William J. Kleinheider v. Phillips Pipe Line Company, a Corporation

528 F.2d 837
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 29, 1976
Docket75--1206
StatusPublished
Cited by18 cases

This text of 528 F.2d 837 (William J. Kleinheider v. Phillips Pipe Line Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William J. Kleinheider v. Phillips Pipe Line Company, a Corporation, 528 F.2d 837 (8th Cir. 1976).

Opinion

HEANEY, Circuit Judge.

The appellants, present owners of fifteen separate parcels of land in Franklin County, Missouri, appeal from an order of the United States District Court for the Eastern District of Missouri holding that the appellee, Phillips Pipe Line Company, could install a third pipeline through and under the appellants’ property. The District Court had jurisdiction over the cause by virtue of diversity of citizenship pursuant to 28 U.S.C. § 1332. Its opinion is reported at 391 F.Supp. 159 (1975). We affirm.

Phillips is a common carrier in the interstate transportation of petroleum *839 products by subsurface pipelines. In 1930, the appellants’ predecessors in title and Phillips entered into easement agreements granting the latter the right to install pipelines through and under the land in question. The instruments, which are substantially identical to each other, were denominated “Right-of-Way Contract” and provide:

FOR AND IN CONSIDERATION of the sum of- Dollars ($ — ), in hand paid, the receipt of which is hereby acknowledged, * * * does hereby grant unto PHILLIPS PIPE LINE COMPANY, * * * Grantee, its successors and assigns, the right to lay, maintain, inspect, alter, repair, operate, remove and relay a pipe line, or pipe lines, for the transportation of oil and gas and products and by-products thereof, water and other substances, and such drips, valves, fittings, meters and other equipment and appurtenances as may be necessary or convenient for such operations, and to erect, maintain, inspect, repair, operate and remove, upon a single line of poles, with necessary anchorage and appurtenances, telephone, telegraph or electrical lines, or any of them, over, through, upon, under and across the following described land in Franklin County, State of Missouri, to-wit:
[land described]
It is expressly agreed that any poles set for above purposes shall be placed along property or fence lines inside the line.
Together with the rights of ingress and egress to and from said line or lines, or any of them, for the purpose aforesaid. Grantor to have the right to fully use and enjoy the above described premises, except as to the rights hereinbefore granted; and Grantee hereby agrees to pay any damages which may arise to crops, pasturage, timber, fences or buildings of said Grantor from the exercise of the rights herein granted, said damages, if not mutually agreed upon, to be ascertained and determined by three disinterested persons, one thereof to be appointed by Grantor, one by Grantee, and the third by the two so appointed, and their written determination of amount to be final and conclusive.
Should more than one pipe line be laid under this grant, at any time, an additional consideration equal to the consideration hereinabove recited, shall be paid for each line so laid after the first line.
Grantee shall bury pipe lines below plow depth.
TO HAVE AND TO HOLD said easement, rights, and rights of way unto the said PHILLIPS PIPE LINE COMPANY, its successors and assigns until said easement be exercised, and so long as any structure installed hereunder is used or remains thereon.
* * * * * $
This agreement is binding upon the heirs, executors, administrators, successors and assigns of the parties hereto.
Executed this _ day of _ 19 30 - 1

Pursuant to these contracts, an eight-inch pipeline was installed during 1930 and 1931, and a second pipeline, ten inches in diameter, was installed in 1952. The second pipeline was laid parallel to and eight feet from the original pipeline. The appellee’s right to continue to operate and maintain these pipelines pursuant to the contract terms is not challenged. The appellants’ challenge is directed at Phillips’ right to maintain and operate a third pipeline under the contract installed in 1972 and 1973. It was laid twelve feet from the original pipeline and on the side opposite the pipeline *840 installed in 1952. 2 It also is ten inches in diameter.

I.

The appellants first argue that the contracts granting the easements are uncertain and indefinite as to their terms. They seek a judicial construction declaring either that the contracts grant to Phillips no enforceable rights as to the 1973 pipeline or that the contracts intend a reasonable limitation on Phillips’ right to install additional pipelines, a limitation that would limit Phillips to the one additional pipeline installed in 1952.

A.

Each easement contract recited a sum certain, ranging from thirty-five dollars ($35.00) to one hundred and twelve dollars ($112.00), as consideration for the right to install the original pipeline. Upon the installation of additional pipelines, future consideration was required. The contract states:

[A]n additional consideration equal to the consideration hereinabove recited, shall be paid for each line so laid after the first line.

The appellants argue that this language renders the contracts uncertain as to consideration and unenforceable. The argument, however, looks beyond the four corners of the contract. See Strauch v. Coastal States Crude Gathering Co., 424 S.W.2d 677 (Tex.Civ.App.1968) (contract similar to those at issue here found to be sufficiently definite and certain). It is based upon the uncertainties that arise upon the partition of the original parcels of land subject to the easement contracts. The appellants argue that the contracts do not provide for this contingency and give no direction as to which new landowner shall receive the additional consideration or the amount thereof.

This contingency has occurred in but one instance. The property subject to right-of-way contract No. 1-108-26 is now owned by appellants Vandelicht and Roetheli. The contract provides for consideration in the sum of forty dollars ($40.00). In fulfillment of its obligations thereunder, Phillips has tendered to both Vandelicht and Roetheli the full amount required.

It must be conceded that payment of the recited consideration to both landowners is not specifically required by the contract terms. Also, it is the law of Missouri that a contract is not enforceable unless the measure of damages resulting from a breach can be determined therefrom. Burger v. City of Springfield, 323 S.W.2d 777, 783 (Mo.1959). But a contract, not certain, which is capable of being made certain by the ascertainment of the parties’ intent and the application of the canons of construction will be enforced. O’Connor v. Great Lakes Pipe Line Co., 63 F.2d 523, 525 (8th Cir. 1933); Babler v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weisel v. BEAVER SPRINGS OWNERS ASS'N, INC.
272 P.3d 491 (Idaho Supreme Court, 2012)
Beavers v. Recreation Ass'n of Lake Shore Estates, Inc.
130 S.W.3d 702 (Missouri Court of Appeals, 2004)
Spanish Oaks, Inc. v. Hy-Vee, Inc.
655 N.W.2d 390 (Nebraska Supreme Court, 2003)
Scherger v. Northern Natural Gas Co.
562 N.W.2d 328 (Court of Appeals of Minnesota, 1997)
United States v. 518.77 Acres of Land
545 F. Supp. 1246 (W.D. Missouri, 1982)
Northwest Pipeline Corp. v. Forrest Weaver Farm, Inc.
646 P.2d 422 (Idaho Supreme Court, 1982)
Steele v. Pfeifer
310 N.W.2d 782 (South Dakota Supreme Court, 1981)
M. H. Siegfried Real Estate, Inc. v. Renfrow
592 S.W.2d 488 (Missouri Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
528 F.2d 837, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-j-kleinheider-v-phillips-pipe-line-company-a-corporation-ca8-1976.