Wilson v. State

9 Ill. Ct. Cl. 443, 1937 Ill. Ct. Cl. LEXIS 121
Court of Claims of Illinois·Decided April 14, 1937·No. No. 1731·Published

Opinion

Mb. Justice Yantis

delivered the opinion of the court:

The complaint herein recites that in September, 1927 respondent gave notice that it would receive proposals and bids for the construction of certain sections of highway known as Section 123-B of Boute No. 122 in Mason County, District No. 6, being one B. C. slab bridge and two B. C. sub-structures for a bridge to be constructed in accordance with the requirements of the standard specifications for road and bridge construction, and according to plans on file in the office of the Division of Highways, Springfield, Illinois; that claimant obtained the plans for the construction of said bridges and in reliance thereon filed their proposal and bid for the work on said three bridge jobs for a consideration of Twenty One Thousand Fifty Four and 18/100 ($21,054.18) Dollars; that such bid was accepted and claimants entered upon the construction of said work, but that due" to the existence of quick sand which was not disclosed in the notice of letting and due further to a variance between the actual elevation of the bed of the stream and the elevation set out in the plans, claimants allege they were misled in submitting the proposal and bid and that they incurred an increased expense in the performance of the contract, amounting to Thirty Five thousand Six Hundred Thirty Six and 03/100 ($35,636.03) Dollars, for which they now seek an award.

Both Bobert O. Wilson and Gr. B. Bichardson, who constitute the co-partnership now seeking this award, are former employees of the State Highway Department of the State of Illinois. Mr. Wilson was an Assistant Highway Engineer for more than a period of five years prior to May 1, 1927. Mr. Bichardson was employed in the Division of Highways of the State for four years, and at the time he left the employ of the State was District Engineer of Designs, and prior to that time was Division Engineer on Construction.

Plaintiffs complain that they were misled in bidding on the bridge work in question, because the State did not disclose to them in its original notice to the contractors that quicksand might be encountered in the construction work in question, and that the Highway Department had knowledge of such condition at the time of the acceptance of proposals for such work. The record discloses that the Highway Department did possess some information in regard to the character of the soil at the proposed bridge locations, and that such information was available to anyone who desired to submit a bid for the work to be done. Claimants’ Exhibit 3, being its proposal for the work in question in Section 6 on page 4 recites that, “He (the bidder) has carefully examined the location of the proposed work, the plans, specifications, etc., etc.” In Section 8 of the proposal it is stated that, “The undersigned declares that he understands that the quantities are approximate only and that they are subject to increase or decrease, etc.” In the standard specifications for road and bridge construction, being a part of Claimant’s Exhibit 3, it is stated in Paragraph 1, page 5, “The bidder should make a careful examination of the site of the proposed work, the proposal, plans, specifications and contract form before submitting a proposal. He should fully inform himself as to the quality and quantity of materials required and the character of the work, and he should further investigate the location and make a careful examination of the source of supply for materials. The bidder will be held responsible for his failure or neglect to observe or comply with these instructions.” It is further stated, in Paragraph 2, “The Department does not guarantee that the estimated quantities given shall obtain strictly. * * In Section 3, “The proposal will state any special provisions or requirements which vary from or which are not contained in these specifications.” Under Section 38 of General Provisions of the Standard Specifications, it is stated, “The contractor shall receive and accept the compensation herein provided in full payment for furnishing all materials, labor, tools and equipment; for performing all work contemplated and embraced under the contract; for all loss or damage arising out of the nature of the work or from the action of the elements; for any unforeseen difficulties or obstructions which may arise or be encountered during the prosecution of the work * * *; for all risks of every description connected with the prosecution of the work.” It is further stated in Section 41 of such General Provisions, “The acceptance by the contractor of the last payment shall operate as and shall be a release to the Department from all claims or liability under this contract for anything done or furnished or relating to the work under this contract, or for any act or neglect of said Department relating to or connected with this contract. ’ ’

From the testimony it appears that soon after claimants began the construction work in question they encountered quicksand. They first began the use of wood-sheeting for the construction of coffer-dams, and later were compelled to abandon same and to construct a steel-sheet piling cofferdam. A substantial loss of time in the construction work resulted from this, but Lewis A. Lush, one of the State Engineers, testified that he had a conversation with claimant Wilson in November, 1927 at the site of the East bridge when the excavation work was first begun. He states that the contractors were then excavating with teams and that the cofferdam material was not yet on the job; that he at that time informed Mr. Wilson they would probably encounter quicksand; that notwithstanding this knowledge, claimants attempted to use wooden coffer-dams and did not abandon their efforts to use such material until between the 16th and 23rd of February, 1928. Both the claimants, as above stated, had been employed in the Highway Department of the State for a number of years. There is no apparent reason why they could not have obtained all the information they may have desired, as to the nature and character of the work for which they proposed to bid. The proposal and specifications attached made it their duty to inform themselves as to such details, if they desired to bid on the job.

The evidence is conflicting as to the variance between the specifications and the actual construction work required, with reference to the elevation of the bed of the stream. Claimants contend that after they arrived on the job they learned that the Drainage District contemplated lowering the existing bed of the stream grades approximately four (4) feet at the points of the bridges, but that this work had not been completed; that claimants were not required to remove additional excavation from the stream bed itself; but that they were required to remove additional excavation in order to go to the required depth for the bridge abutments, (Record p. 37.)

W. L. Esmond, an Assistant Engineer for the State Highway Department, testified that he was one of the Engineers assigned to the supervision of the construction of the three bridges in question, and was in regular attendance at the location of same; that a revision was made in the plans and specifications after the Mid-West Construction Company began its work, and that by such revision, the footings for abutments on the East bridge were raised about one and one-half (1%) feet; that no material change was made on the plans for the middle bridge and that the plans were changed on the west bridge so as to raise the depth of the footings approximately two (2) feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Wilson v. State, 9 Ill. Ct. Cl. 443, 1937 Ill. Ct. Cl. LEXIS 121 (Ill. Super. Ct. 1937).

9 Ill. Ct. Cl. 443 (Wilson v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.