Wiley v. San Pedro & Canon del Agua Co.

4 N.M. 343
Procedural entryThis page is a short order in Wiley v. San Pedro & Canon del Agua Co.. Read the opinion of the Court — 5 N.M. 111
New Mexico Supreme Court·Decided January 15, 1889·Published

Opinion

Long, C. J.

Solon L. Wiley, the appellant in this court, filed in the court below his bill in chancery for an enforcement of an alleged mechanic’s lien upon the property described in the bill, for work done and materials furnished, amounting, as alleged, to $127,522.60. To this bill a demurrer was interposed, the same was sustained, and the cause dismissed. The action of the court in sustaining the demurrer is the only point necessary to be considered. The bill alleged that the defendant company entered into a contract in writing, dated April 21,1880, a copy of which is made a part of this bill, whereby, among other things, it was agreed that plaintiff should construct for the company a system of water-works, which should include two reservoirs on the Sandia mountains, in New Mexico, with a line of wrought-iron pipes from the reservoir to the company’s works. The complainant avers that for this work, which is more fully described in the bill, he was to receive $400,000, to be paid in installments. Complainant avers that under such contract he entered upon its completion, performed, labored, and furnished materials, in all worth over $127,000, and that the work was discontinued on the 24th day of July, A. I). 1882. He avers, further, that no work was done after that date; and" that on the 22d day of September, 1883, complainant filed for record, both with the county recorder of Santa Fe and also of Bernalillo county, a claim, which is fully described in the bill, to establish a mechanic’s lien on the defendants’ real estate. Other averments are also made, but it is not necessary to give them, as the case must be determined upon a question which such averments in no way affect, except as they are further stated.

It will be observed that over one year intervened between the date when the last work was done under the contract and the date when the lien was filed. Section 1524 of the Compiled Laws requires that the claim and statement which constitute the lien shall be filed “within 60 days after the completion of the contract.” So, if the contract either was completed at the date when the work was discontinued, or never was completed, in either case there could be no lien, because of the delay in filing the statement required by that section. The complainant in his bill seeks to obviate this objection to the validity of his lien upon the theory that a contract in writing was entered into by the plaintiff and the company, whereby the work was discontinued by such.agreement, but was to be again resumed by the plaintiff after the expiration of 90 days from notice that the company desired him to renew the work; and by the averment that he never was so notified, though always ready, able, and willing to perform; and that after waiting a reasonable time for such notice he elected to treat the contract as performed, and filed his lien. The appellee contends, on the contrary, that the bill of complaint fails entirely to show that there ever was any contract whatever between the complainant and the company for such extension of time or a suspension of the work. An examination of the averments of the bill on this point is necessary.

All the averments which relate to this point are as follows: “Tour orator further states that by the terms of said contract said reservoir and water-works were to be completed within six months from the date of said contract; and your orator entered upon said work, and was then and there ready, willing, and able to perform and complete the same, in the time and manner required and specified in the said contract; and that, to-wit, on July 14, A. D. 1882, your orator had completed a large portion of said work, and furnished a large part of the material required therefor, in pursuance of said contract, and was then and there ready, able, and willing to fully perform and complete the same; and that on said date said defendant company made, executed, and delivered to your orator a written agreement, a copy of which, marked ‘B,’ is filed herewith, and prayed to be considered as a part hereof; and thereby said company stipulated and agreed that your orator might and should postpone the completion of said contract; and that your orator should be, and thereby was, released from any right of action which might accrue to said company, and any damages by reason of such part postponement of said work under said contract; and it was thereby agreed that your orator should and would again enter upon the completion of said contract at once, upon the expiration •of three months after being notified so to do; and your orator states that in pursuance of said last-mentioned agreement, to-wit, July 24, 1882, he did discontinue work upon and postponed the completion of said contract, and that from that time hitherto your orator has been at all times ready and willing to fully complete the said contract; but your orator avers the said defendant has wholly failed and neglected to notify or permit your orator to enter upon or •complete said contract; and your orator further avers that on September 22, 1883, in consequence of the premises, and by reason of the said failure, neglect, and refusal on the part of the said defendant company to notify or permit your orator to enter upon and complete the portion of said work under said contract which remained unperformed, on said July 24, 1882, and a reasonable and sufficient time therefor having then and there elapsed, your orator •elected and determined to declare said contract ended and terminated, as he lawfully might; and your orator, September 22, 1883, and within 90 days .after the completion of said contract on his part, did file for record, ” etc.

The writing to which reference is made in the foregoing averments is as follows:

“Greenfield, Mass., July 14,1882.
“8. L. Wiley, Esq.: The San Pedro and Canon del Agua Company consent to your postponing the present completion of its contract with you as to dams in the Sandia mountains, and pipe-line from same to the company’s placers, provided you agree that you will again enter upon the completion of the same at once, upon the expiration of three months after being notified by the company to do so. You are also released, provided this extension is entered into, from all rights of action which the company may obtain against you for any •damage that may during any such discontinuance accrue to the said pipe-line and dams by reason of your discontinuing work and care thereon and thereof; the rights of both the company and yourself being and remaining, to all intents and purposes, as though no discontinuance had been agreed upon. Your agreement hereto being evidenced by your signature. This agreement being in full force and effect from the date when said Burham was authorized to enter into such an extension.
[Signed] “San Pedro and Canon del Agua Company,
“By Walter Burham, Yiee-President.
“Accepted.”

Although the word “Accepted” is written on the paper called in the bill of complaint an “agreement,” neither such word nor the paper is signed by Solon Wiley. His name does not anywhere appear on the paper, except as it is addressed to him. It is not averred in the bill that he in fact did accept it, or that the defendant company ever had the slightest knowledge or notice that he accepted the contract, or regarded himself in any mode under obligation to respect its provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Wiley v. San Pedro & Canon del Agua Co., 4 N.M. 343 (N.M. 1889).

4 N.M. 343 (Wiley v. San Pedro & Canon del Agua Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McDonald v. Bewick
16 N.W. 240 (Michigan Supreme Court, 1883)