Williams v. Sullivan

209 So. 2d 618, 1968 Miss. LEXIS 1455
CourtMississippi Supreme Court
DecidedApril 22, 1968
DocketNo. 44877
StatusPublished
Cited by3 cases

This text of 209 So. 2d 618 (Williams v. Sullivan) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Sullivan, 209 So. 2d 618, 1968 Miss. LEXIS 1455 (Mich. 1968).

Opinion

GILLESPIE, Presiding Justice.

Joseph L. Williams, a minor, sued Sullivan, Long & Hagerty, Inc., and its foreman, Luther Ayres, in the Circuit Court of Jackson County to recover damages for personal injuries sustained when a motor scooter being operated by the plaintiff struck a hole in a street known as Jones Road in Jackson County, Mississippi. The plaintiff’s theory of the case was that Sullivan, Long & Hagerty, Inc., hereinafter [619]*619known as Contractor, did certain construction work on Jones Road, and that, after the road was opened for general use by the public and while still under Contractor’s control, Contractor failed to exercise reasonable care to maintain it in a reasonably safe condition. The jury returned a verdict for the plaintiff in the amount of $23,000. Thereafter, the court sustained a motion for judgment notwithstanding the verdict and a judgment was entered by the court for defendants. Plaintiff appealed to this Court and assigned as error the action of the trial court in sustaining the defendants’ motion for judgment notwithstanding the verdict.

On or about December 12, 1963, the Contractor entered into a contract with the Jackson County Board of Supervisors to construct a water distribution and sewage collection improvement in the Bayou Ca-sotte area of Jackson County, Mississippi. The work performed by Contractor amounted to about $3,000,000 and involved various construction work including laying a water line and sewer line in Jones Road west of Highway 63. The engineering firm of Barth and Associates was employed by the Jackson County Board of Supervisors to have general supervision of the contract on behalf of the county. An engineer was kept on the job a portion of the time. The contract provided that payments would be made to the Contractor from time to time as parts of the work were completed. On September 8, 1965, Barth and Associates notified Contractor by letter to pave Jones Road; the sewer and water lines had already been laid, together with certain connecting lines to meters on the south side of Jones Road. The paving of Jones Road was sublet to a sub-contractor and paving was completed on September 20, 1965. When the paving was complete, Contractor had no further work to do on Jones Road and did not perform any other work on this road.

On November 17, 1965, the engineer measured up the work done on Jones Road for payment, all work on said road having been done to the satisfaction of Barth and Associates. Thereupon, contractor was paid for that work, less a ten percent re-tainage as provided by the contract.

After Jones Road was paved and prior to November 26, 1965, when the plaintiff was injured, the Jackson County Utilities, operated by Jackson County, cut three trenches across Jones Road to connect the water line, which had been laid by Contractor, to three houses which faced a road known as “Road X”. This road runs parallel to and north of Jones Road. Contractor performed no work on “Road X”. The trenches cut by Jackson County Utilities were backfilled with dirt and on November 26 one of the trenches had a hole about three to six inches deep and about eighteen inches wide in the travelled part of the road. The plaintiff, an eleven year old boy, rode up and down this road several times a day on his motor scooter. He had been riding over a hump created by the backfill dirt in one of these trenches so that it would make his motor scooter jump into the air. On the day he was injured he missed the hump and hit the hole. This caused him to lose control and resulted in serious personal injuries.

Shortly before the plaintiff was injured, a nearby resident, who daily drove over Jones Road, complained to the Jackson County Board' of Supervisors about the condition of the road. She was referred to Contractor. She then called Contractor’s office and a lady answered the phone. Information was given the lady who answered Contractor’s phone of the poor condition of the road. The evidence showed that Mr. Ayres, one of the defendants, and a foreman of the Contractor, knew that the road had been cut by the Jackson County Utilities. Neither Contractor nor Jackson County Utilities put up any warning signs of the ruts created by these trenches cut in the new pavement.

The contract between Jackson County and the Contractor contained among other things the following provisions:

After the construction work is completed, all refuse and debris resulting [620]*620from the work shall be cleaned up and disposed of to the satisfaction of the engineer, structures shall be washed or swept out and left neat and clear. Dirt and spots shall be removed from the equipment and all painted surfaces. All excess excavation, waste concrete, wiring, piping, lumber or other refuse shall be removed from the site of the work and site leveled, graded and dressed until it is neat, smooth and workmanlike. All work under this section shall be done by the contractor at his own expense.
‡ ‡ % ‡ ifc ‡
Any defective work may be rejected by the engineer at any time before the final acceptance of the work, even though the same may have been previously over looked [sic] and estimated for payment.
* * * ‡ * *
If the Contractor claims that any instructions by drawings or otherwise involve extra cost under this Contract, he shall give the engineer written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute the work, except in emergency endangering life or property, and the procedure shall be then as provided for changes in the work. No claim shall be valid unless so made.
Jjc íjí sjí í{í
The owner agrees to pay the Contractor 100% of the value of the work done each month, less thn [sic] percent (10%) retainage until final acceptance of the work had been made.
* * * * * *
* * * It is the intent of this Specification that the Contractor shall be responsible for all settlement of backfill in trenches occasioned by the work covered herein. He shall refill trenches as often as necessary to bring them back to original grade and during the period when settlement is occurring shall refill them frequently enough to maintain traffic without hazard at all times except when trenches are actually flooded.
* * * * * *
Wherever it becomes necessary in excavating to disturb special surfaces such as concrete, bituminous, or gravel drives, roadways, walks or parking areas, the original surface shall be restored after complete [sic] of the backfill.
i}c ‡ ‡ ‡ *
When the open trench method of installation is specifically permitted by the Engineers in writing, adequate falsework shall be provided to properly maintain traffic on the highway being crossed. When the open trench method is used, the Contractor shall pay all cost of false-work construction and of maintenance of road surface or roadbed resulting therefrom, whether incurred by the Contractor or by others.
******
All materials excavated shall be placed so as to interfere as little as possible with public vehicular traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hosea O. Weaver & Sons, Inc. v. Balch
142 So. 3d 479 (Supreme Court of Alabama, 2013)
McKay v. Boyd Const. Co., Inc.
571 So. 2d 916 (Mississippi Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
209 So. 2d 618, 1968 Miss. LEXIS 1455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-sullivan-miss-1968.