MR. Justice Lansden

delivered the opinion of the Court.

The original bill was filed by the complainant, Williams, against the Birmingham & Northwestern Railway Company as owner, the Jackson Construction Company, a Tennessee corporation, as principal contractor, and Mrs. Susie E. Wright, administratrix of J. W. Wright, Jr., deceased, as subcontractor, for the purpose of enforcing a claimed lien upon the line of railway of the defendant railway company for approximately $2,000 claimed to be due for work and labor done in the construction of the line of railway belong[683]*683ing to the defendant railway company. The chancellor sustained a demurrer to the hill, from which the complainant has appealed and assigned errors. The defendants the railway company and the construction company have filed the record for writs of error to review those parts of the decree of the chancellor in which he overruled certain other grounds of demurrer assigned to the hill. There were fourteen grounds of demurrer in the court below, only four of which were sustained by the chancellor, and this opinion will he confined to discussion of the questions presented hy those grounds.

The bill charged that the defendant railway company “is a railway corporation, with its home office at Jackson, Tennessee, owning and operating a line of railway from Jackson, Tennessee, through the counties of Madison, Crockett and Dyer, which railway company owns its rights of way, tracks, ties, rails tanks, switches, bridges, tunnels, depots, engines, equipments, and franchises”; that the Jackson Construction Company is a Tennessee corporation, with its principal place of business in Jackson, Tennessee, and entered into a contract with the railway company as principal contractor for the construction of its line of railroad; that J. W. Wright, Jr., now deceased, and the intestate of Mrs. Susie E. Wright, entered into a contract with the construction company for the construction and building of the entire line of railway aforesaid; and that the complainant was subcontractor under Wright, in which capacity he did certain , work set out in the bill, [684]*684and for which Wright is indebted to him in the snm of $2,701.81.

The demurrer raised the question that the bill failed to sufficiently describe the line of railroad upon which the lien is claimed, and, there being no attachment of the property, the lien must fail.

It is not insisted that an attachment is necessary to secure the lien, and could not be under the authority of Luttrell v. Railroad, 119 Tenn. 492, 105 S. W. 565, 123 Am. St. Rep. 737; but it is said that in the absence of an attachment, under sound rules of pleading, the bill must describe the property upon which it is sought to fix the lien with sufficient definiteness to identify it and segregate it as the property upon which the lien is claimed. This is unquestionably a sound principle. So the question for determination is whether the description is sufficient. The bill was manifestly modeled after the description contained in Luttrell v. Railroad, supra. In that case it was said:

“The bill is framed in strict conformity with the provisions of sections 2 and 3, chapter 98, of the Acts of 1891. It describes the lines of railroad upon which the lien is sought as leading from Jellico, through the counties of Campbell, Anderson, and Knox, to Knoxville. ’ ’

The description herein is somewhat more specific than that just quoted, and which, the court considered to be in strict conformity with the act of 1891. It is entirely clear that any person reasonably acquainted in the community could identify and locate the line of [685]*685railroad upon which the lien is claimed from the description contained in the bill. The bill further shows that the railroad company is the owner of its tracks, ties, etc. Hence this assignment is sustained.

It is next said that the chancery court of Madison county is without jurisdiction to entertain the bill, and declare and enforce the lien which it seeks, for the reason that the bill shows that the work done out of which the lien claim arises was performed in Dyer county, and the bill was not filed either in the county or the district or chancery division in which the work was done. A proper determination of this question makes it necessary to consider chapter 220, Acts of 1883, and chapter 98, Acts of 1891, amendatory thereof. The first act gave a lien to persons contracting with railroads for work and labor done and material furnished in the construction or repairing; of the railroad. Section 2 provided that the lien created by the act “may be enforced by a suit against the railroad company in the circuit court of the county or district where the work or some part thereof was done or material of some part thereof was delivered.”

Section 3 of the act, while not giving a lien to subcontractors upon the railroad property, provided for a garnishment proceeding in favor of subcontractors and others against the principal contractor in such way as to fix a lien upon funds due the principal contractor from the railroad company in favor of subcontractors and the others. It was provided that this claim “may be enforced against the railroad company [686]*686as garnishee, and the principal contractor as debtor in the circuit conrt, or before any justice of the peace of the county having jurisdiction of the amount claimed”; and section 4 of the act gave a like remedy in favor of laborers, material men, and others employed by subcontractors against the principal contractor, and provided that this remedy “may be enforced against the principal contractor as garnishee and the subcontractor as debtor in the circuit court or before any justice of the peace of the county having jurisdiction of the amount.” Section 3 of this statute was amended by chapter 98, Acts of 1891, so as to place subcontractors and others mentioned in section 3 of the act of 1883 on the same basis with respect to their liens as principal contractors. It was provided, however, that notice shall be given to the railroad company within 90 days after the work and labor done, or the materials are furnished or services rendered. It is then provided in section 2 as follows:

“The liens provided for in this act may be enforced by suit brought against such railroad company in the circuit or chancery court of the county or district where the work or material or any part thereof was done or furnished or any part of said services was rendered. ’ ’

The question made is that the foregoing section is exclusive of all other remedies, and the lien claimant, in order to secure his lien, must bring his suit against the railroad company in the circuit or chancery court of the county, or district, where the work or material [687]*687was done or furnished or the services rendered. As previously stated, the work out of which the present claim arises was done in Dyer county, and Dyer and Madison counties are not in the same chancery division. The suit was brought, however, in the county in which the principal office of the railroad company is situated and in which a part of its line of railway is located. Personal service was had on the defendant.

The argument made here to support the ruling of the learned chancellor is based chiefly upon Barnes v. Thompson, 2 Swan, 314, in which it was held that the mechanic’s lien must be enforced by attachment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Austin v. State
796 S.W.2d 449 (Tennessee Supreme Court, 1990)
Southern v. Beeler, Atty.-Gen.
195 S.W.2d 857 (Tennessee Supreme Court, 1946)
Warren v. Commerce Union Bank
274 S.W. 539 (Tennessee Supreme Court, 1924)
Niehaus v. C. B. Barker Const. Co.
135 Tenn. 382 (Tennessee Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
129 Tenn. 680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-birmingham-n-w-ry-co-tenn-1914.