Wickersham Construction & Engineering, Inc. v. Williamsport Sanitary Authority

38 Pa. D. & C.5th 212, 2014 Pa. Dist. & Cnty. Dec. LEXIS 1052
CourtPennsylvania Court of Common Pleas, Lycoming County
DecidedMay 7, 2014
DocketNo. 11-00,533
StatusPublished

This text of 38 Pa. D. & C.5th 212 (Wickersham Construction & Engineering, Inc. v. Williamsport Sanitary Authority) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Lycoming County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickersham Construction & Engineering, Inc. v. Williamsport Sanitary Authority, 38 Pa. D. & C.5th 212, 2014 Pa. Dist. & Cnty. Dec. LEXIS 1052 (Pa. Super. Ct. 2014).

Opinion

GRAY, J.,

OPINION AND ORDER

And now, this 7th day of May, 2014, following oral argument on the plaintiff’s motion for summary judgment, and after review of the argument, pleadings, motion, response and briefs, the court finds that summary judgment is not warranted. The court enters the following opinion and order.

Procedural and Factual Background

This matter arises from a contract dispute. The plaintiff, Wickersham Construction and Engineering, Inc. (“Wickersham”) was the successful bidder and awarded a contract by defendant Williamsport Sanitary Authority (“WSA”) for “Contract C2-Combined Sewer Overflow compliance.” The parties entered into that construction contract (“contract”) with an effective date of November 24, 2009. The contract pertained to the first in a series of construction projects that were required for WSA to comply with a consent decree entered with the Pennsylvania Department of Environmental Protection (DEP) and United States Environmental Protection Agency (EPA). Regulations [214]*214required the WSA to reduce the nutrients discharged into the Susquehanna River. The time requirements set forth in the contract were crucial because they were set up for the WSA to avoid severe financial penalties under the consent decree. As the first of the construction projects, Wickersham’s failure to meet time the requirements would likely backlog the subsequent contractors who were required to build upon the foundations constructed by Wickersham.

On November 26, 2013, Wickersham filed for summary judgment under Count I, Breach of Contract (Failure to Pay Wickersham its Contract Balance), asserting an unpaid balance of $784,260.1 Wickersham avers in Count I that the value of the contract with approved change orders was $9,006,056.2 WSA paid Wickersham $8,221,796. Wickersham claims payment in full was due on or about August 11, 2011. WSA avers that “[f]rom the inception of the project, Wickersham failed to perform its work in a timely fashion and in accordance with the contract documents and project schedule prepared by Wickersham.” Defendant’s new matter, ¶ 113. The substantial completion date for the contract was extended from February 24, 2011 to March 21, 2011. Nonetheless, Wickersham did not reach substantial completion until June 17,2011. The final completion for the contract was May 20, 2011. However, the final completion of the contract was not achieved until July 11,2011.

WSA withheld liquidated damages in the amount of $556,000 and contractual and special damages (relating to additional engineering and inspection costs) in the amount of [215]*215$205,907.43. Malcolm Pirnie, Inc. (Pirnie) served as engineer for the project. By letters dated April 11, 2011, May 5, 2011, June 3, 2011, July 20, 2011 (copied to Wickersham), Pirnie advised WSA about its recommendation for the withholding of liquidated damages. WSA withheld liquidated and special damages in accordance with Pirnie’s recommendations. The final amount withheld was $789,259.75. No party filed a “claim” with respect to the liquidated or special damages. Wickersham did not assert that the WSA was required to file a claim to withhold damages at the time of the withholding of damages by WSA.

The contract consists of more than a hundred pages. The contract includes thefirstpart called the “agreement,” consisting of 9 pages and 10 articles, with Article 9 incorporating the following documents as “contract documents:” the agreement, performance bond (2 pages), payment bond (3 pages) stipulation against liens (1 page), general conditions (54 pages), supplementary conditions (17 pages and attachments), specifications, as listed in the table of contents of the project manual, set of drawings, addenda numbered 1 through 3, exhibits, notice to proceed, work change directives and change orders that have or may be issued.

The first part of the contract is labeled the “agreement.” It consists of 9 pages and was signed by both parties. It includes Article 4 entitled “CONTRACT TIMES.” Article 4.01 provides that “[a]ll time limits for Milestones, if any, Substantial Completion and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.” (emphasis added) Article 4.02A sets forth the contract times and specifically references paragraph 2.03 of the general conditions with respect to the commencement of contract times and paragraph 14.07 of the general conditions which outlines the procedures for application for final payment.

[216]*216Article 4.03 of the contract provides for liquidated damages as follows.

Owner and Contractor recognize that time is of the essence of this agreement and owner will suffer financial loss, apart from the costs described in Paragraph 4.04A, if the work is not substantially completed within the time specified in Paragraph 4.02A for Substantial Completion, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. Owner and Contractor also recognize the delays, expense and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not substantially completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty) Contractor shall pay Owner $5,500.00 for each day that expires after the time specified in Paragraph 4.02.A for Substantial Completion (adjusted for any changes thereof made in accordance with Article 12 of the General Conditions) until the Work is Substantially Complete. Subsequent to achieving Substantial Completion (adjusted for any changes thereof made in accordance with Article 12 of the General Conditions) until the Work is Substantially Complete. Subsequent to achieving Substantial Completion, Owner and Contractor agree that as liquidated damages for delay (but not as penalty) Contractor shall pay Owner $3,000.00for each day that expires after the time specified in Paragraph 4.02.A for final payment (adjusted for any changes thereof made in accordance with Article 12 of the General Conditions) until the Work associated with final payment is complete, (emphasis added)

Article 4.04A of the contract provides for special damages as follows.

In addition to the amount provided for liquidated damages, [217]*217Contractor shall pay Owner the actual costs reasonably incurred by owner for engineering and inspection forces employed for the Work for each day that expires after the time specified in Paragraph 4.02A for Substantial Completion (adjusted for any changes thereof made in accordance with Article 12 of the General Conditions until the Work is substantially complete)(emphasis added).

Article 4.05 of the contract provides that the “owner may deduct liquidated damages and special damages as determined by the provisions of this article 4 from progress payments due Contractor under this Agreement.” Article 4 does not make any reference to filing of claims or Article 10 of the General Conditions which outlines the procedures for filing claims.

Article 9 of the Agreement incorporates the document entitled General Conditions. The General Conditions document consists of 54 pages and was adapted from “Standard General Conditions of the Construction Contract, EJCDC No. C-700 (2002 Edition).” That document is not signed or initialed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abbott v. Schnader, Harrison, Segal & Lewis, LLP
805 A.2d 547 (Superior Court of Pennsylvania, 2002)
Minnotte Appeal
192 A.2d 394 (Supreme Court of Pennsylvania, 1963)
Pennsylvania Engineering Corp. v. McGraw-Edison Co.
459 A.2d 329 (Supreme Court of Pennsylvania, 1983)
Spatz v. Nascone
424 A.2d 929 (Superior Court of Pennsylvania, 1981)
Brown v. Cooke
707 A.2d 231 (Superior Court of Pennsylvania, 1998)
Maguire v. Ohio Casualty Insurance
602 A.2d 893 (Superior Court of Pennsylvania, 1992)
Young v. Commonwealth Department of Transportation
744 A.2d 1276 (Supreme Court of Pennsylvania, 2000)
SZYMANOWSKI v. Brace
987 A.2d 717 (Superior Court of Pennsylvania, 2009)
Keystone Freight Corp. v. Stricker
31 A.3d 967 (Superior Court of Pennsylvania, 2011)
Atlantic Richfield Co. v. Razumic
390 A.2d 736 (Supreme Court of Pennsylvania, 1978)
Shehadi v. Northeastern Nat. Bank of Pa.
378 A.2d 304 (Supreme Court of Pennsylvania, 1977)
PBS Coal, Inc. v. Hardhat Mining, Inc.
632 A.2d 903 (Superior Court of Pennsylvania, 1993)
Urian v. Scranton Life Ins. Co.
165 A. 21 (Supreme Court of Pennsylvania, 1932)
Trombetta v. Raymond James Financial Services, Inc.
907 A.2d 550 (Superior Court of Pennsylvania, 2006)
Humberston v. Chevron U.S.A., Inc.
75 A.3d 504 (Superior Court of Pennsylvania, 2013)
Trainer v. Wolfe
21 A. 391 (Supreme Court of Pennsylvania, 1891)
Binenstock Trust
190 A.2d 288 (Supreme Court of Pennsylvania, 1963)
Baltic Development Co. v. Jiffy Enterprises, Inc.
257 A.2d 541 (Supreme Court of Pennsylvania, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
38 Pa. D. & C.5th 212, 2014 Pa. Dist. & Cnty. Dec. LEXIS 1052, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickersham-construction-engineering-inc-v-williamsport-sanitary-pactcompllycomi-2014.