Windham Power Lifts, Inc. v. Department of Defense, Air Force Directorate of Contracting & Manufacture (In re Windham Power Lifts, Inc.)

131 B.R. 181, 1990 Bankr. LEXIS 2900
United States Bankruptcy Court, M.D. Alabama·Decided November 13, 1990·No. Bankruptcy No. 87-02696-APG; Adv. No. 87-0183-APG·Published

Opinion

MEMORANDUM OPINION

A. POPE GORDON, Bankruptcy Judge.

Windham Power Lifts, Inc. filed this complaint against the Department of Defense1 to recover $31,264.03 for storing and insuring property of the government for a period of eleven months following the debtor’s petition in bankruptcy.

Trial was held October 24, 1990.2 Many of the facts were undisputed. The remainder are found by the court pursuant to Bankruptcy Rule 7052.

The government awarded Quality Plus Equipment, Inc. a contract to manufacture 234 forklift trucks.3 Quality subcontracted with the debtor to manufacture the forklifts.4

The debtor’s subcontract with Quality incorporated the terms of the government contract5 which, in turn, incorporated applicable provisions of the Federal Acquisition Regulations.

The debtor filed a petition under Chapter 11 in bankruptcy on October 22, 1987 after having manufactured and delivered 97 forklifts.6

On the petition date, the debtor had on hand completed forklifts, forklifts in process, and large quantities of parts and materials for use in forklift production.7

Both the debtor and the government claimed an interest in this property remain[183]*183ing at the debtor’s plant.8

The court entered an order one week after the bankruptcy petition requiring the debtor to segregate, insure, and hold the property subject to further order of the court.9

The government terminated its contract with Quality on April 19, 1988.10 It appears, however, that the subcontract was in default even prior to the debtor’s filing its petition in bankruptcy in October, 1987.

The court entered an order on April 28, 1988 holding that the government held title to the property free of any interest of the debtor.

During the next two and one-half months, the debtor withheld permission to the government to enter the plant to begin removing the property. The debtor spent part of that time in an unsuccessful attempt to renegotiate the Quality contract directly with the government.

The debtor finally allowed the government on July 12, 1988 to send experts to the plant to assess shipment needs.11 The government then began planning for and organizing the removal of the property from the debtor’s premises.

It took the government two months to plan the move. The government spent much of this time negotiating with the debtor by telephone and by mail regarding the dates of the move, the hours of work, the number and names of personnel to be involved in the move, and use of the plant facilities.

The government actually commenced the two-week job of packing and shipping the property on September 13, 1988. The job took thirteen men working seven and one-half hours per day.12

DISCUSSION

Prior to termination of the contract, the debtor was obligated to store and insure the property for the government without charge.13

Therefore, the court must decide whether the debtor may charge the government for storage and insurance costs incurred after termination of the contract and before actual removal of the property.

The court is unable to find any basis in law or equity to support the debtor’s claim.14

The property remained in the debtor’s possession largely through its own actions. Although it took the government two months (from July 13 to September 13, [184]*1841988) to plan the move, planning did begin without undue delay after the July 13,1988 visit to the plant.

It is not surprising that planning and organizing the. move took two months. Removal of such a large quantity of goods presented tremendous and unusual logistical problems.15 In addition, the government spent much of the two-month period negotiating with the debtor regarding details of the move.16 Under the circumstances, the court cannot say that the two-month delay was entirely the fault of the government or that the government acted in bad faith.17

The court concludes that equity is on the side of the government. The evidence does not show that the debtor was required to store the property against its will.18 Additionally, it appears that it was in the best economic interest of the debtor for the government to take delivery of the property at the plant site rather than require the debtor to deliver the property to the government at another site.19 If the debt- or has an equitable claim for compensation, it would be against the contractor Quality.

The debtor argues, without merit, that the order entered at the outset of the case requiring the debtor to segregate, hold, and insure the property bestows validity to its claim. The order was entered prior to termination of the government contract. The contract required the debtor to store the property at the expense of the debtor.20 The order did not purport to change the contract; its purpose was merely to protect the government’s interest in property claimed adversely by the debtor.

The debtor further argues that it has a warehouseman's lien for storage. However, under Alabama law, the debtor is not a warehouseman, because the debtor is not “a person engaged in the business of storing .goods for hire.” See Ala. Code § 7-7-102(l)(h) (1975).

Neither is the debtor a bailee, because the debtor is not a “person who by a warehouse receipt, bill of lading or other document of title acknowledges possession of goods and contracts to deliver them.” See Ala. Code § 7-7-102(l)(a) (1975).

The facts do not support a common law bailment for compensation in that there is no evidence to show that the government and the debtor had an agreement, either express or implied, that some price or compensation would be paid in return for storing the property after termination of the contract. Absent such an agreement, no bailment for compensation arises. See 8 Am.Jur.2d, Bailments § 20.

Judgment for the government will enter separately.

FINAL JUDGMENT

In accordance with the Memorandum Opinion entered this day, it is hereby

[185]*185ORDERED that the plaintiff’s motion for summary judgment is DENIED.

Free access — add to your briefcase to read the full text and ask questions with AI

Windham Power Lifts, Inc. v. Department of Defense, Air Force Directorate of Contracting & Manufacture (In re Windham Power Lifts, Inc.), 131 B.R. 181, 1990 Bankr. LEXIS 2900 (Ala. 1990).

131 B.R. 181 (Windham Power Lifts, Inc. v. Department of Defense, Air Force Directorate of Contracting & Manufacture (In re Windham Power Lifts, Inc.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related