William Sawyer-Overlake II, LLC v. Gregory Jones and Jessica Jones

CourtSupreme Court of Vermont
DecidedOctober 22, 2015
Docket2015-209
StatusUnpublished

This text of William Sawyer-Overlake II, LLC v. Gregory Jones and Jessica Jones (William Sawyer-Overlake II, LLC v. Gregory Jones and Jessica Jones) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William Sawyer-Overlake II, LLC v. Gregory Jones and Jessica Jones, (Vt. 2015).

Opinion

Note: Decisions of a three-justice panel are not to be considered as precedent before any tribunal.

ENTRY ORDER

SUPREME COURT DOCKET NO. 2015-209

OCTOBER TERM, 2015

William R. Sawyer-Overlake II, LLC } APPEALED FROM: } } Superior Court, Chittenden Unit, v. } Civil Division } } Gregory Jones and Jessica Jones } DOCKET NO. 984-9-13 Cncv

Trial Judge: Helen M. Toor

In the above-entitled cause, the Clerk will enter:

This case involves a dispute over a fence owned by defendants that allegedly interferes with a storm water drainage easement. Plaintiff appeals from the trial court’s summary judgment decision in favor of defendants.* We affirm.

Plaintiff sued defendants in September 2013, alleging that it held an easement that crossed defendants’ land. According to plaintiff, this easement allowed for storm water drainage across defendants’ land to a storm water detention pond located on a common land portion of the subdivision. Plaintiff maintained that defendants, or their predecessor-in-title, constructed a fence around the perimeter of the property subject to the easement, and that the fence blocked access to the storm water detention pond, thereby preventing plaintiff from undertaking maintenance and repair to the detention pond.

Defendants subsequently moved for summary judgment, and plaintiff opposed the motion. Before ruling on the motion, the court issued an entry order asking the parties to indicate if a certain map, “The Overlake Subdivision Stormwater Outfall Upgrade Map,” reflected the current location of the drainage pipe and fence. The parties agreed that it did. In addition to answering the court’s query, both sides submitted additional facts and materials.

The court granted summary judgment to defendants in January 2015. At the outset of its decision, the court noted that plaintiff’s statement of disputed material facts did not comply with Vermont Rule of Civil Procedure 56, and thus, the court considered all facts asserted by defendants to be undisputed as long as they were supported by the record. As to the additional facts and materials submitted in response to the court’s entry order, the court found that neither side had submitted an updated statement of material facts and plaintiff had not even submitted an

* We emphasize that in the future, counsel must include page numbers in the printed case’s table of contents. See V.R.A.P. 30(a)(2)(B)(i) (stating that appellant must provide a table of contents that lists the parts of the record included, with references to the page of the printed case at which each part begins). affidavit authenticating the documents it submitted. Because the parties failed to comply with Rule 56, the court declined to consider the additional factual materials.

Turning to the merits, the court identified the following undisputed facts. In December 1999, William R. Sawyer and Dream Builders, Inc., conveyed Lot 28 in the Overlake Subdivision (“the property”) to Tammy Babcock, defendants’ predecessor-in-interest. The 1999 deed described the property as that depicted on a plan of land entitled, “Overlake Subdivision, Developers, W.R. Sawyer and Dream Builders, Inc., Milton,” which appeared as of record at Map Slide 298, Map 405 of the Town of Milton Land Records. The deed further provided:

The within conveyed land is subject to a drainage easement 20 feet in width leading from the cul-de-sac adjacent to said Lot and crossing said Lot to Common Land B as shown on said Plan. Said easement is for the transmission of storm water discharge to a storm water detention pond located upon Common Land B and runs to the benefit of the Town of Milton, its successors and assigns.

Sawyer expected that the town would take control of the drainage easement, but the town declined to do so. In October 2006, Sawyer conveyed the rights and title to his remaining land to plaintiff via a quitclaim deed. In September 2011, Babcock conveyed her property to defendants via a warranty deed which included the language above regarding the drainage easement.

The plan referenced in the deeds in defendants’ chain of title, Map Slide 298B, does not show a detention pond, but it does indicate the location of a “20 [foot] easement.” The 298B easement spans from the cul-de-sac to the southernmost boundary line of the property. A map prepared in June 2013 shows the current location of the drainage pipe, detention pond, and a 20 foot easement encompassing the pipe. This map shows that the drainage pipe was not installed within the 298B easement. The actual pipe originates farther west along the cul-de-sac and exits the property along the westernmost boundary line of the property, as opposed to the southernmost. The fence, which is depicted on the 2013 map, originates at the southwest corner of defendants’ house and extends southeast, crossing over the drainage pipe. The fence does not cross over the 298B easement as the fence turns southwest before doing so. Plaintiff asserted that the easement depicted on the Map Slide 298B was intended to be a pedestrian right-of-way, but it was never constructed. Neither warranty deed mentions a pedestrian easement.

The court found both warranty deeds in defendants’ chain of title unambiguous. Both stated that there was a 20 foot drainage easement crossing the property from the cul-de-sac to Common Land B “as shown on said Plan.” The deed also referenced Map 298B. Because the deed language was clear on its face, the court found no need to look to extrinsic evidence. Even if the court were to consider Sawyer’s statement the easement depicted on Map 298B was for pedestrian access or that the drainage pipe was already installed as depicted on a different map submitted by plaintiff—the Overlake Subdivision Milton Plan/Profile—that evidence contradicted the language of the deeds. The court determined, based on the undisputed material facts, that the easement depicted on Map Slide 298B was the deeded easement and that the drainage pipe was supposed to be installed within that easement. The parties agreed on where the drainage pipe and fence were currently located. Had the drainage pipe been installed within the 298B easement, the fence would not interfere with it. The court thus concluded that plaintiff could not meet its burden of showing that the fence interfered with a deeded easement, and it granted judgment to defendants.

2 Plaintiff moved for reconsideration. Plaintiff asserted that if the 1999 Babcock deed was read in light of extrinsic evidence, there was an ambiguity. Plaintiff maintained that the 1999 deed should be read in conjunction with the 2006 deed from Sawyer to plaintiff. While the 1999 deed referenced the map at Map Slide 298, the Sawyer deed referenced the map at Map Slide 358. Plaintiff reiterated its contention that the easement depicted on the 298B map was intended to be a pedestrian easement.

The court denied the motion to reconsider, finding that plaintiff raised this argument for the first time in its motion, and that it should have been raised earlier. Even if this argument had been timely raised, the court stated that it would reach the same conclusion. The court had ruled that there was nothing ambiguous about a deed referencing a recorded plan and stating that there was a drainage easement “as shown on said Plan.” There continued to be no reason to look to extrinsic evidence. The court recognized that “limited extrinsic evidence of ‘circumstances surrounding the making of the agreement’ [can be considered] in determining whether [a] writing is ambiguous.” Kipp v. Estate of Chips, 169 Vt. 102, 107 (1999) (citing Isbrandtsen v. N. Branch Corp., 150 Vt. 575, 579 (1988)). Extrinsic evidence is only relevant, however, when, in combination with the writing, it supports a different and reasonable interpretation than the one reached on the writing alone. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Woodstock Community Trust and Housing Vermont PRD
2012 VT 87 (Supreme Court of Vermont, 2012)
Nordlund v. Van Nostrand
2011 VT 79 (Supreme Court of Vermont, 2011)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)
Richart v. Jackson
758 A.2d 319 (Supreme Court of Vermont, 2000)
Kipp v. Chips Estate
732 A.2d 127 (Supreme Court of Vermont, 1999)
Brault v. Welch
2014 VT 44 (Supreme Court of Vermont, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
William Sawyer-Overlake II, LLC v. Gregory Jones and Jessica Jones, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-sawyer-overlake-ii-llc-v-gregory-jones-and-jessica-jones-vt-2015.