Wilkinson v. Blount Manufacturing Co.

47 N.E. 1020, 169 Mass. 374, 1897 Mass. LEXIS 82
CourtMassachusetts Supreme Judicial Court
DecidedOctober 23, 1897
StatusPublished
Cited by7 cases

This text of 47 N.E. 1020 (Wilkinson v. Blount Manufacturing Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilkinson v. Blount Manufacturing Co., 47 N.E. 1020, 169 Mass. 374, 1897 Mass. LEXIS 82 (Mass. 1897).

Opinion

Lathrop, J.

1. The first question presented in this case is whether on the facts found it can be said, as matter of law, that the defendant had, on June 26, 1895, waived the right to rescind the contract into which it had entered with the plaintiff on December 7,1889. By the terms of the contract, the plaintiff covenanted to pay for the goods furnished by the defendant within sixty days from their delivery. It was further provided, “ Upon the breach of any of the covenants herein contained by either party, the other party may terminate and rescind this contract.” On June 26,1895, the defendant gave written notice to the plaintiff that it rescinded the contract for breach of this covenant. It appears from the findings of fact, that at this time the plaintiff was indebted to the defendant for goods delivered under the contract during the months of January, February, March, and April, and for which the plaintiff had failed to pay within sixty "days from delivery. It further appears that the defendant had, from time to time, up to and on April 13, 1895, [376]*376accepted, without protest or reservation, payment for all goods delivered to the plaintiff before January 1, 1895. It is only as to these goods so settled for that the decree states that the defendant had waived its right to rescind the contract. We do not understand that the decree in favor of the plaintiff proceeds upon the ground of waiver; but, as the plaintiff contends that there was a waiver, we will briefly consider the question.

As the goods were to be furnished from time to time, there was imposed a continuing liability to pay for each lot within sixty days from delivery thereof. Undoubtedly if the defendant received payment for any lot after the amount was due, it could not rescind the contract for the default in paying for that lot. But a waiver of one breach cannot be considered a waiver of a subsequent breach.

In Thompson v. Knickerbocker Ins. Co. 104 U. S. 252, 259, an action on a policy of insurance, the defence was that the policy had ceased to be of effect because an annual premium, for which in part a note had been given, had not been paid, the policy containing a clause that the omission to pay the annual premium on the day named should cause the policy to be void. The plaintiff filed a replication, setting up a usage and custom of the defendant not to demand punctual payment, but to give thirty days’ grace; that the defendant had repeatedly done so with the plaintiff and others, and that this led the plaintiff to rely on such leniency in this case. This replication was held to be bad, and it was said by Mr. Justice Bradley, in delivering the opinion of the court: “ This was a mere matter of voluntary indulgence on the part of the company, or, as the plaintiff herself calls it, an act of leniency.’ It cannot be justly construed as a permanent waiver of the clause of forfeiture, or as implying any agreement to waive it, or to continue the same indulgence for the time to come.” See also Bleecker v. Smith, 13 Wend. 530, 534; Williams v. Dakin, 22 Wend. 201, 209; Hunter v. Daniel, 4 Hare, 420; Muston v. Gladwin, 6 Q. B. 953; Flower v. Peck, 1 B. & A. 428.

Further, on the question of waiver, the bill alleges that, upon receipt of the notice sent by the defendant rescinding the contract for non-payment of the goods within sixty days, the plaintiff immediately wrote and delivered to the defendant a letter, [377]*377enclosing a check for the full amount due, “ which payment was duly received and receipted for by the defendant.” This is denied by the answer. It would seem that if the plaintiff, immediately after he received the notice, paid what was due, and the defendant received the money, this would be a waiver of the breach, unless it gave notice that it did not intend to waive its right to terminate the contract. See Tuttle v. Bean, 13 Met. 275; Collins v. Canty, 6 Cush. 415; Kimball v. Rowland, 6 Gray, 224; Miller v. Prescott, 163 Mass. 12; Hammacher v. Wilson, 26 Fed. Rep. 239, 241; Platt v. Fire Extinguisher Manuf. Co. 59 Fed. Rep. 897.

But the decree does not proceed upon this ground, and the finding of fact is merely that the plaintiff in his letter in reply to the notice “ inclosed a bank check for the amount then due and payable, according to the books of both parties, for all such door checks not paid for as had been delivered to him sixty-days or more previously.” It is not found that the defendant received the check, or what became of it. For does it appear whether the defendant, if it received it, took it conditionally or unconditionally. What is stated is not enough to amount to a waiver.

2. The decree further states that the defendant, on June 27, 1894, made an agreement with the Corbin Company of Connecticut, with reference to said patents and said patented articles, and that the making of this was a breach of the defendant’s contract with the plaintiff, and caused him damage; that, on June 13, 1895, the defendant made an agreement with reference to said patents and said patented articles and said Corbin Company contract, with the Yale and Towne Manufacturing Company of Connecticut, and that the making of this agreement by the defendant was a breach by the defendant of its contract with the plaintiff, and caused the plaintiff damage; and that, by committing these breaches of its contract of December 7, 1889, for any breach thereof by the plaintiff committed after the defendant had itself broken the agreement, the defendant on June 26, 1895, had no right to rescind said agreement.

It appears by the findings of fact that the goods contemplated by the contract of December 7,1889, were door checks; and that there was upon the market a competing door check known as [378]*378the Corbin door check, manufactured by P. and F. Corbin, a Connecticut corporation. The Corbin check involved some of the material features of the Blount check; and during a considerable time, down to June 27,1894, litigation was in progress between the defendant and the Corbin Company as to the patents used in their respective door checks. On June 27, 1894, the defendant, without the plaintiff’s knowledge, entered into a written contract with the Corbin Company, and the provisions of that contract were carried out by the parties thereto; and under the arrangement thus made, the Corbin Company was allowed by the defendant to sell the Corbin door check in New England, in competition with the sales there by the plaintiff of the Blount check, to the damage of the plaintiff.

By the terms of the agreement between the defendant and the Corbin Company, the parties agreed to share between them the profits arising from the manufacture and sale of liquid door checks. The defendant also, reciting that it was the owner of certain letters patent, licensed the “ Corbin Company, its successors and assigns, during the life of this agreement, to make, use, and sell the inventions and improvements described and claimed in said letters patent, and each of them.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milona Corp. v. Piece O'Pizza of America Corp.
300 N.E.2d 926 (Massachusetts Appeals Court, 1973)
Whitehouse Restaurant, Inc. v. Hoffman
68 N.E.2d 686 (Massachusetts Supreme Judicial Court, 1946)
Canadian Steel Foundries, Ltd. v. Thomas Furnace Co.
203 N.W. 355 (Wisconsin Supreme Court, 1925)
National Contracting Co. v. Vulcanite Portland Cement Co.
78 N.E. 414 (Massachusetts Supreme Judicial Court, 1906)
Merrigan v. Hall
56 N.E. 605 (Massachusetts Supreme Judicial Court, 1900)
Stromberg v. Western Telephone Construction Co.
86 Ill. App. 270 (Appellate Court of Illinois, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
47 N.E. 1020, 169 Mass. 374, 1897 Mass. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilkinson-v-blount-manufacturing-co-mass-1897.