This text of WildEarth Guardians v. Mountain Coal Company (WildEarth Guardians v. Mountain Coal Company) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WildEarth Guardians v. Mountain Coal Company, (D. Colo. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO Judge Raymond P. Moore

Civil Action No. 20-cv-01342-RM-STV

WILDEARTH GUARDIANS, SIERRA CLUB, CENTER FOR BIOLOGICAL DIVERSITY, and HIGH COUNTRY CONSERVATION ADVOCATES,

Plaintiffs,

v.

MOUNTAIN COAL COMPANY, and ARCH RESOURCES,

Defendants. ______________________________________________________________________________

ORDER ______________________________________________________________________________

This citizen enforcement suit is before the Court on the Recommendation of United States Magistrate Judge Scott T. Varholak (ECF No. 70) to grant Defendants’ Motion to Dismiss the Complaint Pursuant to F.R.C.P. 12(b)(6) Based on the Statute of Limitations (ECF No. 18). Plaintiffs have filed Objections to the Recommendation (ECF No. 75), and Defendants have filed a Response (ECF No. 76). For the reasons below, the Court sustains the objection that Plaintiffs’ claim regarding Defendants’ lack of a proper operating permit for the West Elk coal mine is not barred on statute of limitations grounds. The Recommendation is otherwise adopted and incorporated into this Order by reference. See 28 U.S.C. § 636(b)(1)(B); Fed. R. Civ. P. 72(b). I. LEGAL STANDARDS Pursuant to Fed. R. Civ. P. 72(b)(3), this Court reviews de novo any part of the magistrate judge’s recommendation to which a proper objection is made. An objection is proper only if it is sufficiently specific “to focus the district court’s attention on the factual and legal issues that are truly in dispute.” United States v. One Parcel of Real Prop., 73 F.3d 1057, 1060 (10th Cir. 1996). “In the absence of timely objection, the district court may review a magistrate’s report under any standard it deems appropriate.” Summers v. Utah, 927 F.2d 1165, 1167 (10th Cir. 1991). In evaluating a motion to dismiss under Fed. R. Civ. P. 12(b)(6), a court must accept as true all well-pleaded factual allegations in the complaint, view those allegations in the light most

favorable to the plaintiff, and draw all reasonable inferences in the plaintiff’s favor. Brokers’ Choice of Am., Inc. v. NBC Universal, Inc., 757 F.3d 1125, 1136 (10th Cir. 2014); Mink v. Knox, 613 F.3d 995, 1000 (10th Cir. 2010). The complaint must allege a “plausible” right to relief. Bell Atl. Corp. v. Twombly, 550 U.S. 544, 569 n.14 (2007); see also id. at 555 (“Factual allegations must be enough to raise a right to relief above the speculative level.”). Conclusory allegations are insufficient, Cory v. Allstate Ins., 583 F.3d 1240, 1244 (10th Cir. 2009), and courts “are not bound to accept as true a legal conclusion couched as a factual allegation,” Twombly, 550 U.S. at 555 (quotation omitted). “A statute of limitations defense may be appropriately resolved on a Rule 12(b) motion when the dates given in the complaint make clear

that the right sued upon has been extinguished.” Sierra Club v. Okla. Gas & Elec. Co., 816 F.3d 666, 671 (10th Cir. 2016) (quotation omitted). II. BACKGROUND Plaintiffs contend that Defendants are operating the West Elk coal mine without two air pollution permits required by the Clean Air Act (“CAA”): a Prevention of Significant Deterioration (“PSD”) construction permit and a Title V operating permit. Although the mine has been in operation since the 1980s, Defendants began a substantial expansion in January 2020, prompting a notice letter under 42 U.S.C. § 7604(b) and this lawsuit. Defendants’ Motion to Dismiss was referred to the magistrate judge, who held a hearing and ordered supplemental briefing. Taking the allegations in the Complaint as true and also considering the attached Notice Letter (ECF No. 1 at 30-44), the magistrate judge determined that a PSD permit was not required under the circumstances and that Plaintiffs’ claim based on Title V was barred by the

applicable five-year statute of limitations. Plaintiffs object to both determinations. III. ANALYSIS A. PSD Permit Whether Defendants needed a PSD permit to proceed with their expansion of the West Elk mine turns on whether the Complaint sufficiently alleges that the West Elk mine was not a “major stationary source” of regulated emissions at that time. As explained in the Recommendation, under Colorado’s CAA framework, a PSD permit is required for “any physical change that would occur at a stationary source not otherwise qualifying as a major stationary source . . . if the change would constitute a major stationary source by itself.” 5 Colo.

Code Regs. § 1001-5:3D.II.A.25.c (emphasis added). But both the Complaint and the Notice Letter allege the mine’s emissions exceeded levels for major stationary sources prior to the expansion. As a result, Plaintiffs are now in the position of trying to identify contrary allegations that would establish a plausible inference that the mine did not already qualify as a major stationary source at the time of the expansion. Their efforts are unsuccessful. Plaintiffs point to allegations about an “air permit” Defendants renewed in 2010 that is not a major source PSD permit (ECF No. 1 at ¶ 57), arguing that “[t]here is no better evidence that the Mine did not qualify as a major stationary source than its minor-source permit.” (ECF No. 75 at 18.) But the allegations pertaining to the 2010 permit are insufficient to support an inference that the mine did not qualify as a major stationary source when the expansion began in 2020, particularly where Plaintiffs have simultaneously alleged that the mine did in fact qualify as a major stationary source in the years leading up to the expansion. (See, e.g., ECF No. 1 at ¶¶ 67, 69; see also id. at 37-38.) The allegations that Defendants did not have a major source

PSD permit when the Complaint was filed (id. at ¶¶ 79, 80) are also insufficient to support such an inference. To survive a motion to dismiss, a plaintiff must nudge its claims across the line from conceivable to plausible. Khalik v. United Air Lines, 671 F.3d 1188, 1190 (10th Cir. 2012). Whatever relevance the 2010 permit has with respect to whether the mine qualified as a major stationary source in 2020, the Court finds it does not raise Plaintiffs’ right to relief above the level of speculation, especially in light of the other allegations in the Complaint and Notice Letter. The Court discerns no error in the magistrate judge’s analysis of this issue. Perhaps recognizing the inadequacy of the allegations in the Complaint, Plaintiffs urge the Court to consider other allegations “shown in referenced documents and public records.”

(ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Mink v. Knox
613 F.3d 995 (Tenth Circuit, 2010)
Cory v. Allstate Insurance
583 F.3d 1240 (Tenth Circuit, 2009)
Khalik v. United Air Lines
671 F.3d 1188 (Tenth Circuit, 2012)
Sierra Club v. Oklahoma Gas & Electric Co.
816 F.3d 666 (Tenth Circuit, 2016)
United States v. 2121 East 30th Street
73 F.3d 1057 (Tenth Circuit, 1996)
Miller v. Glanz
948 F.2d 1562 (Tenth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
WildEarth Guardians v. Mountain Coal Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wildearth-guardians-v-mountain-coal-company-cod-2021.