Wilson v. Rahman

22 So. 3d 178, 2008 La.App. 4 Cir. 1511, 2009 La. App. LEXIS 1565, 2009 WL 2573989
CourtLouisiana Court of Appeal
DecidedAugust 20, 2009
Docket2008-CA-1511
StatusPublished
Cited by1 cases

This text of 22 So. 3d 178 (Wilson v. Rahman) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Rahman, 22 So. 3d 178, 2008 La.App. 4 Cir. 1511, 2009 La. App. LEXIS 1565, 2009 WL 2573989 (La. Ct. App. 2009).

Opinion

JOAN BERNARD ARMSTRONG, Chief Judge.

| 'The plaintiff-appellant in the main demand and defendant-appellee in reconvention, Eulister Wilson, appeals pro se a judgment rendered by the First City Court of the City of New Orleans on September 11, 2008, dismissing his claim with prejudice against the defendant-appellee in the main demand and plaintiff-appellee in reconvention, Irshad Daniel Rahman. Mr. Rahman in turn appeals the dismissal in the same judgment of his reconventional demand against Mr. Wilson.

This is a fact intensive case involving no significant legal issues. Therefore, our review essentially consists of reviewing the record as a whole to determine whether the trial judge committed manifest error in reaching the conclusions he reached.

Mr. Wilson filed suit on June 20, 2007, claiming that Mr. Rahman owed him $25,000.00 for construction work he allegedly performed on properties owned by Mr. Rahman located at 4121 Fountainbleu Drive and 5420 Clara Street in New Orleans. On November 28, 2007, Mr. Rah-man filed an- answer and reconventional demand based on theories of breach of contract and constructive abandonment and asking for unspecified damages for:

|21) Cost to repair substandard work;
2) Cost to complete work left uncompleted;
3) Loss of rent;
4) Any and all other damages.

In his written reasons for judgment issued contemporaneously with the judgment, the trial judge dismissed both parties’ claims, finding that Mr. Wilson did *180 not complete the job timely and Mr. Rah-man was in part responsible for the delay because he pulled Mr. Wilson off of one job to have him work on another unrelated job. The trial judge further found that Mr. Wilson did not perform all the work he performed in a workman like manner and that he failed to supervise or hire someone to supervise his employees or subcontractors. The trial judge also found that Mr. Wilson hired people who were not qualified or who failed to perform the work they were hired to do, specifically the electrical, plumbing and sheet rock contractors.

In addition to ruling against Mr. Rah-man’s claim in reconvention because he pulled Mr. Wilson off of the jobs for which he had contracted to work on another job, the trial judge also found that Mr. Rahman was not entitled to some of the damages he claimed. Those damages were claimed by Mr. Rahman in connection with payments he was allegedly forced to make to other contractors he hired to correct and finish the work he hired Wilson to do. However, the trial judge found that some of what Mr. Rahman claimed in this regard was not for work that Mr. Wilson had contracted to do.

All of these are factual findings subject to manifest error of review.

The trial on the merits commenced on July 31, 2008. Eulister Wilson was the first to testify. He testified that in March of 2006 he entered into a written |3agreement with Mr. Rahman to do work on his 4131 Fountainbleu Drive property in the sum of $66,641. This contract is dated March 15, 2006. While Mr. Wilson filed suit in his name and that of his limited liability corporation, E & S Construction, Mr. Eulister is not shown as a party to the contract; only his limited liability corporation, E & S Construction, L.L.C. is. The contract provided for payment as follows:

Upfront materials deposit of $18,247.00 and 3 progressive payments of $13,917.00 leaving a retainage balance of $6,643.14 to be collected at completion of project.

The contract stated an estimated time of completion of 90 days and the contract provided that the “term of this Agreement will begin on the date of this Agreement and will remain in full force and effect until completion of the Services.” Paragraph “9” of the Agreement is entitled in boldface “Time of the Essence ” and, as indicated in the title, provides that time is of the essence and that: “No extension or variation of this Agreement will operate as a waiver of this provision.” Although Paragraph “5” of the Agreement is given the boldface title, “Non Performance Penalties ” the contract is silent as to penalties. Annexed to the contract in evidence is an “Invoice/Proposal” along with a detailed listing and cost of each item of work to be performed under the contract. However, the issue is not so much a dispute over the meaning and scope of the contract, but the quality, quantity and timeliness of the work performed by Mr. Wilson.

Mr. Wilson testified that because of post-Katrina issues there was no electrician available between March 3, 2006 and April 14, 2006. He testified that Mr. Rah-man had an electrician he wanted to use, but that he never showed up. He testified that workmen hired by Mr. Rahman cut out all of the wood flooring and |4left nothing but joists, requiring him to give Mr. Rahman a price on redecking the floor and the stairwell for the back of the house, thereby creating a change.

Mr. Wilson then testified that on April 14, 2006, Mr. Rahman, pulled him off the job to work on his brother’s house. As a result he worked on both Mr. Rahman’s house and that of his brother between April 14, 2006 and September 29, 2006.

*181 Mr. Wilson testified that on May 4, 2006, Mr. Rahman put in the first change order which was in writing and entitled, “Change Order # 1.” He also testified that Mr. Rah-man decided to have central air instead of window units, thus requiring a change in wiring which in turn required a change in the panel boxes.

Mr. Wilson then testified that on May 15, 2006, Mr. Rahman pulled him off of the job again, this time to work on property he owned at 5422 Clara Street. At the same time Mr. Rahman had him doing roofing work at 7635 Freret Street.

Mr. Wilson testified that Clara Street had galvanized pipes that needed to be replaced at considerable expense. Mr. Rahman’s indecision concerning the cost resulted in delay.

Mr. Wilson testified that on July 25, 2006, Mr. Rahman issued a change order calling for “major changes” regarding the Fountainbleu property. The record contains a substantial written change order of that date signed by both parties. He testified that at this time he went to his home in North Carolina to work on the new proposal. He testified that he returned to New Orleans a week later with the change order, but that Mr. Rahman put off signing it until August 23. He testified that he did not proceed with the work during the period of time he was waiting for Mr. Rahman to sign the change order. During the period of time during which he | ¿waited for Mr. Rahman to sign the change order he worked on Mr. Rahman’s brother’s house.

Mr. Wilson testified that before he could even get started on the change order dated July 25, 2006 referred to in the preceding paragraph, Mr. Rahman asked for another change order for the work to be done on the Fountainbleu property. A copy of the written change order is in the record signed by both parties.

Next, Mr. Wilson testified that on September 13, 2006, Mr. Rahman called him with instructions that now he wanted him to complete the work he was doing on the Clara Street property. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Radcliffe 10, L.L.C. v. Zip Tube Systems of Louisiana, Inc.
22 So. 3d 178 (Louisiana Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
22 So. 3d 178, 2008 La.App. 4 Cir. 1511, 2009 La. App. LEXIS 1565, 2009 WL 2573989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-rahman-lactapp-2009.