Wildhorse Resources Management Company, LLC v. G&C Construction International, LLC

CourtDistrict Court, S.D. Texas
DecidedOctober 31, 2019
Docket4:18-cv-02456
StatusUnknown

This text of Wildhorse Resources Management Company, LLC v. G&C Construction International, LLC (Wildhorse Resources Management Company, LLC v. G&C Construction International, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wildhorse Resources Management Company, LLC v. G&C Construction International, LLC, (S.D. Tex. 2019).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION WILDHORSE RESOURCES § MANAGEMENT COMPANY, LLC, § § Plaintiff, § § v. § CIVIL ACTION H-18-2456 § G&C CONSTRUCTION INTERNATIONAL, LLC, § § Defendant. § MEMORANDUM OPINION AND ORDER Pending before the court are plaintiff Wildhorse Resources Management Company, LLC’s (“Wildhorse”) partial motion for summary judgment (Dkt. 19), defendant G&C Construction International, LLC’s (“G&C”) response in opposition (Dkt. 26), Wildhorse’s reply (Dkt. 31), G&C’s motion for leave to file sur-reply (Dkt. 33), and Wildhorse’s objections (Dkt. 37). Having considered the motion, responses, evidentiary record, and applicable law, the court finds that Wildhorse’s motion should be DENIED.1 I. BACKGROUND This is a declaratory judgment action arising out of an August 15, 2016 oilfield accident in which G&C’s employee, Dalarius Qualls, was injured while transporting saltwater to one of Wildhorse’s disposal wells in Louisiana. Dkt. 19 at 7; Dkt. 26 at 2. Qualls sued Wildhorse in 1 Although Wildhorse purports to object to G&C’s motion for leave to file sur-reply, Wildhorse offers no reasons why G&C’s motion should not be granted. Instead, Wildhorse simply responds to G&C’s arguments. See Dkt. 37. Accordingly, the court GRANTS G&C’s motion (Dkt. 33) and Wildhorse’s request in the alternative to file a sur-reply of its own. However, for the reasons explained below, these arguments are moot since the court finds that Louisiana law controls. Louisiana state court (“the underlying suit”).2 Dkt. 19-1. Wildhorse instituted the instant suit in Texas state court on May 16, 2018, seeking a declaration that, under the parties’ Master Service Agreement (“MSA”), G&C is contractually obligated to defend and indemnify Wildhorse. Dkt. 19-3 at 5. Specifically, Wildhorse asked the court to find that the MSA obligates G&C to defend and

indemnify Wildhorse in the underlying suit. Id. Wildhorse also requested attorney’s fees and costs. Id. On May 23, 2018, during mediation, one of Wildhorse’s insurance carriers settled with Qualls. Dkt. 27 at 34. G&C removed the suit to this court on July 17, 2018. Dkt. 1. Wildhorse filed its motion for partial summary judgment on March 7, 2019. Dkt. 19. The relevant portions of the MSA are the recitals, choice of law, and indemnity provisions. The recitals refer to Wildhorse as the “Company” and G&C as the “Contractor.” Dkt. 19-2 at 1. Paragraph 24 discusses the parties’ choice of law:

a. THIS AGREEMENT WILL BE INTERPRETED UNDER THE LAWS OF THE STATE OF TEXAS WITHOUT GIVING EFFECT TO ITS CONFLICTS OF LAW PRINCIPLES . . . . b. THE PARTIES RECOGNIZE THAT WORK PERFORMED UNDER THIS AGREEMENT MAY BE PERFORMED IN MULTIPLE AND VARIOUS JURISDICTIONS. HOWEVER, THE PARTIES GENERALLY PREFER AND AGREE THAT, TO THE EXTENT POSSIBLE, THIS AGREEMENT SHALL BE CONSTRUED AND ENFORCED CONSISTENTLY IN ACCORDANCE WITH ITS EXPRESS TERMS AND THAT THE PARTIES’ FIRST PREFERENCE OF THE LAW TO BE APPLIED SHALL BE GIVEN EFFECT IF AT ALL POSSIBLE. Id. ¶ 24. Paragraph 8 of the MSA discusses the parties indemnity obligations. Specifically, paragraph 8(b) provides: b. Contractor’s Indemnity – Personal Injury. Contractor will release, protect, Defend, indemnify, and hold harmless Company Group from and against any and all Claims for personal injury, bodily injury, illness or death of any member of 2 The underlying suit is Qualls v. Wildhorse Resources, LLC, No. C651811, Section 26, 19th Judicial District Court, Parish of East Baton Rouge, Louisiana. 2 Contractor Group, which arise out of, relate to, or are connected with this Agreement. Id. ¶ 8(b). Wildhorse owes G&C an identical indemnity obligation for claims against G&C by any Wildhorse personnel. See id. ¶ 8(d). Paragraph 8(f) further provides: f. Express Negligence. THE RELEASE, DEFENSE AND INDEMNITY OBLIGATIONS CONTAINED IN SECTIONS 8(b) THROUGH 8(e) SHALL APPLY EVEN IF CAUSED, IN WHOLE OR IN PART, BY . . . NEGLIGENCE OR OTHER FAULT, WHETHER PASSIVE OR ACTIVE, . . . BUT NOT TO THE EXTENT CAUSED BY OR RESULTING FROM THE GROSS NEGLIGENCE OR WILLFUL MISCONDUCT . . . . BOTH PARTIES AGREE THAT THIS STATEMENT COMPLIES WITH THE REQUIREMENT KNOWN AS THE EXPRESS NEGLIGENCE RULE TO EXPRESSLY STATE IN A CONSPICUOUS MANNER TO AFFORD FAIR AND ADEQUATE NOTICE THAT THIS SECTION 8 HAVE [sic] PROVISIONS REQUIRING ONE PARTY TO BE RESPONSIBLE FOR THE NEGLIGENCE , STRICT LIABILITY, OR OTHER FAULT OF ANOTHER PARTY. Id. ¶ 8(f). Finally, the parties included “SPECIAL PROVISIONS FOR LOUISIANA” which provide that “[i]f, and only if, it is determined that the Parties’ defense and indemnity rights and obligations hereunder are subject to the application of the State of Louisiana’s Oilfield Anti- Indemnity Act, LSA-R.S. 9:2780 (the “LOIA”), then the provisions of this Section 8(i) shall apply[.]” Id. ¶ 8(i). Paragraph 8(i)(iii) states that these provisions “are intended to comply with the provisions [sic] Marcel v. Placid Oil Co., 11 F.3d 563 (5th Cir. 1994),” while paragraph 8(i)(iv) clarifies that “nothing in this Section 8(i) shall affect the Parties’ choice of law set forth in Section 24 below.” Id. ¶ 8(i). The parties agree that three issues are before the court in Wildhorse’s partial motion for summary judgment: (1) whether Texas or Louisiana law governs interpretation of parties’ rights under the MSA; (2) whether G&C is obligated to defend and indemnify Wildhorse in the underlying suit; and (3) whether Wildhorse qualifies as an additional insured under G&C’s insurance. Compare Dkt. 19 at 7 (setting forth issues before the court), with Dkt. 26 at 1–2 (same). 3 II. LEGAL STANDARD Summary judgment is proper only when “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “[O]n summary judgment, ‘the evidence of the nonmovant is to be believed, and all justifiable

inferences are to be drawn in his or her favor.’” Waste Mgmt. of La., L.L.C. v. River Birch, Inc., 920 F.3d 958, 972 (5th Cir. 2019) (quoting Tolan v. Cotton, 572 U.S. 650, 656, 134 S.Ct. 1861, 188 L. Ed. 2d 895 (2014) (per curiam)). With regards to this partial motion for summary judgment, there are no disputed facts, only legal questions. III. ANALYSIS A. Conflict of Laws Wildhorse asserts that this dispute—the question of whether G&C is obligated to indemnify

Wildhorse for its settlement with Qualls3—is governed by Texas law, because that is the law chosen by the parties in their MSA. Dkt. 19 at 8–15. G&C asserts that, despite the MSA’s choice of law provision, Louisiana law governs “because application of Texas law . . . would be contrary to a fundamental policy of Louisiana—a state with a materially greater interest in this dispute than Texas.” Dkt. 26 at 7. The court “need not decide which state’s laws apply unless those laws conflict.” Sonat Expl. Co. v. Cudd Pressure Control, Inc., 271 S.W.3d 228, 231 (Tex. 2008) (citing Compaq Comput. Corp. v. Lapray, 135 S.W.3d 657, 672 (Tex. 2004)).

3 Because it is undisputed that “G&C did provide a defense for Wildhorse, through G&C’s insurers, for the entire duration of the Underlying Lawsuit” (Dkt. 26 at 1), the issue of whether G&C owes a duty to defend Wildhorse is moot. However, “a case may be moot as to some or most issues but viable as to others.” New Orleans S.S. Ass’n v. Plaquemines Port Harbor & Terminal Dist., 816 F.2d 1074, 1077 (5th Cir. 1987) (citing Fla. Bd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marcel v. Placid Oil Co.
11 F.3d 563 (Fifth Circuit, 1994)
Federal Deposit Insurance v. Massingill
24 F.3d 768 (Fifth Circuit, 1994)
Roberts v. Energy Development Corp.
235 F.3d 935 (Fifth Circuit, 2000)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Fisher v. Metropolitan Life Insurance Company
895 F.2d 1073 (Fifth Circuit, 1990)
Compaq Computer Corp. v. Lapray
135 S.W.3d 657 (Texas Supreme Court, 2004)
Sonat Exploration Co. v. Cudd Pressure Control, Inc.
271 S.W.3d 228 (Texas Supreme Court, 2008)
Silverman v. MIKE ROGERS DRILLING CO., INC.
34 So. 3d 1099 (Louisiana Court of Appeal, 2010)
Ken Petroleum Corp. v. Questor Drilling Corp.
24 S.W.3d 344 (Texas Supreme Court, 2000)
Chesapeake Operating, Inc. v. Nabors Drilling USA, Inc.
94 S.W.3d 163 (Court of Appeals of Texas, 2002)
DeSantis v. Wackenhut Corp.
793 S.W.2d 670 (Texas Supreme Court, 1990)
Maxus Exploration Co. v. Moran Bros., Inc.
817 S.W.2d 50 (Texas Supreme Court, 1991)
Dresser Industries, Inc. v. Page Petroleum, Inc.
853 S.W.2d 505 (Texas Supreme Court, 1993)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
CMA-CGM (America), Inc. v. Empire Truck Lines, Inc.
416 S.W.3d 495 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Wildhorse Resources Management Company, LLC v. G&C Construction International, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wildhorse-resources-management-company-llc-v-gc-construction-txsd-2019.