Winchester Manufacturing Co. v. United States

72 Ct. Cl. 106, 1930 U.S. Ct. Cl. LEXIS 332, 1930 WL 2510
CourtUnited States Court of Claims
DecidedDecember 1, 1930
DocketNo. D-842
StatusPublished
Cited by1 cases

This text of 72 Ct. Cl. 106 (Winchester Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winchester Manufacturing Co. v. United States, 72 Ct. Cl. 106, 1930 U.S. Ct. Cl. LEXIS 332, 1930 WL 2510 (cc 1930).

Opinions

Green, Judge,

delivered the opinion:

This suit is brought by the plaintiff to recover $1,288,-328.10 claimed to be due it from defendant on a contract to manufacture cartridges and other war materials.

On July 20, 1917, the plaintiff entered into a contract (No. 14067) with the defendant for the manufacture of a very large number of cartridges. This contract was subsequently modified by six other supplemental contracts which greatly increased the number of cartridges to be manufactured and also provided for the manufacture of other war material. As so modified, the original contract and these supplements constituted in effect one contract and will be [120]*120so treated in this opinion. Before the plaintiff had finished the manufacture of the war material covered by the original contract and supplements thereto the contract was terminated by a notice given by the Government. There is no controversy but that plaintiff fully carried out the contract on its part except as directed by the cancellation, notice.

The original contract with the supplements are set out in exhibits attached to plaintiff’s petition which show that the contract was of the class or kind commonly denominated “ cost-plus contracts.” In a general way it may be said that it provided for the payment to plaintiff of all manufacturing costs with a percentage of profit, and also for the payment of certain other costs and in certain cases a percentage of profit thereon. As the parties dispute over the proper construction of the contract it becomes necessary to consider the circumstances under which the contract was made as well as the wording thereof.

Prior to the beginning of the World War the plaintiff was a manufacturer on a large scale of small arms and ammunition therefor, the value of its plant being about nine or ten millions of dollars. Between November 24,1914, and August 27,1915, plaintiff entered into several contracts with the British and Russian Governments for the manufacture of military rifles and cartridges at a fixed price. The amount of these contracts in round numbers was $40,000,000.

In order to perform these large foreign contracts it was necessary to greatly increase the capacity of its plant and purchase large amounts of additional machinery. These additions to the plant were connected with the original plant as much as practicable, but some buildings were not attached to the old plant. Most of the new machinery was placed in the additional plant, but some old machinery was put in the new part and some new in the original plant.

These contracts were not profitable, and in the spring of 1916 a supplemental contract was entered into which changed these contracts to actual-cost contracts with a further provision that all rifle machinery and equipment were to be paid for and retained by the British Government. A right of cancellation was also provided. In the fall of 1916 [121]*121these contracts were canceled. Plaintiff was paid the cost of all production and for the rifle machinery — in all about $32,000,000.

The total plant expansion during this time amounted in round numbers to $8,000,000. The machinery was not moved or dismantled by the British Government, and at the end of the year 1916 the plaintiff-, had-' on hand this very large plant with machinery owned by itself and the British Government, together with skilled and unskilled labor sufficient to operate the entire plant. It owed approximately $17,000,000, one-half of which represents the cost of the plant expansion, but its original plant was adequate for its commercial work, which was about the same as it had been before it had made the foreign contracts. The plaintiff was in a position to undertake at once the manufacture of orders for arms and ammunition on a large scale, with the exception that it did not own the new.rifle machinery, which, shortly after the United States entered the World War, had been sold by the British Government to the United States. As a natural consequence of entering into the World War this Government became in need of large quantities of ammunition, and its officers were acquainted with the facilities of plaintiff’s plant and its financial standing. Plaintiff held out as an inducement of the letting of large contracts to it its facilities and readiness to commence work at once, which undoubtedly was one of the reasons for the Government entering into the contract. In short, the plaintiff had on hand a large plant for which it needed large orders, which only the defendant offered, and the Government wished to place them where they could be filled with the greatest dispatch.

The plaintiff admits that the defendant has paid all that is due it under the contract except as to two matters which constitute the issues in the case, and are as follows:

(1) The plaintiff claims that it is entitled to recover the depreciation of value which it alleges it sustained with reference to its plant and machinery used in carrying out the contract from the time when the contract was entered into up to the time when it was terminated by direction of the defendant.

[122]*122(2)Plaintiff also claims that it is entitled to 10 per cent profit on the value of the unworked material purchased either by defendant or itself for use in performing the contract.

The contentions of the defendant may be summarized as follows:

(1) That when properly construed, the contract makes no provision for payment to the plaintiff of the depreciation in value of the plant and machinery used in the performance of the contract.

(2) That the evidence fails to show the amount of such depreciation and that it does not support the claim for 10 per cent profit on the value of the unworked material.

(3) That plaintiff, by submitting its claims to certain boards appointed for the purpose of hearing them and to the Secretary of War, is bound by the decision made by such boards and the Secretary denying it any further compensation.

(4) That in any event, plaintiff, having failed to ask that its claims be heard in the manner provided by the contract, can not now obtain relief in this court.

A determination of the proper construction of the contract, as applied to the claim of the plaintiff first above set out, presents a difficult question. It will be seen that as set out above what plaintiff really seeks to recover is the loss which it alleges it has sustained in the value of its plant and machinery used in carrying out the contract. It is true that plaintiff does not state its claim in that way, either in the petition or in the argument, but calls the amount which it seeks to recover “ depreciation of value ” which is calculated by plaintiff by determining the difference between the market value of the plant and machinery used in the contract at the time the contract was entered into and at the time when, the work terminated, as shown by plaintiff’s testimony. But this can not in the final analysis mean anything else but the loss in market value during this period. Ordinarily, this would not be called “ depreciation ” but “ amortization,” and that is what plaintiff’s own witnesses call it in their testimony. In connection with [123]*123manufacturing plants and machinery, depreciation ordinarily means the diminution in value by reason of wear and tear, the effect of the elements, and other similar causes, and does not refer to market value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winchester Manufacturing Co. v. United States
75 Ct. Cl. 710 (Court of Claims, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
72 Ct. Cl. 106, 1930 U.S. Ct. Cl. LEXIS 332, 1930 WL 2510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winchester-manufacturing-co-v-united-states-cc-1930.