Williams Companies, Inc. v. PA PUC

Commonwealth Court of Pennsylvania·Decided August 19, 2026·No. 1232 C.D. 2024·Published·Wojcik. Cohn Jubelirer. Dumas

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Williams Companies, Inc., :

:

Petitioner :

:

v. : No. 1232 C.D. 2024 : Argued: September 10, 2025 Pennsylvania Public : Utility Commission, :

:

Respondent :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE PATRICIA A. McCULLOUGH, Judge HONORABLE ANNE E. COVEY, Judge HONORABLE MICHAEL H. WOJCIK, Judge HONORABLE LORI A. DUMAS, Judge HONORABLE STACY WALLACE, Judge HONORABLE MATTHEW S. WOLF, Judge

OPINION BY JUDGE WOJCIK FILED: August 19, 2026

In this case of first impression, Williams, Inc. (Williams) petitions for review the August 21, 2024 order of the Pennsylvania Public Utility Commission (PUC) denying reconsideration and upholding its prior determination that Williams’ proposed solar photovoltaic systems, which bypass the electric distribution company’s (EDC) distribution system and the regional transmission organization’s (RTO) transmission system, do not meet the definition of an “alternative energy system” and thus do not qualify for “solar renewable energy credits” (solar credits)

under the Alternative Energy Portfolio Standards Act (AEPS Act)1 as amended by Section 2804 of The Administrative Code of 1929 (Act 40).2 Williams contends that the PUC erred and/or abused its discretion by denying reconsideration and concluding that its proposed solar photovoltaic systems, which will directly deliver electricity generated to Williams’ natural gas compressor stations, do not qualify for solar credits. Upon concluding that the PUCs interpretation of Act 40 was erroneous, we reverse.

I. Background

Williams is an energy company with a primary focus on natural gas infrastructure. Williams owns a subsidiary, Transcontinental Gas Pipe Line Company, LLC (Transco), that operates the Transco natural gas pipeline, a major interstate pipeline system that transports approximately 15% of the nation’s natural gas. Transco operates multiple natural gas compressor stations along the pipeline, which demand energy. Williams plans to construct two large solar photovoltaic systems, using solar arrays with a nameplate capacity of approximately 11 megawatts each,3 to provide electricity to two of Transco’s natural gas compressor stations located in Wyoming and Columbia Counties, Pennsylvania. The compressor stations receive electricity from PPL Electric Utilities (PPL), an EDC; Transco is the retail customer of record at both locations. For each project, the solar arrays will be located on land adjacent to the compressor station and be physically

1 Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§1648.1-1648.8.

2 Act of April 9, 1929, P.L. 177, added by the Act of October 30, 2017, P.L. 379, 71 P.S. §714.

3 This nameplate capacity is too large to net meter. See Section 2 of the AEPS Act, 73 P.S.

§1648.2 (definition of “customer-generator”); R.R. at 50a.

connected to the compressor station’s existing internal electric system. The solar energy generated will flow directly into Transco’s compressor stations’ internal electric systems to support the stations’ operations. Williams expects the entirety of the solar generation to be consumed by the compressor stations, which will reduce reliance on PPL for electricity.

On June 26, 2023, Williams filed a Petition for Declaratory Order with the PUC seeking a declaration that Williams’ proposed solar photovoltaic systems would qualify for solar credits under the AEPS Act. Reproduced Record (R.R.) at 1a-7a. In support, Williams relied on the language of Act 40 that a solar photovoltaic system that “directly deliver[s] the electricity it generates to a retail customer of an [EDC],” even if not interconnected to the grid, would qualify.4 Id. at 4a (quoting Act 40, 71 P.S. §714). The PUC determined that Williams’ proposed solar photovoltaic systems were ineligible for solar credits. Williams filed a Petition for Reconsideration, which the PUC granted pending further review. Ultimately, the PUC rejected Williams’ interpretation and concluded that the projects did not qualify based on lack of connection to the grid. The PUC reasoned that when Act 40 is read in pari materia with the AEPS Act, “alternative energy systems,” including solar photovoltaic systems, must be connected to an EDC’s distribution system or an RTO’s transmission system to qualify for solar credits. Thus, by decision dated August 21, 2024, the PUC denied reconsideration and upheld its determination that

4 Interconnection is the physical connection to the grid; delivery is the transfer of electricity to a retail customer or the grid.

Williams’ proposed solar photovoltaic systems are ineligible for solar credits.5 This appeal now follows.6

II. Issue

The sole issue for our review is whether Williams’ proposed solar photovoltaic systems, which will directly deliver the electricity to a PPL retail customer, without grid interconnection, qualify for solar credits under the AEPS Act.

III. Discussion A. Contentions

Williams argues that the PUC erred in concluding that its proposed solar photovoltaic systems are not eligible for solar credits under the AEPS Act. According to Williams, the clear and unambiguous language of Act 40 specifies that a solar photovoltaic system qualifies for solar credits under the AEPS Act if it “[d]irectly deliver[s] the electricity it generates to a retail customer of an [EDC].” 71 P.S. §714(1)(i) (emphasis added). The proposed solar photovoltaic systems here will directly deliver the electricity generated to Transco’s compressor stations. Transco is a retail customer of an EDC – PPL. Thus, Williams maintains that the proposed systems should qualify for solar credits under the AEPS Act. According

5 The PUC noted that the reduced electric consumption by Williams due to the proposed solar photovoltaic systems may qualify as demand-side management and would be eligible to generate Tier II alternative energy source under the AEPS Act. PUC Opinion, 8/21/24, at 20; R.R. at 69a.

6 We review the PUC’s denial of reconsideration for abuse of discretion. Executive Transportation Company, Inc. v. Pennsylvania Public Utility Commission, 138 A.3d 145, 148 (Pa. Cmwlth. 2016); J.A.M. Cab Company, Inc. v. Pennsylvania Public Utility Commission, 572 A.2d 1317, 1318 (Pa. Cmwlth. 1990). “An abuse of discretion occurs if the agency decision demonstrates bad faith, fraud, capricious action or an abuse of power.” J.A.M. Cab, 535 A.2d at 1246.

to Williams, the PUC’s contrary interpretation disregards Act 40’s plain statutory text and undermines the General Assembly’s intent to encourage in-state solar development.

The PUC counters that Williams’ interpretation completely disregards other interconnection requirements embedded within the AEPS Act. When Act 40 and the AEPS Act are read together, the PUC asserts that an ambiguity arises based on the definition of “alternative energy system,” which requires grid connection. The PUC advances that interconnection remains a prerequisite for solar credits, and Act 40 did not alter or eliminate this requirement or create a standalone eligibility pathway for solar credits. The PUC contends that Williams’ interpretation would effectively result in an implied repeal of Sections 2 and 3 of the AEPS Act, 73 P.S. §§1648.2, 1648.3, which is not favored under the law, by eliminating the requirement that qualifying systems deliver electricity to the grid. Such a reading would allow any solar facility serving only its own load to earn solar credits, which is contrary to the AEPS Act’s structure and intent. Because Williams’ proposed solar photovoltaic systems will not interconnect with an EDC or RTO, they fail to meet the statutory definition of an “alternative energy system” and cannot qualify for solar credits under the AEPS Act.

B. Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Williams Companies, Inc. v. PA PUC, (Pa. Ct. App. 2026).

Williams Companies, Inc. v. PA PUC (Williams Companies, Inc. v. PA PUC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

ARIPPA v. Pennsylvania Public Utility Commission
966 A.2d 1204 (Commonwealth Court of Pennsylvania, 2009)
J.A.M. Cab Co. v. Pennsylvania Public Utility Commission
572 A.2d 1317 (Commonwealth Court of Pennsylvania, 1990)
Pleasant Hills Construction Co. v. Public Auditorium Authority
784 A.2d 1277 (Supreme Court of Pennsylvania, 2001)
Executive Transportation Co. v. Pennsylvania Public Utility Commission
138 A.3d 145 (Commonwealth Court of Pennsylvania, 2016)
Nat'l Labor Relations Bd. v. SW Gen., Inc.
580 U.S. 288 (Supreme Court, 2017)
PA State Police, Aplt. v. Grove, M.
161 A.3d 877 (Supreme Court of Pennsylvania, 2017)
Downingtown Borough (Friends of Kardon Park,Aplts)
161 A.3d 844 (Supreme Court of Pennsylvania, 2017)
D.L. Smith v. Ivy Lee Real Estate, LLC
165 A.3d 93 (Commonwealth Court of Pennsylvania, 2017)
Mercury Trucking, Inc. v. Pennsylvania Public Utility Commission
55 A.3d 1056 (Supreme Court of Pennsylvania, 2012)