Williamson v. Powell

140 S.W. 359, 1911 Tex. App. LEXIS 310
CourtCourt of Appeals of Texas
DecidedOctober 11, 1911
StatusPublished
Cited by6 cases

This text of 140 S.W. 359 (Williamson v. Powell) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williamson v. Powell, 140 S.W. 359, 1911 Tex. App. LEXIS 310 (Tex. Ct. App. 1911).

Opinion

JAMES, C. J.

The parties herein, on November 28, 1908, made a contract, by which Powell agreed 'to make two wells for Williamson for the price of $2 per foot, the wells “to be made to a depth of 550 feet or to the second stratum of the artesian water, with 12-inch casing, and the balance of the depth tq be made with an 8-inch easing, is to be commenced not later than the 5th of December, 1908, and to be done in a good workmanlike manner and pushed to completion by party of the second part,” and further “to furnish his own fuel oil and to haul same and build derricks and to guarantee "these wells to be equal to the average of the surrounding wells.”

Williamson agreed “to furnish all material needed in the construction of said wells, ■ su.ch as all necessary casing, screenings and material for one derrick for each well and to do the hauling of all machinery and materials necessary for the completion of the work.” It was further agreed that Williamson “is to advance to the party of the second part $500.00 which is to be credited on the first well, and when the first well is completed the party of the first part is to pay the party of the second part $2.00 per foot for said well without delay.”

Appellee Powell brought this action, alleging the contract, and alleging in substance that defendant failed to haul plaintiff’s machinery and apparatus to the site of the first wells to be bored, and that plaintiff was compelled to do so at the expense of $50, completing said hauling on December 13, 1908, and on.January 7, 1909, he completed the first well to the depth of 521 feet to the artesian stratum, and was then ready and anxious to place the easing therein and complete the well for washing and testing; that, though under the contract the casing should have been on the ground, in order for it to be rushed to completion and to protect the well from caving, defendant failed to have it there when so needed, whereby plaintiff was compelled to suspend operations and permit said well to remain uncased, and to hold his crew and machinery idle for 27 working days and until about February 10, 1909, waiting for the casing, and causing great additional damage and loss of time by the caving in of said well, to plaintiff’s damage, $675; that on March 25, 1909, when said well was ready for the washing and placing of the pit and pump therein, and a Lane & Bowler interlocking steel pit and pump had been placed upon the ground, to be placed in said well, and the use of the same would have permitted the sinking of the well to any depth desired by defendant, defendant refused to permit said pit and pump to be used, and thereafter, after plaintiff being thus caused a delay of three days at an expense of $75, defendant delivered for use in said well a Gray pump in lieu thereof; that on April 3, 1909, plaintiff completed said well in accordance with the terms of the contract, and placed the Gray pit and pump therein, and pumped and tested said well, and proved an exceptionally good well, and defendant thereupon received and accepted said well, and promised to pay plaintiff therefor, and, then and there discharged plaintiff from all further obligation to sink the second well, and promised to pay plaintiff $2 per foot for the 521 feet, the depth of said well, less the sum of $500 advanced, leaving a balance of $542 of the contract price.

The petition claimed damages for the said sums of $542, $75, $675, $5, and the further sum of $150, for the sinking and setting of the Gray pit and pump, which defendant promised to pay, and which was a reasonable charge therefor, making in all $1,492. Certain persons joined the plaintiff as interven-ers.

The defenses need not be stated, unless it may be necessary to do so in passing on the assignments of error. There was a verdict for plaintiff for $542, balance of the contract price, $270 for 27 days delay in waiting for *361 materials, and $76 for three days holding the crew waiting for the pit and pump.

[1] The first assignment of error is multifarious, and its consideration cannot be expected under the rules.

We overrule the third assignment of error; to sustain it would be to hold that a party has to plead his evidence.

[2] The fourth assignment is as follows: “The court erred in permitting Powell to testify as to the damages sustained by him in having to wait 27 days for casing and screens, because the contract did not obligate defendant to have said material on the ground at any particular time.” Appellant’s proposition is that, where time is not of the essence of a contract, the law allows a reasonable time for performance. Tested by this proposition, the court committed no error in the ruling. If, as contended, defendant had a reasonable time in which to furnish the casing and screens after needed for the prosecution of the work, there still was no error in admitting the testimony, because the question of reasonable time would be matter for the jury to consider in connection with the evidence.

[3-5] The eighth assignment complains of the following charge: “If you believe that plaintiffs got the well ready for the casing, and that defendant failed to provide it when needed, and that plaintiffs were compelled to hold their crew and machinery idle, waiting for the delivery of such easing, to their injury, then plaintiffs would be entitled to recover from defendant such sums as will compensate them for the wages and board of the crew and the reasonable value of the machinery compelled thereby to remain idle, while the same was idle.” The objections to this charge cannot be considered by this court beyond what are specified in the propositions. The propositions are: First. “A party cannot recover special damages for breach of contract, unless his adversary had notice, at the time of its execution, of the loss that might be expected from its breach.” The charge is not subject to such objection. Defendant by his contract obligated himself to furnish the casing for the work, and must have anticipated that his default in that respect would delay the progress of the work and cause plaintiff damage in the suspension of the work. The second proposition is that: “It is the duty of a party claiming damages to use diligence to minimize his loss.” If the testimony raised such an issue, defendant should have requested a charge thereon in connection with the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grant v. Grant
190 S.W. 229 (Court of Appeals of Texas, 1916)
Glover v. Houston Belt & Terminal Ry. Co.
163 S.W. 1063 (Court of Appeals of Texas, 1914)
Freeman v. McElroy
149 S.W. 428 (Court of Appeals of Texas, 1912)
Hayes v. Groesbeck
146 S.W. 327 (Court of Appeals of Texas, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
140 S.W. 359, 1911 Tex. App. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williamson-v-powell-texapp-1911.