Williams Company Southeast v. Solar Eclipse Window Coverings, LLC

CourtDistrict Court, W.D. Virginia
DecidedOctober 29, 2025
Docket3:24-cv-00075
StatusUnknown

This text of Williams Company Southeast v. Solar Eclipse Window Coverings, LLC (Williams Company Southeast v. Solar Eclipse Window Coverings, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Company Southeast v. Solar Eclipse Window Coverings, LLC, (W.D. Va. 2025).

Opinion

AT LED. VILLC, VAN October 29, 2025 LAURA A. AUSTIN, CLERK IN THE UNITED STATES DISTRICT COURT erty CLERK POR THE WESTERN DISTRICT OF VIRGINIA CHARLOTTESVILLE DIVISION

Williams Company Southeast, ) ) Plaintiff, ) ) v. ) Civil Action No. 3:24-cv-00075 ) ) Solar Eclipse Window Coverings, LLC, ) ) Defendant. ) ) ) MEMORANDUM OPINION This matter is before the court on Plaintiff Williams Company Southeast’s (“Williams Company’) motion for default judgment against Defendant Solar Eclipse Window Coverings, LLC (SEWC”) (Dkt. 9). Williams Company seeks damages resulting from SEWC’s alleged breach of contract, taxable costs pursuant to 28 U.S.C. § 1920, and post-judement interest pursuant to 28 U.S.C. § 1961. For the reasons outlined below, the court will grant Williams Company’s motion for default judgment. I. Background A. Factual History On August 7, 2023, Williams Company executed a subcontract with SEWC, under which SEWC was to furnish and install window blinds for apartments in a multi-family residential building in exchange for $92,900. (Compl. {6-7 (Dkt. 1); S-1 Subcontract at 2, 14 (Dkt. 1-3) [hereinafter “Subcontract’].) The apartment building, owned by OC Stonefield

Residential Property Owner (“Owner”), was being constructed at 2105 Bond Street, Charlottesville, Virginia pursuant to an earlier agreement between Owner and Williams Company. (Compl. ¶ 7; see Dkt. 1-2 at 119.) Williams Company’s subcontract with SEWC

called for SEWC to “[p]rovide and install” all window blinds for the project, which required “horizontal window blinds for all exterior windows in all apartment [sic]” as well as one “roller Shade at Flex Room.” (Subcontract at 2.) This totaled approximately “227 units worth” of blinds, or “1,600 total blinds,” in addition to the singular “motorized roller shade in the fitness area” of the building. (Compl. ¶ 7.)

Several months later, on March 8, 2024, Williams Company issued a “Change Order #001” for SEWC to upgrade the window shades “to a faux wood blind per request of [Owner]” for an additional $98,400. (Compl. ¶ 8; Dkt. 1-4 at 2.) Both Michael Ricotta, an employee of the Williams Company, and a SEWC representative signed the change order for the upgrade reflecting the increased contract total of $191,300. (Dkt. 1-4 at 2.) SEWC also requested an advance payment enabling them to order the upgraded shades. (Compl. ¶ 9.)

Williams Company complied by providing SEWC with a $73,041.40 check on April 10, 2024. (Id. ¶ 10; Dkt. 1-5 at 2–3.) Tiffany Adams, SEWC’s owner and registered agent, (see Dkt. 1-1 at 2), cashed the check on April 11, 2024, (Compl. ¶ 10; Dkt. 1-5 at 3). On May 6, 2024, SEWC first began installing the blinds on site. (Compl. ¶ 11.) They installed “approximately 340 blind segments across the first and second floors of the Project.” (Id.) A little over a week later, SEWC informed Williams Company that “all of the materials

had been released and were in transit to the Project.” (Id. ¶ 12.) Several days later, on May 20, 2024, Williams Company issued a second advance payment for $73,040.82. (Compl. ¶ 13.) Again, the check was cashed the next day by Tiffany Adams. (Id.; Dkt. 1-6 at 2–3.) Altogether, Williams Company paid SEWC $146,082.22 in advance payments. (Compl. ¶ 28.) After Tiffany Adams cashed the second check, SEWC stopped responding to emails

and calls. (Id. ¶ 14.) Williams Company made “numerous attempts to contact SEWC and its employees and owner, Tiffany Adams.” (Id.) On June 3, 2024, Williams Company contacted SEWC’s manufacturer and supplier for the horizontal window blinds, Lotus and Windoware (“Lotus”). (Id. ¶ 15.) Lotus stated that SEWC “had only placed a single purchase order in the amount of $21,413 for a total of 464 blinds”—approximately 1,136 blinds short of the total number required for the subcontract project. (Id.) This order provided SEWC with the blinds

that they had started to install on May 6, 2024. (Id.) The same day, Williams Company reached out to SWF Contract, the supplier of the roller shade for the fitness room. (Id. ¶ 16.) SWF Contract confirmed that it had not received any prior orders from SEWC, nor did it have “any accounts associated with SEWC.” (Id.) Williams Company issued a Notice of Delay letter to SEWC on June 5, 2024, which stated that SEWC had only purchased 464 blinds despite having received the full advance

payment for purchase and installation of 1,600 blinds. (Id. ¶ 17; Dkt. 1-7 at 2.) The letter also warned SEWC that they would be in breach of contract if the issue was not rectified within 72 hours. (Dkt. 1-7 at 2.) The letter was sent to SEWC’s Woodbridge address that was, at the time, their registered office address. (Dkt. 1-7 at 2; Dkt. 1-1 at 2.) SEWC did not respond to the Notice of Delay letter. (Compl. ¶ 18.) On July 9, 2024, Williams Company sent a “Demand for Payment and Notice of

Termination” letter to SEWC via email and certified mail. (Id. ¶ 19; Dkt. 1-8 at 2–3.) The letter was sent by Williams Company’s attorney and declared that SEWC’s failure to respond constituted a material breach that enabled Williams Company to terminate the subcontract. (Dkt. 1-8 at 2–3.) The letter also demanded that SEWC return the portion of Williams

Company’s advance payments that were not used to purchase and install blinds within ten days. (Id.) After SEWC once again failed to respond, in late July, Williams Company subcontracted with Commonwealth Blinds and Shades to install the 124 blinds that had been delivered to the project but not installed by SEWC. (Compl. ¶ 20.) The new subcontract with Commonwealth cost Williams Company $16,500 in labor and installation costs for the remaining 124 blinds. (Id.; Dkt. 1-9 at 2.)

B. Procedural History On September 17, 2024, Williams Company filed a complaint in this court seeking to recover the following damages: (1) $124,669.22 in advance payments made to SEWC and not used as required by the subcontract, (2) $16,500 in costs incurred when Williams Company had to hire replacement Commonwealth Blinds to complete the installation of materials that SEWC purchased but did not install, and (3) “other related expenses and costs.” (Compl.

¶ 35.) The complaint alleged a single cause of action, breach of contract, stemming from SEWC’s failure to use the advance payments to install the remaining window blinds under their subcontract and SEWC’s abandonment of its work without communication to Williams Company. (Id. ¶ 24–35.) On December 12, 2024, Williams Company filed a motion for entry of default against SEWC. (Pl.’s Mot. for Entry of Default (Dkt. 6) [hereinafter “Mot. for Default”].) Williams

Company delineated the steps it took to serve SEWC; it attempted service of process at five different addresses associated with SEWC, including SEWC’s registered office, at a variety of times and dates spanning a month. (Id. ¶ 2; Dkt. 6-1 at 2–3.) After the process server’s unsuccessful attempts, Williams Company sought to serve the clerk of the State Corporation

Commission of Virginia pursuant to Va. Code Ann. § 13.1-1018(B), which allows the clerk of the Commission to be deemed “an agent of the limited liability company” “whenever [the company’s] registered agent cannot with reasonable diligence be found at the registered office.” (Mot. for Default ¶ 3). Williams Company served the clerk on October 30, 2024, in accordance with Va. Code Ann. § 12.1-19.1. (Mot for Default ¶ 4; Dkt. 6-2 at 2.) The Certificate of Compliance was filed by this court on November 20, 2024. (Dkt. 5.)

On December 13, 2024, Magistrate Judge Joel C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
United States v. Nasser Moradi
673 F.2d 725 (Fourth Circuit, 1982)
Directv, Inc. v. Pernites
200 F. App'x 257 (Fourth Circuit, 2006)
Sunrise Continuing Care, LLC v. Wright
671 S.E.2d 132 (Supreme Court of Virginia, 2009)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Ulloa v. Qsp, Inc.
624 S.E.2d 43 (Supreme Court of Virginia, 2006)
Estate of Taylor v. Flair Property Associates
448 S.E.2d 413 (Supreme Court of Virginia, 1994)
Tweedy v. RCAM TITLE LOANS, LLC
611 F. Supp. 2d 603 (W.D. Virginia, 2009)
Securities & Exchange Commission v. Lawbaugh
359 F. Supp. 2d 418 (D. Maryland, 2005)
William H. Gordon Assocs., Inc. v. Heritage Fellowship
784 S.E.2d 265 (Supreme Court of Virginia, 2016)
Navar, Inc. v. Federal Business Council
784 S.E.2d 296 (Supreme Court of Virginia, 2016)
Ryan v. Homecomings Financial Network
253 F.3d 778 (Fourth Circuit, 2001)
Hummel v. Hall
868 F. Supp. 2d 543 (W.D. Virginia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Williams Company Southeast v. Solar Eclipse Window Coverings, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-company-southeast-v-solar-eclipse-window-coverings-llc-vawd-2025.