Willner v. Wallinder Sash & Door Co.

28 N.W.2d 682, 224 Minn. 361, 1947 Minn. LEXIS 542
CourtSupreme Court of Minnesota
DecidedJuly 18, 1947
DocketNo. 34,392.
StatusPublished
Cited by8 cases

This text of 28 N.W.2d 682 (Willner v. Wallinder Sash & Door Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willner v. Wallinder Sash & Door Co., 28 N.W.2d 682, 224 Minn. 361, 1947 Minn. LEXIS 542 (Mich. 1947).

Opinion

Julius J. Olson, Justice.

This was an action to foreclose a mechanic’s lien upon certain real estate belonging to the corporate defendant. The issues to be determined here are limited to the respective claims and denials of plaintiff and the corporate defendant. The complaint is in the usual and standard form in mechanics’ lien cases. Defendant answered, setting forth in substance that an agreement had been made between it and plaintiff whereby plaintiff was to construct an addition to defendant’s manufacturing plant. Plaintiff was to furnish the labor and equipment to do the job, and defendant was to furnish the material. Plaintiff’s compensation was to be upon a cost-plus percentage basis. By its separate pleading, defendant also counterclaimed for damages amounting to $165,500, which has for its basis the claim that plaintiff negligently started a fire during the performance of his work and that he negligently permitted the fire so started to spread, thereby destroying defendant’s entire plant, including the work then partly performed by him under his construction contract. Plaintiff replied, denying all new matter, averred that defendant was contributorily negligent in its effort to put out the fire, and that its efforts in this respect were so negligently performed as to cause, in large part at least, the loss sustained.

*363 At the commencement of the trial, counsel stated that, while this was an action which would ordinarily he tried to the court without a jury, arrangements by counsel had been made to submit certain questions to the jury. The questions submitted and the answers thereto were as follows:

1. “Did the fire start as a result of any negligence of Mr. Willner or a member or members of the Willner crew?” The jury’s answer was “Yes.”

2. “Was the fire permitted to spread as a result of any negligence of Mr. Willner or a member or members of the Willner crew?” The jury’s answer was “No.”

3. “Was there any negligence on the part of Wallinder Sash & Door Co. or a member or members of its crew which contributed to the starting of the fire?” This question was answered by the court “No” as a matter of law.

á. “Was there any negligence on the part of the Wallinder Sash & Door Co. or a member or members of its crew which contributed to the spreading of the fire?” The jury’s answer was “Yes.”

In this connection, Mr. Boyle, of counsel for defendant, stated for the record:

“I think it was clearly understood by counsel that the question of independent contractor, or of employer and employee would be reserved for decision by the court, and the jury would be merely asked to decide the questions which I have read into the record. I don’t know if there is anything to be added to that statement. The question of proximate cause is to be determined by the court.

“The Court: I understand it is for the jury to decide these questions alone?

“Mr. Boyle: Yes, the relationship of independent contractor and employer and employee and other questions are to be determined by the court afterwards.”

No one questioned Mr. Boyle’s statement. Thereupon and within the agreed limits, the trial proceeded. The resulting special verdicts have been recited.

*364 There had been pre-trial conferences between counsel and the court. As a result of these, the jury issues were framed. The issues raised by defendant’s counterclaim were to be first determined, and thereafter all other issues were to be tried to and disposed of by the court.

After the jury trial had been concluded and the special verdicts rendered, the court, on defendant’s motion, vacated the jury’s negative answer to the second question and substituted its own affirmative answer. It did the same thing with respect to the fourth question, substituting its own negative answer in place of the jury’s affirmative finding.

When the court trial had been concluded, the court made findings adverse to plaintiff’s theory as to defendant’s liability, awarding, instead, $64,500 to defendant as damages under its counterclaim. After the usual motions had been made for amended findings or a new trial, judgment was entered in conformity with the findings, and it is from this judgment that plaintiff has appealed.

A brief résumé should be made of these findings. During the times herein material, defendant owned and operated upon its premises, the subject matter of plaintiff’s action, a manufacturing plant. The controversy before the trial court and here arises out of and by reason of plaintiff’s negligence in the performance of his contract, entered into between the parties on October 17, 1944, under the terms of which plaintiff agreed to construct for defendant an addition to its then functioning factory. For some time prior to the making of this contract, defendant had been engaged in the manufacture of army airplane cargo-loading bins, army tread ways and display fixtures, and other products. It had in its factory the machinery, equipment, tools, and materials necessary for the manufacture of the articles mentioned. In the construction job undertaken by plaintiff for the building of an addition to defendant’s factory, plaintiff had full authority over the details and manner of performance of the work and the means and methods to be observed in the conduct thereof. Defendant had no such authority, nor did it attempt to exercise any such authority. While plaintiff was engaged in con *365 structing the addition, defendant actively continued the operation of its old factory, wherein it manufactured the various things to which we have already referred. Its work was largely what is termed war work. On December 15, one of plaintiff’s men, in doing his employer’s work, negligently caused a. fire in that portion of the structure then being built. Plaintiff and his crew negligently permitted the fire to spread so that the entire factory, both the old and new, together with the machinery, fixtures, and other property therein located, was wholly destroyed. The court, moreover, specifically found that the fire which destroyed defendant’s factory and other property did not start as a result of any negligence on defendant’s part; that the fire was not permitted to spread as the result of any negligence on the part of defendant or any of its employes, but, on the contrary, that “as a direct result” of plaintiff’s negligence “in the starting of said fire and in permitting said fire to spread and destroy said factory and personal property, the defendant has been damaged in the sum of $61,500.” Upon these facts, the court directed the entry of judgment that plaintiff had no cause of action under his lien, and that defendant was entitled to the damages mentioned.

Considerable time and testimony was devoted to the question of whether the relationship between plaintiff and defendant was that of master and servant. In its memorandum, the court expressed the opinion that plaintiff retained control over the new construction, not only as to what should be done, but also as to the method and manner of doing it, and that plaintiff himself apparently was of the opinion that he was an independent contractor, since he applied for a permit to construct the building, his application having been made by him personally and not as an agent or servant of anyone.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wild v. Rarig
234 N.W.2d 775 (Supreme Court of Minnesota, 1975)
Larson v. Montpetit
147 N.W.2d 580 (Supreme Court of Minnesota, 1966)
Pluwak v. Lindberg
130 N.W.2d 134 (Supreme Court of Minnesota, 1964)
Peter Buchanan v. United States
305 F.2d 738 (Eighth Circuit, 1962)
Nicholas v. Hennepin Wheel Goods Co.
58 N.W.2d 572 (Supreme Court of Minnesota, 1953)
Schenstrom v. Continental Machines, Inc.
85 F. Supp. 374 (D. Minnesota, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
28 N.W.2d 682, 224 Minn. 361, 1947 Minn. LEXIS 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willner-v-wallinder-sash-door-co-minn-1947.