Wild-Fire, Inc. v. Laughlin, Unpublished Decision (3-9-2001)

CourtOhio Court of Appeals
DecidedMarch 9, 2001
DocketC.A. Case No. 2000 CA 51, T.C. Case No. 97 CV 0751.
StatusUnpublished

This text of Wild-Fire, Inc. v. Laughlin, Unpublished Decision (3-9-2001) (Wild-Fire, Inc. v. Laughlin, Unpublished Decision (3-9-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wild-Fire, Inc. v. Laughlin, Unpublished Decision (3-9-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
Wild-Fire, Inc. is appealing a judgment of the Clark County Common Pleas Court awarding it $16,733 under the theory of quantum meruit rather than the $48,132.73 which it sought for breach of contract.

Appellees, Laughlin Scanlan, Inc. (hereinafter Laughlin Scanlan) and the individual partners, Eric Laughlin and Brian Scanlan, were the general contractors for the construction of a Holiday Inn Express in London, Ohio. As the general contractor, Laughlin Scanlan sought bids from subcontractors to fulfill the hotel's electrical needs. The lowest bid was Appellant Wild-Fire, Inc (hereinafter "Wild-Fire"), who bid $81,910.00. Eric Laughlin, president of Laughlin Scanlan, testified that originally the hotel was planned to be a Super 8 motel and then the owners decided to make it a Holiday Inn Express. He testified that from the outset the hotel was a design-build project, meaning that they were using a set of stock plans which would need to be altered and he informed all of the bidders of this situation. Additionally, he had received a letter from the electric company, Ohio Edison, stating that the hotel would need three electric services, which he testified that he provided to all of the bidders, including Wild-Fire. Additionally, Mr. Laughlin testified that he had a preconstruction meeting in July of 1996 with Wayne Laughman (hereinafter "Wayne"), a Wild-Fire representative, a representative for Ohio Edison, and other subcontractors in which they discussed the fact that no gas was available at the hotel site and thus it would have to be an all electric hotel and would require three services. Mr. Laughlin's notes referencing Wayne's presence at this preconstruction meeting were admitted at trial. Additionally, Mr. Laughlin testified that when the contract was signed in August of 1996, he again went over with Wayne the need for three electric services and made notes of their discussion and stapled this to the back of the contract after he signed it. Therefore, Laughlin Scanlan assert that Wild-Fire's bid included not one electric service but three.

In contrast, Wayne and Wild-Fire's president, Nancy Shaffer, testified that Wild-Fire's bid was based on the hotel plans provided by Laughlin Scanlan, which only showed one electric service for the hotel. Additionally, Wayne testified that he never received the letter from Ohio Edison which stated three electric services were required and that he did not meet a representative of Ohio Edison until after the contract was signed and construction had begun. Both Wayne and Ms. Shaffer testified that they were not informed of the need for two additional electric services until after they had begun construction on the hotel. Therefore, Wild-Fire planned to add these two additional electric services to their price as change orders.

Additionally, Wayne testified that throughout the project either the hotel owner or Brian Scanlan would ask him to add or change services from the original design and bid. The written contract provided that all such change orders had to be in writing and pre-approved before implementing the change. However, Wild-Fire fell into the practice of performing the service and then billing later for the change order. Following this procedure, in February of 1997, three change orders were submitted and approved after the service was performed and Laughlin Scanlan paid for the change order. In March and April, Wild-Fire submitted its remaining twenty three change orders to Laughlin Scanlan. The amount Wild-Fire claimed to be owed was $48,132.73. The majority of this amount stemmed from the additional two electric services which Wild-Fire claimed were change orders and Laughlin Scanlan argued were a part of the original bid. Over the next three months Wild-Fire and Laughlin Scanlan had several meetings to attempt to resolve their dispute. As a result of these meetings, Laughlin Scanlan sent two letters to Wild-Fire which they assert were settlement proposals. One letter offered to pay Wild-Fire $16,733. This figure was based on thirteen change orders which Laughlin Scanlan stated they "approved" but had not paid amounting to $12,068.00,1 plus $4165.00 to increase Wild-Fire's base bid to the next highest bidder's price who included three electric services and two water heaters, and $500 for a third water heater. Wild-Fire refused this offer and brought suit against Laughlin Scanlan for payment of the change orders.

Wild-Fire sued Laughlin Scanlan under the theories of breach of contract and quantum meruit. A bench trial was held on May 16, 2000 and immediately following the trial, the court awarded judgment to Wild-Fire based on quantum meruit in the amount of $16,733, which it found to be the "value of the services that were rendered to the defendant and were not compensated." A separate hearing was held on Wild-Fire's request for interest and attorney fees on May 19, 2000. On June 7, 2000, Wild-Fire requested findings of fact and conclusions of law. On June 15, 2000, without ruling on Wild-Fire's request for findings of fact and conclusions of law, the trial court filed its judgment entry awarding $16,733 based on quantum meruit and denying interest and attorney fees. Wild-Fire filed this timely appeal., Appellant Wild-Fire raises three assignments of error:

1. THE TRIAL COURT ERRED BY FAILING TO PROPERLY DETERMINE THE AMOUNT OF DAMAGES AND, FURTHER, BY FAILING TO ISSUE FINDINGS OF FACT AND CONCLUSIONS OF LAW.

2. THE TRIAL COURT ERRED BY FINDING THAT DAMAGES WERE AWARDED PURSUANT TO A THEORY OF UNJUST ENRICHMENT AND NOT BREACH OF CONTRACT.

3. THE TRIAL COURT ERRED BY FAILING TO AWARD STATUTORY INTEREST AND ATTORNEY FEES PURSUANT TO OHIO REVISED CODE 4113.61, OHIO'S PROMPT PAY ACT.

A judgment of a trial court will not be reversed on appeal as being against the manifest weight of the evidence if it is supported by some competent, credible evidence going to all of the essential elements of the case. C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, syllabus, 8 O.O.3d 261. The appellate court is directed by the presumption that the findings of the trier of fact are correct. Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 79. The trier of fact is in the best position to observe witnesses and weigh their credibility. Id.

Appellant's first assignment of error:

Wild-Fire argues that the trial court erred in calculating the damages under the theory of quantum meruit. We agree.

When a court finds that a party has been unjustly enriched by an aggrieved party, the court adopts a legal fiction, quasi contract, to provide the aggrieved party a remedy, which is a claim for quantum meruit. Caras v. Green Green (June 28, 1996), Montgomery App. No. 14943, unreported. Generally, "a claim for unjust enrichment lies whenever a benefit is conferred by plaintiff upon a defendant with knowledge by the defendant of the benefit and retention of the benefit by the defendant under circumstances where it would be unjust to do so without payment." Kraft Constr. Co. v. Cuyahoga Cty. Bd. of Commrs. (1998), 128 Ohio App.3d 33, certiorari granted (1998), 83 Ohio St.3d 1434, appeal dismissed (1999), 85 Ohio St.3d 1430, quoting Donovan v. Omega World Travel, Inc. (Oct. 5, 1995), Cuyahoga App. No. 68251, unreported. The court may impose civil liability in a situation where one party retains the benefit from the labors of the other party. Shaw v. J. Pollock Co. (1992), 82 Ohio App.3d 656, 662.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burke & Associates, Inc. v. Koinonia Homes, Inc.
735 N.E.2d 479 (Ohio Court of Appeals, 1999)
Shaw v. J. Pollock & Co.
612 N.E.2d 1295 (Ohio Court of Appeals, 1992)
Soloman v. Excel Marketing, Inc.
682 N.E.2d 724 (Ohio Court of Appeals, 1996)
Sammarco v. Anthem Insurance Companies, Inc.
723 N.E.2d 128 (Ohio Court of Appeals, 1998)
Kraft Construction Co. v. Cuyahoga County Board of Commissioners
713 N.E.2d 1075 (Ohio Court of Appeals, 1998)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Sammarco v. Anthem Insurance Companies, Inc.
719 N.E.2d 963 (Ohio Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Wild-Fire, Inc. v. Laughlin, Unpublished Decision (3-9-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/wild-fire-inc-v-laughlin-unpublished-decision-3-9-2001-ohioctapp-2001.