Wilson v. Stone Container Corp.

548 So. 2d 101, 1989 La. App. LEXIS 1512, 1989 WL 100402
CourtLouisiana Court of Appeal
DecidedAugust 23, 1989
DocketNo. 20643-CA
StatusPublished
Cited by1 cases

This text of 548 So. 2d 101 (Wilson v. Stone Container Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Stone Container Corp., 548 So. 2d 101, 1989 La. App. LEXIS 1512, 1989 WL 100402 (La. Ct. App. 1989).

Opinions

SEXTON, Judge.

The plaintiff, Lowell L. Wilson, appeals the trial court’s granting of a motion for summary judgment filed by the defendant, Stone Container Corporation (Stone). We affirm.

On October 23, 1984, the plaintiff, an employee of Combustion Engineering, Inc. (Combustion), was injured while making repairs on a C-line filtrate tank at Stone’s paper mill in Hodge, Louisiana. As the plaintiff was attempting to remove a heavy piece of metal from the tank, he slipped on an accumulation of a slippery substance referred to in the paper mill trade as “black liquor.” He fell and sustained fractures to his right hand, contusions and abrasions to his left foot, and injury to one or more discs in his lower back.

The plaintiff filed a suit for personal injuries against Stone. In its answer Stone stated that the plaintiff was its statutory employee and that his exclusive remedy was under the worker’s compensation statute.

On the day of the trial, Stone filed a motion for summary judgment. Attached to the motion were the depositions and affidavits of five managerial employees of Stone and Combustion: John Newman, Jr., superintendent of maintenance planning at Stone; Paul Hayes, the current mill engineer at Stone; Donnie Briehn, superintendent of mechanical maintenance at Stone; A1 Wise, senior project engineer at Stone; and James Dousay, project manager for Combustion.

The depositions and affidavits reveal the following. Stone shuts down the Hodge plant for a short time each year in order to do extensive maintenance and repair at the plant. The engineering department, headed by Paul Hayes, decides what major maintenance projects need to be done during a shutdown. When the projects are complex, the engineering department hires contractors to perform the work. Combustion was just one of the contractors, although a primary one, hired by Stone to do work at the mill during the 1984 shutdown. The work which was to be done by Combustion during the 1984 fall shutdown was specified in a June 1984 letter agreement. (This agreement, attached to the deposition of Mr. Hayes, was labeled Hayes # 2 and will be hereinafter referred to as such.)

This letter of agreement appears to contemplate seven items of work which are summarized in Attachment II. This attachment also delineates the work to be done on “Unit #2 Lower Sidewall” which is described as “replacement work.” Attachments B through G (there is no attachment A) further delineate the other six items of work. We note that in addition to the Unit # 2 Lower Sidewall work, two other items of work are described as “replacement work.” One item is said to be “tube repair”; one is “concrete/structural steel removal”; one is “tank inspection and post weld heat treating”; and one is “retubing.”

It should be noted that item C of the letter agreement between Combustion and Stone states that the “[tjerms and conditions governing any order resulting from this quotation will be in accordance with those previously negotiated for the ‘Hodge Super Stretch’ program....” The Hodge Super Stretch Program (or contract) was entered into between Combustion and the predecessor of Stone, Continental Forest Industry, and covered some $71 million worth of work to be performed between 1981 and 1983. The record indicates that a [103]*103term of the Super Stretch Contract of special interest to Stone with regard to the 1984 maintenance contract was that pertaining to an “orange book agreement,” an agreement between the contractor and the union under which the union worked at reduced rates. There are other general terms which were obviously of interest to both parties to the 1984 agreement such as “Article 5.0 Final Payment,” “Article 7.0 Mutual Compliance,” and “Article 9.0 General” (this article dealt with such things as compliance with applicable codes, the requirement that the work be done in a workmanlike manner and the requirement that the contractor’s employees perform harmoniously with the workmen of other contractors and with those in the plant).

The maintenance planning department headed by Mr. Newman scheduled each job that was to be done during the 1984 shutdown and assigned workers to each job. The planning department scheduled an inspection of the filtrate tank involved in the accident. Stone’s mechanical maintenance department assigned two millwrights and a welder to inspect and perform minor repairs on the tank. However, the inspection revealed a greater degree of deterioration than Stone had anticipated as part of the baffle in the tank had corroded.

The tank itself is a holding tank which allows the liquor, a useful by-product, to settle out. The baffle is a metal device, either a cylinder or a flat plate, which controls the flow of the liquid through the tank. To repair a baffle, the worker cuts the deteriorated portion off of the baffle and welds a new piece of metal onto the baffle. Because it had not allocated sufficient manpower and hours for work on the tank, the planning department referred the job to the engineering department to in turn assign it to a contractor.

An authorization request, Stone # 1, was issued to request funding for the work. The repairs to the tank were then contracted to Combustion by means of a purchase order. The authorization request lists the project title as the “C Line Filtrate Tank Repairs” and gives an estimated cost of $50,000. The authorization request also states the following: “This project is an addition to the 1984 Major Maintenance Program and can be completed within budgeted funds.” The purchase order lists the cost of the baffle repairs in the C line tanks as $14,800. Mr. Hayes accounted for the large difference between the estimated cost and the actual purchase order cost for the baffle repair by explaining that several other projects besides the repairs covered by the purchase order were charged against the authorization request.

Hayes stated that when the need for additional work becomes known during a shutdown, Stone frequently adds additional employees. He also stated that, on the other hand, Stone may ask a maintenance contractor already performing work during the shutdown to extend the scope of its work to include the additional work.

The work that the plaintiff was doing was not specialized. Stone had approximately 100 employees who could have done this particular job. Stone employees had also done this type of work before. In fact, during the shutdown, Stone employees were performing similar work in other parts of the mill. During normal operations, a Stone employee did metal work on a tank at least once a week.

In his affidavit, James Dousay, the project manager for Combustion, stated that the purchase order formed no part of the general contract for the shutdown. The work was additional work requested by Stone due to Stone’s manpower shortage. In addition, Stone’s employees routinely do this type of maintenance and repair on a daily basis. A1 Wise, the senior project engineer at Stone, also stated that Stone’s employees normally do the type of work that the plaintiff was doing.

The trial court granted the motion for summary judgment. In oral reasons for judgment, the trial court found that “the plaintiff was not performing work under the super stretch contract, but rather under another agreement between defendant and CE” (Combustion Engineering). The court also found that “the work contract whose scope must be considered is the separate agreement to do repairs on the [104]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. Stone Container Corp.
552 So. 2d 395 (Supreme Court of Louisiana, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
548 So. 2d 101, 1989 La. App. LEXIS 1512, 1989 WL 100402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-stone-container-corp-lactapp-1989.