William A. McIntyre & Sons, LLC v. Navitsky, N.

CourtSuperior Court of Pennsylvania
DecidedMay 12, 2021
Docket920 MDA 2020
StatusUnpublished

This text of William A. McIntyre & Sons, LLC v. Navitsky, N. (William A. McIntyre & Sons, LLC v. Navitsky, N.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William A. McIntyre & Sons, LLC v. Navitsky, N., (Pa. Ct. App. 2021).

Opinion

J-A29016-20

NON-PRECEDENTIAL DECISION – SEE SUPERIOR COURT I.O.P. 65.37

WILLIAM A. MCINTYRE & SONS, LLC : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : NEAL J. NAVITSKY : : Appellant : No. 920 MDA 2020

Appeal from the Judgment Entered September 4, 2020, in the Court of Common Pleas of Adams County, Civil Division at No(s): 17-S-1038.

BEFORE: DUBOW, J., KUNSELMAN, J., and COLINS, J.*

MEMORANDUM BY KUNSELMAN, J.: FILED MAY 12, 2021

Neal J. Navitsky appeals from the judgment entered in favor of William

A. Mcintyre & Sons, LLC (“Mcintyre”) in this breach of contract action. Upon

review, we affirm.

The trial court aptly summarized the facts as follows:

[McIntyre] and [Navitsky] entered into a residential construction contract where it was agreed that McIntyre would build a home for [Navitsky] at 55 Plum Run Road, New Oxford, PA. The agreed upon price for this home was for $290,521.00, with $30,000 of that amount being credited to [Navitsky] for work he agreed to do on his own. The contract included language that required signed change orders for all additional work not specifically included in the contract. As an ancillary to the contractual agreement, [Navitsky] entered into a draw schedule with his lender York Traditions Bank. Per the draw schedule, [McIntyre] would be paid in increments for work completed on the home. During the process of building [Navitsky’s] home, [McIntyre] presented ____________________________________________

* Retired Senior Judge assigned to the Superior Court. J-A29016-20

[Navitsky] with at least one verifiable change order, and credible evidence suggested as many as three change orders were presented for [Navitsky] to sign. These change orders were for extra expenses that arose because [Navitsky] requested changes to the originally agreed upon scope of work. The parties had a good and trusting working relationship. Therefore, [McIntyre] performed some or all of the requested additional items of work to [Navitsky’s] home before the change orders were signed, as [McIntyre] expected no issue because [Navitsky] specifically requested these changes. The total amount of the change order request, after deductions and credits to [Navitsky] for additional items in the original contract that [Navitsky] was now completing on his own, came to $9,375.00. [Navitsky] however, refused to sign the change orders, despite the fact that [McIntyre] completed the extra work. Therefore, [McIntyre] sought legal advice from counsel.

At the same time [McIntyre] performed the extra work, [McIntyre] also performed a substantial amount of the work covered by draw schedule four. As a result of that work, the total amount owed to [McIntyre] under draw schedule four was $41,318.37. [McIntyre] however, was never paid by [Navitsky] for any of that work as [Navitsky] did not authorize York Traditions Bank to release any of the draw four funds to [McIntyre]. [Instead, Navitsky kept that money.]

Upon advice from counsel, [McIntyre] stopped working on [Navitsky’s] home when [he] refused to sign the change order or pay for the work done. As a result of [Navitsky] failing to sign the change order, and [Navitsky] failing to pay [McIntyre] for the extra work [McIntyre] completed under the change order and draw schedule four, [McIntyre] filed suit alleging [Navitsky] breached their contract and was unjustly enriched.

Trial Court Opinion, 4/29/20, at 1-3.

Following a bench trial on January 14, 2020, the court ruled in favor of

McIntyre on its breach of contract claim in the amount of $41,318.37 for work

contracted for, but not paid to McIntyre, under draw four. Additionally, the

court found in favor of McIntyre on its unjust enrichment claim and awarded

-2- J-A29016-20

it $9,375.00 for extra work not included in the contract. McIntyre’s total

judgment was $50,693,37. Navitsky filed a post-trial motion seeking

judgment notwithstanding the verdict, or alternatively, a new trial, which the

trial court denied.

Navitsky filed this timely appeal. The trial court and Navitsky complied

with Pennsylvania Rule of Appellate Procedure 1925.

On appeal, Navitsky raises the following issues:

1. Whether the [trial court] committed an error of law and/or abused its discretion when it denied [Navitsky’s] Motion for Judgment Notwithstanding the Decision/Verdict since:

a) the evidence was insufficient to show that [Navitsky] had anticipatorily breached the contract;

b) the evidence established that [McIntyre] had materially breached the contract to preclude its contract claim; and,

c) the evidence was insufficient to support an unjust enrichment award.

2. Whether the [trial court] committed an error of law and/or abused its discretion when it denied [Navitsky’s] Motion for a New Trial, in the alternative, since:

a) the Decision was manifestly against the weight of the evidence as [McIntyre’s] proof failed to substantiate its claims of an anticipatory breach of the contract and unjust enrichment, and [McIntyre’s] material breach of the contract also precluded its contract claim; and,

b) the award was also excessive and against the weight of the evidence since [McIntyre] did not prove at trial that it was owed more under the contract than what it had already been paid.

Navitsky Brief at 5.

-3- J-A29016-20

In his first issue, Navitsky claims that the trial court erred in denying his

motion for judgment notwithstanding the verdict. We consider this matter

with the following in mind:

In reviewing a trial court's decision whether or not to grant judgment in favor of one of the parties, we must consider the evidence, together with all favorable inferences drawn therefrom, in a light most favorable to the verdict winner . . . . We will reverse a trial court's grant or denial of a judgment notwithstanding the verdict only when we find an abuse of discretion or an error of law that controlled the outcome of the case.

There are two bases upon which a judgment notwithstanding the verdict can be entered; one, the movant is entitled to judgment as a matter of law and/or two, the evidence is such that no two reasonable minds could disagree that the outcome should have been rendered in favor of the movant. With the first, the court reviews the record and concludes that, even with all the factual inferences decided adverse to the movant, the law nonetheless requires a verdict in his favor. Whereas with the second, the court reviews the evidentiary record and concludes that the evidence was such that a verdict for the movant was beyond peradventure.

Reott v. Asia Trend, Inc., 7 A.3d 830, 835 (Pa. Super. 2010) (citations and

internal brackets omitted), affirmed, 55 A.3d 1088 (2012).

In support of his claim that he was entitled to judgment notwithstanding

the verdict, Navitsky makes several arguments. First, Navitsky claims that

the evidence was insufficient to establish that he anticipatorily breached the

contract. Specifically, he argues that, because the trial court found that the

change orders were not contracts, there could not be an anticipatory breach

thereof. Navitsky’s Brief at 18. Additionally, he contends that the language

of the contract did not require Navitsky to agree to and sign any and all change

-4- J-A29016-20

order proposals unilaterally prepared by McIntyre. Id. at 19, 23, 25, 28.

Consequently, Navitsky could not have breached the contract. Id. at 28.

We agree with Navitsky that without a contract there could be no

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yacoub v. Lehigh Valley Medical Associates, P.C.
805 A.2d 579 (Superior Court of Pennsylvania, 2002)
Myers-Macomber Engineers v. M. L. W. Construction Corp.
414 A.2d 357 (Superior Court of Pennsylvania, 1979)
Commonwealth v. Cousar
928 A.2d 1025 (Supreme Court of Pennsylvania, 2007)
Lane Enterprises, Inc. v. L.B. Foster Company
710 A.2d 54 (Supreme Court of Pennsylvania, 1998)
Giant Food Stores, LLC v. THF Silver Spring Development, LP
959 A.2d 438 (Superior Court of Pennsylvania, 2008)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)
Criswell v. King
834 A.2d 505 (Supreme Court of Pennsylvania, 2003)
Samuel-Bassett v. Kia Motors America, Inc.
34 A.3d 1 (Supreme Court of Pennsylvania, 2011)
Gunn v. Grossman
748 A.2d 1235 (Superior Court of Pennsylvania, 2000)
Reott v. Asia Trend, Inc.
7 A.3d 830 (Superior Court of Pennsylvania, 2010)
Lane Enterprises, Inc. v. L.B. Foster Co.
700 A.2d 465 (Superior Court of Pennsylvania, 1997)
Reott v. Asia Trend, Inc.
55 A.3d 1088 (Supreme Court of Pennsylvania, 2012)
Commonwealth v. Clay
64 A.3d 1049 (Supreme Court of Pennsylvania, 2013)
In re Estate of Smaling
80 A.3d 485 (Superior Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
William A. McIntyre & Sons, LLC v. Navitsky, N., Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-a-mcintyre-sons-llc-v-navitsky-n-pasuperct-2021.