WIN Waste Innovations of Seneca Cty., L.L.C. v. Washington Twp. Bd. of Zoning Appeals

Ohio Court of Appeals·Decided July 27, 2026·No. 5-25-28·Published

Opinion

[Cite as WIN Waste Innovations of Seneca Cty., L.L.C. v. Washington Twp. Bd. of Zoning Appeals, 2026-Ohio-2870.]

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT

HANCOCK COUNTY

WIN WASTE INNOVATIONS OF SENECA COUNTY, LLC, CASE NO. 5-25-28

APPELLEE,

v.

BOARD OF ZONING APPEALS FOR OPINION AND WASHINGTON TOWNSHIP, JUDGMENT ENTRY HANCOCK COUNTY, OHIO,

APPELLANT.

Appeal from Hancock County Common Pleas Court Trial Court No. 2024 CV 00164

Judgment Reversed

Date of Decision: July 27, 2026

APPEARANCES:

Jeffrey M. Stopar for Appellant Steven A. Friedman for Appellee

WALDICK, J.

{¶1} Defendant-appellant, the Board of Zoning Appeals for Washington Township, Hancock County, Ohio (“the BZA”), appeals the August 18, 2025 judgment of the Hancock County Common Pleas Court entered in favor of plaintiff- appellee, WIN Waste Innovations of Seneca County, LLC (“WIN Waste”). In the judgment appealed, the trial court reversed the BZA’s denial of WIN Waste’s application for a zoning certificate to construct a pond on a piece of real property located in Washington Township. For the reasons set forth below, we reverse.

Procedural History and Relevant Facts

{¶2} On September 15, 2023, WIN Waste filed an application to build a pond, approximately 94 acres in size, on a 155-acre property located at 23990 County Road 216 in Washington Township, Hancock County. That Washington Township property is nearby a solid waste disposal facility (“the landfill”) owned and operated by WIN Waste in Seneca County. WIN Waste acknowledges that its intention in constructing the pond is to use it as a borrow pit, meaning that the company intends to export the spoils from the excavation of the pond for use as cover material at the landfill. Information presented by WIN Waste representatives at prior proceedings in this case reflects that the company anticipates taking four to five years to dig and remove all of the dirt necessary to construct the pond at issue.

{¶3} Hearings on WIN Waste’s application were held before the Washington Township Zoning Commission, and the zoning commission then denied the

issuance of the zoning certificate sought by WIN Waste in order to build the pond. On January 26, 2024, WIN Waste appealed the decision of the zoning commission to the BZA. On March 26, 2024, the BZA upheld the decision of the zoning commission.

{¶4} On April 19, 2024, WIN Waste filed an administrative appeal in the Hancock County Court of Common Pleas. In the preliminary proceedings before the trial court in the administrative appeal, it was decided that the proper procedure actually required the Washington Township Zoning Inspector to make a determination on the pond application and that any appeal from that decision should then be made to the BZA. For that reason, on October 16, 2024, the parties filed a joint motion to remand the case to the Washington Township Zoning Inspector for consideration of the pond application, and that motion was granted by the trial court on October 17, 2024.

{¶5} On remand, after review of WIN Waste’s application for a permit to build the pond, the Washington Township Zoning Inspector denied the application. That decision of the zoning inspector was then appealed by WIN Waste to the BZA.

{¶6} On January 7, 2025, the BZA held a hearing on the matter. Of particular relevance at the January 7, 2025 hearing was testimony received from one Randy Boes. Boes’ sworn statement reflected that he has operated an excavation company for over three decades. In that time, Boes has dug three to four ponds each year,

primarily in Hancock, Seneca, and Wood Counties. At the hearing, Boes testified that, based on climate statistics, the area at issue receives approximately 40 inches of rain per year, with an evaporation rate of 30 inches of rain per year. Based on those statistics and a calculation relating to a pond with approximately 90 acres of water surface area, Boes indicated that it would take 10.6 years for the pond to fill. Additionally, as the drawings submitted by WIN Waste reflected an 18-foot difference in elevation in the land surrounding the proposed pond, Boes testified, “this thing will never, ever be full, never. Because they’re not * * * building a bank down at the creek to make the pond level.” (1/7/25 Tr., 27). Boes added that, based on his experience, “ponds dug near a ditch like that – not all the time, but most of the time, - does [sic] not have suitable water holding properties. Meaning the water will move through the soil.” (Id.).

{¶7} On January 21, 2025, the BZA issued a decision upholding the zoning inspector’s denial of WIN Waste’s application for a zoning certificate to build the pond. In that January 21, 2025 decision, the BZA made the following findings in support of its denial of WIN Waste’s application to build the pond at issue:

1. The proposed pond is so large, over 90 acres, that its construction necessarily converts this use from an agricultural pond to an industrial use, which is not permitted or contemplated in the A-1 Agricultural District. There were several versions of the plans submitted as part of the packed. [sic] When the zoning inspector requested clarification on which to use, WWSC identified Doc 10 – Attachment A – WIN Pond – Detailed Set – 6.19.2024.pdf as the final set. This drawing was not approved by the Hancock Soil and Water District, and therefore cannot be a basis for an approved artificial pond or lake. The original

drawing, which was approved by the Soil and Water District suggested a recreational area, which is not permitted in the A-1 District.

2. The necessary construction activities associated with the borrow pit would be permitted and better suited for an I-2 Industrial District.

3. WWSC has not submitted a site plan as required by Article XII, Section 16, which states, “A site plan shall be submitted to the Zoning Commission for Approval for any development, except agricultural, single-family and two-family residential.” On this point, we specifically note that this issue has been raised specifically with the applicant, which has failed to submit a site plan although this application has now been pending for over one year. In addition, it is within our discretion to interpret both Article XII, Section 16 (site plans) and Article XII (Artificial Ponds or Lakes) together, so as to give both sections meaning in considering the underlying application and this appeal. We further find that nothing in Article XII, Section 20 expressly exempts ponds or lakes from the site plan requirement. The failure to submit to the site plan process is an independent basis for denying the requested permit.

4. We further find that although WWSC has at times described the proposed construction as a pond or lake, its own initial application identifies the project as a borrow area. We find that there is no dispute that the soils removed will be used as a cover for a nearby landfill. We therefore conclude that the proposed construction is not really a pond or a lake, but is, in fact, a borrow pit, and is therefore an industrial, not agricultural, use.

5. The septic systems of three houses to the immediate south of the property would drain into the proposed pond, and create health and safety issues. We specifically raised this issue with the applicant at the hearing, and the applicant declined to respond to those concerns or to offer any evidence or testimony on this point.

6. Given the difference in elevation of approximately 23 feet between the north end of the site and the south end of the site, it will take over a decade for the lake or pond to fill with water as testified by Randy Boes at the January 7, 2025 hearing. This was based on average rainfall and evaporation rates in the area. Indeed, some parts of the pond or lake will never be full due to (a) elevation issues; and (b) the

soil does not have adequate water holding property properties. [sic]

Free access — add to your briefcase to read the full text and ask questions with AI

WIN Waste Innovations of Seneca Cty., L.L.C. v. Washington Twp. Bd. of Zoning Appeals, (Ohio Ct. App. 2026).

WIN Waste Innovations of Seneca Cty., L.L.C. v. Washington Twp. Bd. of Zoning Appeals (WIN Waste Innovations of Seneca Cty., L.L.C. v. Washington Twp. Bd. of Zoning Appeals) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Straley (Slip Opinion)
2014 Ohio 2139 (Ohio Supreme Court, 2014)
ISHA, Inc. v. Risser
2013 Ohio 2149 (Ohio Court of Appeals, 2013)
In Re Aultman Hospital
608 N.E.2d 1104 (Ohio Court of Appeals, 1992)
Glass City Academy, Inc. v. City of Toledo
903 N.E.2d 1236 (Ohio Court of Appeals, 2008)
Parker v. Swan Creek Twp. Bd., Unpublished Decision (2-24-2006)
2006 Ohio 863 (Ohio Court of Appeals, 2006)
Access Ohio, L.L.C. v. Gahanna
2020 Ohio 2908 (Ohio Court of Appeals, 2020)
Lind Media Co. v. Marion Twp. Bd. of Zoning Appeals
2022 Ohio 1361 (Ohio Court of Appeals, 2022)
Dudukovich v. Lorain Metropolitan Housing Authority
389 N.E.2d 1113 (Ohio Supreme Court, 1979)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Kisil v. City of Sandusky
465 N.E.2d 848 (Ohio Supreme Court, 1984)
Henley v. City of Youngstown Board of Zoning Appeals
735 N.E.2d 433 (Ohio Supreme Court, 2000)