William E. Brock, Secretary of Labor v. Schwarz-Jordan, Inc.

777 F.2d 195, 12 OSHC (BNA) 1562, 1985 U.S. App. LEXIS 25064, 54 U.S.L.W. 2343
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 26, 1985
Docket84-4601
StatusPublished
Cited by12 cases

This text of 777 F.2d 195 (William E. Brock, Secretary of Labor v. Schwarz-Jordan, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William E. Brock, Secretary of Labor v. Schwarz-Jordan, Inc., 777 F.2d 195, 12 OSHC (BNA) 1562, 1985 U.S. App. LEXIS 25064, 54 U.S.L.W. 2343 (5th Cir. 1985).

Opinion

PER CURIAM.

Respondent, Schwarz-Jordan, Inc. (Schwarz-Jordan), a drywall contractor, contested a citation for violating 29 C.F.R. section 1926.451(e)(10), a regulation promulgated pursuant to the Occupational Safety and Health Act of 1970, 29 U.S.C. section 651-678 (Act). An Occupational Safety and Health Administration (OSHA) administrative law judge found the company in serious violation of 29 C.F.R. section 1926.451(e)(10). Schwarz-Jordan petitioned for discretionary review by the Occupational Safety and Health Review Commission (Commission), which, by a two-one majority, reversed the administrative law judge’s decision. Petitioner, the Secretary of Labor (Secretary), appeals that decision.

Facts

After a general schedule inspection of an office building construction site in Arlington, Texas, conducted pursuant to section 9(a) of the Act, an OSHA compliance officer cited Schwarz-Jordan, the drywall subcontractor, for a serious violation of 29 C.F.R. section 1926-451(a)(4), the general guardrail requirement for scaffolds. 1 The scaffold found in violation was a manually propelled mobile scaffold, five feet eight inches in height with a platform measuring two feet by seven feet, and was without guardrails, though it was fitted with holes for their installation. The scaffold was *196 located on the first floor of the building being constructed, near its side and next to the framework. The first floor was approximately ten and one-half feet above the ground on this side of the building. Accordingly, it was approximately sixteen feet from the scaffold platform to the ground. The scaffold was placed near a window opening which was approximately four feet high and eight feet wide. The employee using the scaffold was kneeling on its platform holding a screwgun in one hand and resting the other hand on a horizontal metal track approximately four feet above the scaffold platform.

Schwarz-Jordan contested the citation. Following a hearing, the administrative law judge stated that he was amending the citation, sua sponte, 2 to allege violation of 29 C.F.R. section 1926.451(e)(10), the specific standard for manually propelled mobile scaffolds. That regulation requires guardrails on such a scaffold which is “more than ten feet above the ground or floor.” 3 Relying upon Commission precedent, Julius Nasso Concrete Corp., O.S.H.Cas. (BNA) 1235 (Apr. 11, 1977), the administrative law judge held that the scaffold was more than ten feet above the ground or floor because the fall distance was greater than ten feet and affirmed the citation because Schwarz-Jordan’s unguarded scaffold, as it was being used, exposed its employee to a fall of more than ten feet.

On review, by a two-one majority, the Commission reversed the administrative law judge’s decision. Though accepting his factual findings, the Commission rejected the interpretation of the phrase “more than ten feet above the ground or floor” in 29 C.F.R. section 1926.451(e)(10) as fall distance. The Commission stated that the interpretation of the same phrase in Julius Nasso had turned entirely on the interrelationship of 29 C.F.R. section 1926.451(o )(7) with section 1926.451(o )(1) 4 and therefore had no precedential value for this case which involves 29 C.F.R. section 1926.-451(e)(10) for which there is no analogous interrelationship. The Commission then overruled an earlier decision, Automatic Sprinkler Corp., 7 O.S.H.Cas. (BNA) 1957 (Nov. 30, 1979), which had relied on Julius Nasso in interpreting the phrase “more than ten feet above ground or floor” in 29 C.F.R. section 1926.451(e)(10) as fall distance.

In the Commission’s view here, “[a] manually propelled mobile scaffold has its base on the ground or floor, so the natural interpretation of ‘above the ground or floor’ would be the distance between the scaffold platform and the base of the scaffold.” The Secretary appeals that decision.

Discussion

Standard of Review.

When construing a statute or regulation, the courts show great deference to the interpretation of the officers or administrative bodies charged with its administration. *197 Udall v. Tallman, 380 U.S. 1, 16-17, 85 S.Ct. 792, 801, 13 L.Ed.2d 616 (1965). The Occupational Safety and Health Act empowered the Secretary of Labor “to set mandatory occupational safety and health standards applicable to businesses affecting interstate commerce,” 29 U.S.C. section 651(b)(3), and created the “Occupational Safety and Health Review Commission for carrying out adjudicatory functions” under the Act. Id. When there is a difference of interpretation between the Secretary and the Commission, several circuits have considered the deference due to the Secretary to be diminished and have given the Commission’s decision substantial weight to be upheld if not unreasonable. Marshall v. Anaconda Co., 596 F.2d 370, 374 (9th Cir.1979); Usery v. Hermitage Concrete Pipe Co., 584 F.2d 127, 132 (6th Cir.1978); Marshall v. Western Electric, Inc., 565 F.2d 240, 244 (2d Cir.1977); Brennan v. Occupational Safety and Health Review Commission, 513 F.2d 713, 715 (8th Cir.1975). However, this Court has stated: “We have chosen to adopt a somewhat different approach to the respective roles of the Secretary and the Commission.” Marshall v. Southwestern Industrial Contractors and Riggers, Inc., 576 F.2d 42, 45 (5th Cir.1978). This Court has held that the Secretary’s interpretation “is controlling as long as it is one of several reasonable interpretations, although it may not appear as reasonable as some other.” Brennan v. Southern Contractors Service, 492 F.2d 498, 501 (5th Cir.1974); Marshall v. Southwestern Industrial Contractors and Riggers, Inc., 576 F.2d at 44. This panel is, of course, bound by these prior decisions of this Court. The standard of review they mandate is determinative of our decision here.

Reasonable Interpretation.

The language at issue in this regulation is susceptible of two reasonable interpretations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. St. Joe Resources
916 F.2d 294 (Fifth Circuit, 1990)
United States v. Dow Chemical Co.
695 F. Supp. 233 (M.D. Louisiana, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
777 F.2d 195, 12 OSHC (BNA) 1562, 1985 U.S. App. LEXIS 25064, 54 U.S.L.W. 2343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-e-brock-secretary-of-labor-v-schwarz-jordan-inc-ca5-1985.