 Iowa 223 (Supreme Court of Iowa, 1913)
Snouffer & Ford v. City of Tipton
129 N.W. 345 (Supreme Court of Iowa, 1911)
Swan v. City of Indianola
121 N.W. 547 (Supreme Court of Iowa, 1909)
Hartshorn v. Wright County District Court
120 N.W. 479 (Supreme Court of Iowa, 1909)
Snouffer & Ford v. Grove
116 N.W. 1056 (Supreme Court of Iowa, 1908)
Bennett v. City of Emmetsburg
115 N.W. 582 (Supreme Court of Iowa, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
134 Iowa 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wingert-v-snouffer-iowa-1906.