Williams v. M. T. Connolly Contracting Co.

65 A. 179, 74 N.J.L. 105, 1906 N.J. Sup. Ct. LEXIS 36
CourtSupreme Court of New Jersey
DecidedNovember 12, 1906
StatusPublished

This text of 65 A. 179 (Williams v. M. T. Connolly Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. M. T. Connolly Contracting Co., 65 A. 179, 74 N.J.L. 105, 1906 N.J. Sup. Ct. LEXIS 36 (N.J. 1906).

Opinion

The opinion of the court was delivered by

Pitney, J.

This was an action upon contract in which the plaintiff sued to recover the balance due upon an account for hauling-pipe for the defendant in the month of September, 1903, and several succeeding months. His charges against the defendant aggregated $1,296.55, upon which credits amounting to $1,184.81 were allowed, leaving a balance of $111.74 unpaid. It was admitted upon.the trial that plaintiff’s account was correct, excepting as affected by defendant’s claim to recoupment.

The hauling of pipe, out of which the plaintiff’s charges arose, was done under a contract entered into between the parties on or about September 4th, 1903, defendant having-accepted plaintiff’s written proposition bearing date that day, which was as follows: “I propose to haul all the cast-iron [106]*106pipe from the cars on the Central railroad to the different points throughout the city of Bayonne where the pipe is to go for the sum of 80 cents per ton. All broken pipe to be left on the ears and not moved, and I to be responsible for breakage or any damage done to pipe in hauling them and putting them on the ground.”

Defendant filed a notice of recoupment that included three claims. The first of these, for failure to haul certain pipe to the location where it was to go, by reason whereof defendant was obliged to hire men to do the work at a cost of $45.15, was conceded to he a just claim.

The second item of recoupment was for damage and breakage clone to pipes in hauling them and putting them upon the ground, for which the plaintiff was responsible under the terms of his contract.

The third item was for failure of the plaintiff to remove the pipe from the cars of the railroad company promptly to the different points where the pipe was to go, by reason whereof defendant became liable to pay to the railroad company, and did pay, certain charges for demurrage.

The case was tried before the district judge without a jury. Tie gave judgment in favor of the plaintiff for the difference between the conceded balance due upon his account ($111.74) and the amount due to the defendant upon the first item of its notice of recoupment ($45.15), the difference for which judgment was rendered being $66.49.

From the state of the case, as settled by the trial judge, it appears that he disallowed the second and third items of recoupment on the ground that they were not substantiated by the evidence. As to the second item — that for broken pipe — the trial judge certifies among his findings of fact that certain pipes arrived broken upon the cars, and that while the contract contemplated that these were to be left upon the ears and not moved, the plaintiff, by consent of the defendant, and in order to prevent car demurrage being charged up against the defendant, removed such broken pipe from the cars; that plaintiff's agent took the bills of lading to the freight agent, had the condition of the broken pipe [107]*107noted upon the bills of lading and delivered these bills so noted to the defendant; that some time after the middle of December, 1903, defendant made a claim against the plaintiff for breakage of nine pipes, alleging damages to the amount of $181.48, which claim was allowed by the plaintiff and credited in his account. The claim under defendant’s second item of recoupment was for six additional pipes, claimed to have 'been broken by the plaintiff in handling during the same period, for which, by mistake, as alleged, no claim was made when the claim for the nine pipes was made and allowed. The judge found that the claim that plaintiff had broken any more pipe than had been allowed for in the settlement of December, 1903, was not substantiated.

As to the third item of recoupment — that for car demur-rage, occasioned by plaintiff’s failure to promptly unload the cars — the trial judge found that by the custom of the railroad company all cars not unloaded within forty-eight hours after arrival at their destination, exclusive of Sundays and legal holidays, were charged for the excess time at the rate of $1 per car per day ; that there was no express agreement that the plaintiff should be responsible for the demurrage, nor that he should remove the pipe within any specified time, and no evidence of delay on his part such as would charge him with negligence in the performance of his contract; that the facilities for handling cars laden -with 'heavy freight at the Bayonne station permitted only three such cars to go at once upon the siding, and that they were shifted only once each dajr; that often there were cars waiting for a considerable period before being put upon the siding to be unloaded, and that the evidence failed to show the specific position of the cars upon which the defendant’s pipe was loaded during the time for which demurrage was charged, and so this item of recoupment was held not to be established.

Defendant’s appeal to this court is based upon Pamph. L. 1902, p. 565, and is limited to questions of law only. This court will not review the findings of the District Court upon questions of fact beyond inquiring whether there was any legal evidence upon which the finding might be based. Ellis [108]*108Company v. Eyth, 40 Vroom 579; Phelps v. Seymour, 41 Id. 626; VanVechten v. McGuire, Id. 657; Cosgrove v. Metropolitan Construction Co., 42 Id. 106; Burr v. Adams Express Co., Id. 263; McLaughlin v. Beck, Id. 380.

In order that alleged error of law may be reviewed, there must be something in the state of the case to show that the question was raised in the trial court. O’Donnell v. Weiler, 43 Vroom 142, 145; Hanson v. Pennsylvania Railroad Co., Id. 407.

The state of the case now before us does not show that any legal question was raised by the appellant in the trial court and there decided adversely to- its contention. The ground suggested for reversal is that there was no legal evidence produced at the trial upon which the judge’s findings of fact forming a basis for the judgment can be supported. In view of this suggestion the court made an order calling upon the trial judge to certify the evidence upon which such findings of fact were based. In obedience to that order the trial judge has certified the evidence called for. It is now argued (to quote the language of the brief) that as to the second item of the defendant’s claim against the plaintiff, “the evidence did hot justify the District Court in finding that the plaintiff did not break the pipe, but, on the contrary, shows that he did break them, and is therefore responsible to the defendant for their value.” And as to the claim of demurrage the argument is “that the evidence did not justify the District Court in holding that plaintiff was not liable, but,, did. show that the defendant should have been allowed $109.83, the amount of car service charges paid by it.”

The peculiarity of the situation is that with respect to both of these claims the burden of proof was upon the defendant, and the finding of the trial judge was negative, to wit, that the defendant had not sustained the claims by evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. B. Ellis Co. v. Eyth
55 A. 54 (Supreme Court of New Jersey, 1903)
McLaughlin v. Beck
58 A. 1081 (Supreme Court of New Jersey, 1904)
O'Donnell v. Weiler
59 A. 1055 (Supreme Court of New Jersey, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
65 A. 179, 74 N.J.L. 105, 1906 N.J. Sup. Ct. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-m-t-connolly-contracting-co-nj-1906.