Williams v. Tidex International, Inc.

674 F. Supp. 548, 1987 U.S. Dist. LEXIS 9170, 1987 WL 23386
CourtDistrict Court, E.D. Louisiana
DecidedSeptember 30, 1987
DocketCiv. A. No. 85-4061
StatusPublished

This text of 674 F. Supp. 548 (Williams v. Tidex International, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Tidex International, Inc., 674 F. Supp. 548, 1987 U.S. Dist. LEXIS 9170, 1987 WL 23386 (E.D. La. 1987).

Opinion

MEMORANDUM OPINION

MENTZ, District Judge.

The Court has before it the motion of the plaintiff, Michael Williams, for a new trial (which is actually a motion for reconsideration of this Court’s order granting the defendant’s motion for summary judgment). Three issues had been presented on the motion for summary judgment, and the Court ruled in favor of the defendant on all of these issues. Presented for review were (1) the extent to which plaintiff was entitled to wages, (2) whether the plaintiff was entitled to double wages, and (3) whether the plaintiff was entitled to punitive damages for failure to pay maintenance and cure.

The Court’s holding was based in part on the holding of Judge A.J. McNamara of this district in the case of Dowdle v. Offshore Express. The Court found the rationale and analysis therein to be sound and convincing, and followed the reasoning of Judge McNamara. However, subsequent to this Court’s granting defendant’s motion, the Court of Appeal reversed Judge McNamara’s ruling. Dowdle v. Offshore Express, 809 F.2d 259 (5th Cir.1987). The plaintiff has consequently moved for reconsideration of this Court’s ruling on all issues. Although the defendant has valiantly attempted to distinguish Dowdle, the Court is compelled to VACATE IN PART the summary judgment. However, the Court affirms its earlier ruling on the other issues, and supplies reasons more thorough than those rendered in open court at the time of the hearing.

The plaintiff was working for the defendant as an “ocean master” aboard supply vessels in Tidex’s Brazilian Operations. The plaintiff’s work contracts ran for three months with options at the conclusion. In September of 1982, the plaintiff was working under a contract signed in February, 1982 and subsequently extended for three month intervals. In September, the plaintiff left the vessel (later stating he did so because he felt ill) and was fired for being absent without permission. Plaintiff was discharged on September 15,1982, and was repatriated. Plaintiff was rehired on November 1, 1982. In August, 1983, plaintiff was laid off for economic reasons and filed a claim for medical expenses resulting from the above mentioned illness (it was determined that he had hepatitis). Once the plaintiff filed his complaint, Tidex investigated, and paid for his medical treatment and maintenance for September 16— November 1, 1982.

[550]*550WAGE ISSUE

Central to a determination of whether the plaintiff can recover wages is the issue of what time period controls. There are three possible options: (1) the end of the voyage, (2) the end of the contractual period, and (3) the contractually specified period. The law is well settled that option No. 1 applies when the articles specify or contemplate a voyage of specific duration. 2 Norris, The Law of Seamen, § 544 (3d Edition). However, where the articles are for a specified period (as here), then the seaman can recover wages until the end of the contractual period or until he is fit to return to work. Id. Thus, it would seem that option No. 2 would control and the plaintiff could recover wages until November 10, 1982, at which point he returned to work. However, the employment contract specifies that wages will be paid only until the end of the pay period, if the employee becomes ill while on the job. If the employee is fired for cause, then the contract specifies that wages cease immediately. If the employee is fired without cause, wages will be paid until the point of return to the United States. Therefore, depending upon whether the plaintiff was terminated without cause, with cause, or because of illness, the latest date at which he was entitled to wages would be September 15th. The plaintiff contends that the contract is unclear, and therefore it should be construed against the defendant. However, it appears to the Court that the contract is quite clear on these points.

There seems also to be a dispute as to the nature of the plaintiff’s working arrangements. The defendant claims that the contract, executed February 3, 1982, was extended in three month intervals (the contract specified one such three month extension). Thus, the defendant claims the then existing contract was the one signed in February; such that the employment arrangements were as follows:

February 3 — May 3, 1982: Contract

May 4 — August 4, 1982: Extension # 1

August 5 — November 5, 1982: Extension #2

For some unknown reason the plaintiff disagrees with this analysis, stating in his “Contested Issues” that the arrangements were in a series of sixty day arrangements. However, in his memorandum, plaintiff contends the following:

February 3 — May 3, 1982:

Contract Period

May 4 — August 4, 1982: Contract Period August 5 — August 25, 1982: Vacation August 25 — November 25, 1982: Contract Period

Thus, the plaintiff adopts the three month extension interpretation.

Although the contract contemplates only one three month extension, and requires issuance of a new “Working Agreement,” the parties have agreed that, in fact, he was covered by the contract during the period at issue.

Thus, the real issue before the Court is whether the contractual provisions can modify the rule that wages are due until the end of the contract or until the plaintiff returns to work.

As mentioned, Judge McNamara had this same issue before him in Dowdle v. Offshore Express, Inc., C.A. No. 84-3791. In his opinion, Judge McNamara reasoned that as the rate and mode of payment of maintenance and cure could be regulated by contract, so could wages, citing Grove v. Dixie Carriers, Inc., 553 F.Supp. 777 (E.D.La.1982) and Hodges v. Keystone Shipping Co., 578 F.Supp. 620 (S.D.Texas 1983).

This Court initially agreed with this rationale. However, the Court of Appeal did not, holding that

No agreement is competent to abrogate the seaman’s right to maintenance and cure. Cortes v. Baltimore Insular Line, Inc., 287 U.S. 367, 371, 53 S.Ct. 173, 174, 77 L.Ed. 368 (1932). Correspondingly, the seaman’s right to unearned wages also may not be contractually abrogated. See Vitco v. Joncich, 130 F.Supp. 945, 951 (S.D.Cal.1955) (absent clear quid pro quo received in exchange for contractual abrogation of right to unearned wages, such contractu[551]*551al abrogation is ineffective), aff’d, 234 F.2d 161 (9th Cir.1956)—
Even assuming arguendo that the district court’s decision in Grove is correct —a question never addressed by and not presently before this court — there is a fundamental difference between contractual regulation of the rate of maintenance payments and contractual elimination of such payments altogether.

Id. at 263.

The contractual clause at issue in Dowdle

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caminetti v. United States
242 U.S. 470 (Supreme Court, 1917)
Crooks v. Harrelson
282 U.S. 55 (Supreme Court, 1930)
Cortes v. Baltimore Insular Line, Inc.
287 U.S. 367 (Supreme Court, 1932)
Haggar Co. v. Helvering, Com'r of Internal Revenue
308 U.S. 389 (Supreme Court, 1940)
United States v. American Trucking Associations
310 U.S. 534 (Supreme Court, 1940)
Reiter v. Sonotone Corp.
442 U.S. 330 (Supreme Court, 1979)
Griffin v. Oceanic Contractors, Inc.
458 U.S. 564 (Supreme Court, 1982)
Lee D. Harper v. Zapata Off-Shore Company
741 F.2d 87 (Fifth Circuit, 1984)
Phillips Oil Company v. Okc Corporation
812 F.2d 265 (Fifth Circuit, 1987)
Vitco v. Joncich
130 F. Supp. 945 (S.D. California, 1955)
Grove v. Dixie Carriers, Inc.
553 F. Supp. 777 (E.D. Louisiana, 1982)
Hodges v. Keystone Shipping Co.
578 F. Supp. 620 (S.D. Texas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
674 F. Supp. 548, 1987 U.S. Dist. LEXIS 9170, 1987 WL 23386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-tidex-international-inc-laed-1987.