Wilds v. Universal Resources Corp.

1983 OK 35, 662 P.2d 303, 76 Oil & Gas Rep. 291, 1983 Okla. LEXIS 167
CourtSupreme Court of Oklahoma
DecidedApril 12, 1983
Docket53283
StatusPublished
Cited by15 cases

This text of 1983 OK 35 (Wilds v. Universal Resources Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilds v. Universal Resources Corp., 1983 OK 35, 662 P.2d 303, 76 Oil & Gas Rep. 291, 1983 Okla. LEXIS 167 (Okla. 1983).

Opinion

SIMMS, Vice Chief Justice:

Eldon T. Wilds and Bonnie B. Wilds, lessors, [hereafter the Wilds] brought this action to cancel an oil and gas lease and to quiet title against Universal Resources Corporation, lessee [hereafter Universal], alleging the lease had terminated at the end of the primary term because of Universal’s failure to commence and prosecute drilling operations with due diligence. The trial court sustained Wild’s motion for summary judgment from which order Universal appealed.

The Court of Appeals, Division I, reversed the trial court, and remanded with instructions that the trial court set aside the judgment and enter judgment for Universal. Wilds petitioned for a writ of cer-tiorari and it was granted. Though the Court of Appeals found that the record supported the lower court’s award of summary judgment for Wilds under the theory argued by the parties, it reversed the decision because in its view the parties misconstrued the elements necessary to entitle a lessor to the equitable relief of cancellation.

The lease was entered into on March 5, 1975, for a primary term of three years with a provision that unless lessees commenced drilling operations prior to March 5, 1978 or paid rental, the lease would terminate. Prior to the expiration of the primary term, lessee Universal cleared location. Two days before the primary term expired, Universal entered the drilling unit with a rathole drilling rig, a device used for drilling shallow holes to set conductor pipe. This rathole rig, capable of drilling to 150 feet total at the rate of 60 to 80 feet per day, was maintained with one employee for eight hours each day until March 26, 1978. Between March 3 and March 26, 1978, the rathole rig drilled to 67 feet; the drilling company was instructed by Universal to drill only a few feet each day. Apparently a drilling rig was available, but lessee made a business decision to use the rig on another location. On March 24, the Wilds made written demand of Universal for the lease. On March 27, Universal moved a drilling rig onto the unit and commenced actual drilling.

In sustaining Wilds’ motion for summary judgment, the trial court found that Universal’s activities did not constitute good faith commencement of drilling operations and therefore the lease terminated automatically. In reversing this decision, Wilds argue, the Court of Appeals has erred in its *305 holding that the lease could not be cancelled because the lessor failed to give notice of default and opportunity for compliance under an implied covenant to develop fully. The breach of an implied covenant and the necessity of notice were neither asserted in the trial court nor on appeal.

The precise question for review, then, is whether an implied covenant was at issue, necessitating notice before cancellation of the lease.

The lease provision at issue states:

“This lease shall remain in force for a term of three years from date (herein called the primary term) and as long thereafter as oil, gas, casinghead gas, cas-inghead gasoline, or any of the products covered by this lease is or can be produced from said land or from land with which said land is pooled, or operations are being continued as hereinafter provided.”
“It is expressly agreed that if lessee shall commence operations for the drilling of a well at any time while this lease is in force, this lease shall remain in force and its term shall continue for so long as such operations are prosecuted and, if production results therefrom, then so long as such production may continue.”

The foregoing provision contains a typical “unless” clause as distinguished from an “or” clause; the distinction is significant in determining the manner of terminating the lessee’s interest and the basis of lessee’s obligation:

“The unless clause is one of special limitation that terminates ipso facto according to its terms upon failure to drill or pay. The lessee does not promise either to drill or pay, but if the lease is to continue, he must do one or the other. The or clause is one of condition subsequent that requires affirmative action by the lessor or lessee for termination. The lessee affirmatively covenants to drill or pay * *. The ‘or’ clause is seldom used today * *.” Sullivan, Handbook of Oil and Gas Law, 105-106 (1955). See, also, 2 Summers, Oil and Gas (perm, ed.) 397-399, § 337.

The provision can also be denominated a commence provision, whereby the primary term of the lease can be extended by drilling operations commenced within the primary term and completed afterwards. Simons v. McDaniel, 154 Okl. 168, 7 P.2d 419 (1932). In State v. Carter Oil Co., we defined a commence type lease:

“Where the lease involved is a ‘completion’ lease, a well must be completed within the primary term thereof or when the lease involved is a ‘commence’ lease, a well must be commenced before and completed with due diligence after the primary term fixed therein, producing oil or gas in paying quantities.” (emphasis supplied) Okl., 336 P.2d 1086, 1095.

In order to satisfy the terms of the commencement provision, Universal has to show not only that operations were commenced, but that operations were prosecuted with due diligence. In other words, a lessee will not be allowed simply to go through the motions by doing preparatory activity to satisfy the commencement requirement and then delay. Unless changed by contract a commencement clause of an oil and gas lease has been generally interpreted to mean that operations for the drilling of a well and not the actual drilling must be commenced prior to the end of the primary term with good faith intention of completing the operation. Smith v. Gypsy Oil Co., 130 Okl. 135, 265 P. 647 (1928). In The Law of Oil and Gas, § 32.3, p. 67, Professor Kuntz explains the two-pronged requirement for commencement:

“A lessee has commenced a well if he has conducted operations on the land in good faith preparation for the drilling of a well for oil or gas and has continued the operation in good faith and with due diligence.”

The Court of Appeals explained the requirement of due diligence as arising from an implied covenant, while lessor Wilds argues that the requirement is implicit in the drilling clause. Both parties agreed that operations for drilling had begun, thus satisfying the first prong of the test of commencement; the question is whether *306 Universal’s lack of due diligence during the 3 weeks after the end of the primary term caused the lease to terminate automatically or whether notice was required by the lessor under an implied covenant to develop fully. 1

Case law and commentators agree that under an unless type commencement clause, the lessee must be in good faith in beginning and continuing his operation; otherwise, the lease is lost, (in effect, the “commencement” in its two-pronged sense has never taken place.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neely v. First State Bank, Harrah
1998 OK 119 (Supreme Court of Oklahoma, 1998)
King v. Halliburton Co.
1991 OK CIV APP 34 (Court of Civil Appeals of Oklahoma, 1991)
Large v. Acme Engineering & Manufacturing Corp.
1990 OK 34 (Supreme Court of Oklahoma, 1990)
Anderson v. Northwestern Electric Cooperative
1988 OK 81 (Supreme Court of Oklahoma, 1988)
Buckner v. General Motors Corp.
1988 OK 73 (Supreme Court of Oklahoma, 1988)
Hinson v. Cameron
1987 OK 49 (Supreme Court of Oklahoma, 1987)
Krebsbach v. Henley
1986 OK 58 (Supreme Court of Oklahoma, 1986)
Vance by and Through Vance v. Thomas
1986 OK CIV APP 3 (Court of Civil Appeals of Oklahoma, 1986)
Pic Oil Co., Inc. v. Grisham
1985 OK 34 (Supreme Court of Oklahoma, 1985)
Mann v. State Farm Mutual Automobile Insurance Co.
1985 OK 27 (Supreme Court of Oklahoma, 1985)
Zaragosa v. Oneok, Inc.
700 P.2d 662 (Court of Civil Appeals of Oklahoma, 1985)
Winn v. Nilsen
1983 OK 91 (Supreme Court of Oklahoma, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
1983 OK 35, 662 P.2d 303, 76 Oil & Gas Rep. 291, 1983 Okla. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilds-v-universal-resources-corp-okla-1983.