Williams v. Kaerek Builders, Inc.

568 N.W.2d 313, 212 Wis. 2d 150, 1997 Wisc. App. LEXIS 684
CourtCourt of Appeals of Wisconsin
DecidedJune 18, 1997
Docket96-2396
StatusPublished
Cited by4 cases

This text of 568 N.W.2d 313 (Williams v. Kaerek Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Kaerek Builders, Inc., 568 N.W.2d 313, 212 Wis. 2d 150, 1997 Wisc. App. LEXIS 684 (Wis. Ct. App. 1997).

Opinion

BROWN, J.

This case primarily concerns the application of the Hansen/Borello 1 discovery rule to a negligence suit brought against a home builder due to a leaky basement. The builder made several representations to the homeowners which allegedly induced them to delay discovering the cause of their wet basement and initiating this lawsuit. The circuit court nonetheless determined that the representations should not have delayed the homeowners and awarded summary judgment to the builder because the statute of limitations had expired. We hold, however, that the question of whether the homeowners reasonably relied on the representations is a question of fact and remand for a trial.

Facts

The record contains the following undisputed facts. In October 1987, Fredrick and Sharlene Williams purchased a house from Kaerek Builders, Inc. (the *153 Builder). At that time, the house was still in the final stages of construction, but the Williamses were able to move in by that December. The purchase agreement included a warranty furnished by the Builder.

In addition to these undisputed facts, the Wil-liamses' complaint and affidavits filed in opposition to summary judgment raise the following allegations. For the purposes of our analysis — reviewing a summary judgment award in favor of the Builder — we accept these allegations in a light most favorable to the Wil-liamses. See Grams v. Boss, 97 Wis. 2d 332, 339, 294 N.W.2d 473, 477 (1980).

Within a few months after the Williamses moved in, they noticed "dampness, leakage and seepage" in the basement. They reported this problem to the Builder, who told them that the problems resulted from "condensation" and that all new homes have such problems. The Builder furnished them with some waterproofing paint which was applied in the spring of 1988. During the summer of 1988, the house nonetheless remained damp.

As this water problem continued, the Williamses again consulted the Builder in the fall of 1988. This time the Builder installed a second sump pump in the basement. The Builder assured the Williamses that this water problem was not unusual and it would resolve itself.

Although the Williamses' basement remained dry that winter, in the summer of 1989 the water problems returned. Then in the fall of 1989, the basement dried out. But again, during the summer of 1990, the water problems returned. The basement was dry during the winter of 1990.

When the water problem reoccurred in the spring of 1991, the Williamses returned to the Builder who *154 now told them that the water problem was related to a temporary sediment pond located on the building site next door. The Builder assured the Williamses that when the construction on that site was completed, and the pond removed, then their water problem would cease.

But while the house next door was finished by the fall of 1991, the Williamses' water problems continued. When the Williamses looked to the Builder for an answer, the Builder again said that over time their leaky basement problem would resolve itself.

The Williamses waited until the summer of 1994 when their basement worsened. The Williamses now had "cracks in the floor of the basement, running water, fungus on the drywall, and water lines on the cement blocks." In July 1994, they retained a waterproofing company to inspect their basement.

The company could not determine the cause of the leaking from a visual inspection and had to excavate outside the basement wall and dig up the concrete floor. The company was then able to determine that the drain tiles were not properly installed. The company performed the necessary repairs at a total cost of $8926; and the problem was solved.

In June 1996, the Williamses retained an engineer to further explore the cause of their water problem. The expert opined that there were two main causes for the water problem. One, the house was built at too low of an elevation. The drain system was thus below the water table, causing surface runoff to run toward the house, not away from the house. Two, the Builder wrongfully backfilled the foundation with clay, instead of with a porous material such as small stones. Over time, as the clay retained water, consolidated and settled, it began to exert pressure on the basement walls. *155 The expert provided this summary to the Williamses: "[the Builder] could have given you a dry basement if [it] had set the first floor grade elevation properly and if [it] had backfilled with stone."

Procedural Background

The Williamses filed suit against the Builder in July 1995 asserting two causes of action. First, they claimed that the Builder negligently constructed the house. Second, they claimed that the Builder breached the 1987 purchase contract and warranty by failing to construct the home in a "workmanlike manner" and to "cure defects in the construction."

After filing a timely answer, the Builder moved for summary judgment in June 1996 on grounds that the six-year statute of limitations on the two claims had expired. 2 See §§ 893.43 and 893.52, STATS. The Builder furnished an affidavit which confirmed that it built the house and performed some "additional repairs in 1988," but which otherwise alleged that it had no "further contact" with the property after that time. The Builder argued that the Williamses discovered their injury as soon as they moved in and that there was no reasonable explanation for why they waited until 1994 to hire the waterproofing company to uncover the cause of their injury. The Builder made a similar argument against permitting the breach of contract action to move forward.

The circuit court agreed. With regard to the negligence claim, it found that the Williamses had known *156 about this injury — the wet basement- — soon after they moved in. The circuit court further found that the Wil-liamses should have realized sooner that the Builder "was simply giving them the runaround." The circuit court thus reasoned that the Williamses should have contacted the waterproofing company earlier (not waited until 1994) to substantiate their suspicion that the Builder had done something to cause their water problem. The circuit court concluded that because the Williamses did not file their claim until July 1995, eight and one-half years after they moved in, their claim was barred under the six-year statute of limitations.

In addition, the circuit court awarded judgment to the Builder on the breach of contract claim. Here, the Williamses sought to invoke the doctrine of equitable estoppel and bar the Builder from asserting the statute of limitations because the Builder had made continuing representations that it was going to remedy the problem. See generally Hester v. Williams, 117 Wis. 2d 634, 644-46, 345 N.W.2d 426, 431-32 (1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Antonio S. Davis v. Circuit Court for Dane County
2024 WI 14 (Wisconsin Supreme Court, 2024)
Schwark v. M+ S Brugg Ag
2007 WI App 203 (Court of Appeals of Wisconsin, 2007)
Nugent v. Slaght
2001 WI App 282 (Court of Appeals of Wisconsin, 2001)
Schimpf v. Gerald, Inc.
52 F. Supp. 2d 976 (E.D. Wisconsin, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
568 N.W.2d 313, 212 Wis. 2d 150, 1997 Wisc. App. LEXIS 684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-kaerek-builders-inc-wisctapp-1997.