Wilson v. Public Service Commission

89 Pa. Super. 352, 1926 Pa. Super. LEXIS 71
CourtSuperior Court of Pennsylvania
DecidedOctober 12, 1926
DocketAppeal 17
StatusPublished
Cited by13 cases

This text of 89 Pa. Super. 352 (Wilson v. Public Service Commission) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Public Service Commission, 89 Pa. Super. 352, 1926 Pa. Super. LEXIS 71 (Pa. Ct. App. 1926).

Opinion

Opinion by

Cunningham, J.,

Appellant is the owner of a tract of land situate in the 35th Ward of the City of Philadelphia, approximately 800 by 3,498 feet, and containing about fifty-six acres. The intervening appellee, The Philadelphia Electric Company (hereinafter referred to as the company), was incorporated October 27, 1902, under the Act of April 29,1874, P. L. 73, and its supplements, *355 and more particularly under the Act of May 8, 1889, P. L. 136, for the purpose of supplying heat, light and power by electricity to consumers residing in or adjacent to the City and County of Philadelphia, etc. Having undertaken the construction of a 66,000 voltage transmission line on steel towers from a substation at Luzerne and G Streets in the 33rd Ward of said city through the northeastern section thereof to the Bucks County line, and being desirous of securing a right-of-way for said line across the property of appellant, with whom it was unable to agree upon compensation for the damages which would be sustained, the company instituted appropriate proceedings before the Public Service Commission of this Commonwealth for the purpose of obtaining the approval of the Commission of the exercise by it of the right conferred upon it by the Act of May 21, 1921, P. L. 1057, to appropriate private property for, inter alia, the erection of facilities for the transmission or distribution of electric power. By this act it is provided that before any such company shall exercise such powers the Commission “upon application of such company shall have found and determined, after public hearing, that the service to be furnished by said company through the exercise of said power is necessary or proper for the service, accommodation, convenience or safety of the public.” Accordingly, on October 16, 1925, the company presented to the Commission its petition, after-wards amended by permission, setting forth in substance that it is constructing the above mentioned transmission line on a private right-of-way (therein minutely described) for the purpose of “supplying and furnishing light, heat and power, or any of them, by means of electricity to the public in the City and County of Philadelphia and particularly the section thereof lying northeastwardly of said Luzerne Street and in the 35th Ward thereof, including Bustleton, *356 Somerton, Byberry and intervening territory, and also for the purpose of supplying and furnishing the same to the public in territory adjacent to said City and County, to wit, in Bucks and Montgomery Counties, by supply of electric energy to Philadelphia Suburban Gas & Electric Company, which supplies the same directly to its customers in said other counties, adjacent to the City 'and County of Philadelphia.” The petition contains the usual averments relative to the ownership by appellant of the tract over which it desires to secure a right-of-way, the inability of the company to reach any agreement with him, and the public necessity for the construction of the line.

Appellant protested the granting of said certificate but after a public hearing the Commission under date of November 16, 192'5, filed its report and order, in which it stated that it had found, from the evidence ■adduced, that the construction of the proposed line “will manifestly improve” the service of the company and that the service to be furnished through its proposed exercise of the right of eminent domain is necessary and proper for the service and convenience of the public and accordingly granted an appropriate certificate. Prom the order thus granted appellant took this appeal. During its pendency the company presented a petition setting forth that at his offices on December 24, 1925, it had tendered to the attorney who represented appellant before the Commission and who took the appeal the bond of the company, with a corporate surety, conditioned for the payment of such damages as appellant should be entitled to receive after the same had been agreed upon or assessed as provided by law, which bond had been accepted by the attorney in behalf of appellant, and praying for a rule to show cause why the appeal should not be quashed because the questions involved had, by reason of such acceptance, become academic and *357 because appellant was no longer -affected by tbe order appealed from. Upon this petition a rule was granted returnable October 1, 1926, to which appellant filed an answer, and we directed that the questions arising under the rule -and answer should be argued at the same time argument was heard upon the merits of the appeal. For reasons hereinafter stated we now discharge this rule and proceed to a consideration of the appeal upon its merits.

At the argument the assignments of error alleging that the proceedings had been instituted without proper corporate action were withdrawn. The remaining assignments charge error on the part of the Commission: (a) in not requiring the company to prove that it had municipal consent to enter on the streets of the city for the construction of the transmission line; (b) in failing properly to describe in its order the premises thereby affected.

1. At the hearing the learned counsel for -appellant sought to raise the question whether the company had obtained consent of the city to cross public streets with the high tension line in question. It was objected that this amounted to a collateral attack upon the franchises of the company and that the question was not material to the issue before the Commission, which objection was sustained by the sitting Commissioners. Subsequent to the hearing there was filed with the Commission a copy of the charter of the company and of a franchise-ordinance granted to it by the City of Philadelphia on December 26, 1902. This ordinance authorized the company to enter upon and use the streets and alleys of the city for the purpose, inter alia, of constructing and operating “underground conduits, erecting poles and wires overhead,” etc., for the purpose of furnishing electric service “to the public and to private individuals and corporations in and throughout the City of Philadelphia.” It is argued *358 in behalf of appellant that there was no evidence before the Commission that the city had given its consent to the erection of the present line for the purpose of supplying service “outside of the City of Philadelphia.” It does not appear that there are any opened streets on appellant’s property and the City of Philadelphia was not a protestant against the granting of the application. We prefer, however, to base our disposition of this matter upon a broader ground than the absence or remoteness of the interest of appellant in the question he endeavors to raise.

When the jurisdiction of the Commission, as an administrative body, and the scope and effect of its order in a proceeding of this kind are properly considered it is clear the Commission was right in declining to consider and construe this ordinance in disposing of the application then before it. Manifestly the order of the Commission does not confer the right of eminent domain upon an applicant company. That right is conferred upon it as an additional. right and power by the Act of 1921, supra; but such power may not be exercised until the Commission shall have determined that there is a public necessity for the service to be rendered through its exercise. We said in Reiber v. Commission, 83 Pa. Superior Ct. 507, and in Hege v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kearns v. Pennsylvania Public Utility Commission
191 A.2d 700 (Superior Court of Pennsylvania, 1963)
West Penn Power Co. v. Pennsylvania Public Utility Commission
184 A.2d 143 (Superior Court of Pennsylvania, 1962)
Lower Chichester Township v. Pennsylvania Public Utility Commission
180 Pa. Super. 503 (Superior Court of Pennsylvania, 1956)
Duquesne Light Co. v. Upper St. Clair Township
377 Pa. 323 (Supreme Court of Pennsylvania, 1954)
Borough v. Pennsylvania Public Utility Commission
15 A.2d 547 (Superior Court of Pennsylvania, 1940)
Pittsburgh Railways Co. v. P. S. C.
174 A. 670 (Superior Court of Pennsylvania, 1934)
Commonwealth v. Keystone Pipe Line Co.
24 Pa. D. & C. 400 (Dauphin County Court of Common Pleas, 1934)
State Upon the Information of Shartel v. Missouri Utilities Co.
53 S.W.2d 394 (Supreme Court of Missouri, 1932)
Dickel v. Bucks-Falls Electric Co.
160 A. 115 (Supreme Court of Pennsylvania, 1932)
Boland v. Public Service Commission & Abington Electric Co.
101 Pa. Super. 102 (Superior Court of Pennsylvania, 1930)
Harrisburg Light & Power Co. v. Sebastian
11 Pa. D. & C. 30 (Lebanon County Court of Common Pleas, 1927)
Westside Electric Street Railway Co. v. Public Service Commission
91 Pa. Super. 162 (Superior Court of Pennsylvania, 1927)
Westside Elec. St. R.R. Co. v. P.S.C.
91 Pa. Super. 162 (Superior Court of Pennsylvania, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
89 Pa. Super. 352, 1926 Pa. Super. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-public-service-commission-pasuperct-1926.