Wicker v. Messinger

12 Ohio Cir. Dec. 425
Ohio Circuit Courts·Decided June 18, 1901·Published

Opinion

Parker, J.

This is a proceeding in error brought to obtain the reversal of the judgment of the court ot common pleas. The action in the court below was by Messinger and Hull, building contractors, against Wicker, to recover under a contract lor the building of a certain structure in this city now occupied by the Lincoln club, and to recover as well lor extras not provided for in. the contract; the first cause oi action setting forth that (he amount to be paid tor the construction of the building was $8,598; that plaintiff had finished the building, but that there was still an unpaid balance due them under this contract of $1,589.20.

They set forth in the petition a copy of the contract, which contains a provision that the payments “ shall be paid in current funds by the owner to the contractor in installments as follows: Payments shall be made upon the architect’s estimates. The final payment shall be made within thirty days alter this contract is fulfilled. All payments shall be made upon written certificates ot the architects to the effect that such payments have become due.”

There is no averment in the petition that the plaintiffs had received from the architects a certificate lor this $1,589.20, or any part of it, but the petition upon that subject contains this averment: “That since the making and payment of said estimate of November 29, 1898, (which was the last payment actually made,) the architects ot said building, at the express direction and request of said defendants, and said defendants wholly without reason theretor, have tailed, neglected and relused, and fail, neglect and refuse to furnish plaintiffs with further certificates of estimates tor materials furnished and labor perlormed upon and toward the construction and completion of said building, although plaintiffs duly requested and demanded that such certificates oi estimates should be made and furnished to them, and said defendants have failed, neglected and refused, and fail, neglect and refuse to pay plaintiffs the balance of said contract price, to-wit, the sum of $1,589.20, although payment thereof [427] has been duly demanded from said defendants by plaintiffs, and the amount is due,” etc. That is the first cause of action.

The second cause of action is for extras.

No remarks need be made upon the third cuase of action, since there is no controversy respecting the matters therein stated.

To this petition the delendants filed an answer in which they make various denials and among them these:

‘‘They deny that plaintiffs ever duly complied with or performed all the terms or conditions of said contract on their part to be complied with or performed; and
‘‘They deny that these answering defendants, or either of them, ever directed or requested the architects of said building to neglect or retuse to furnish plaintiffs with estimates for materials furnished or labor performed for the construction oi said building.”

A reply was filed, which does not change the issues with respect to these questions that are made by the petition and the answer.

Upon these pleadings the defendants moved for a judgment, insisting that the petition did not aver sufficient to entitle the plaintiffs to recover; that it should have averred either that the architects had furnished these certificates or estimates or that they had fraudulently, or wrongiully, or wilfully and unreasonably withheld such certificates; that it was not sufficient that they had withheld them at the express direction and request of said defendants, for it is urged that even though they may have withheld them at the request and direction of defendants, and although the defendants may have had no reason to make such request, yet the architects may have had good and sufficient reasons, aside from this, which would justify them under the contract in withholding the certificates or estimates.

The case of Ashley v. Henahan, 56 Ohio St. 559 [47 N. E. Rep. 578], is brought to our attention by counsel for plaintiffs in error and very much relied upon. In that case the contract contained a provision that ‘‘tüe architect shall certify in writing, that all the work upon the performance of which the payment is to become due, has been done to his satisfaction.” And the evidence in the case disclosed that that had not been done by the architect and that there was nothing in the case to show any waiver of that provision. The court says:

‘‘Had the plaintiff shown that he had made application to the architect for the requisite certificates, and that he had obstinately and unreasonably refused to certify, he might then have established his case by other evidence. As said in Smith v. Brady, 17 N. Y. 173: ‘The parties have seen fit to make the production of such certificate a condition precedent to the payment. The plaintiff is as much bound by this part ot his contract as any other. It is not enough for him to bring his action and say he has completed the work which he undertook to do. He has agreed that the architects named should decide whether the work is completed or not. He cannot now withdraw the decision of this question from them and refer it to the determination of a legal tribunal. ’ He might, however, as suggested above, on an averment supported by evidence that the architect had fraudulently or unreasonably refused his certificate, recover by showing a substantial performance of the work as required by the contract, but in the absence of such a showing against the architect, a recovery cannot be had witfiout his certificate.”

So that we are called upon to place a construction upon this averment and decide whether it is sufficient to bring the plaintiffs within [428] the requirements of the rules laid down in Ashley v. Henahan, supra. And we suppose that in passing upon this question we should, consider the petition, upon an application or motion of this kind Submitted to the court, as if it had been demurred to. It it is sufficient to stand against a general demurrer, it is sufficient to justify the court in rel using the motion to allow a judgment upon the pleadings. No motion having been made to require an amendment of this pleading, to make it definite or certain in any respect in which it might seem to be somewhat indefinite and uncertain, and it having been submitted in this way, as it stood, we are of the opinion that it should receive such liberal construction as would be given it if a general demurrer had been filed, and, so considering it, we conclude that the averment that the architects of the building, at the express direction and request of the defendants, refused the certificates of estimates, and that the defendants in making this request proceeded wholly without reason thereior, is equivalent to an averment that the architects had no other reason for refusing the certificates than the request ot the defendants, and that this request being without reason, therefore it follows that the refusal of the architects was without reason or justification; that it is equivalent to an averment that fhe architects ot said building, at the express direction and request ot said defendants and wholly on that account, refused the certificates, and that there was no reason or justification in the facts for such r'elusal.

Free access — add to your briefcase to read the full text and ask questions with AI

Wicker v. Messinger, 12 Ohio Cir. Dec. 425 (Ohio Super. Ct. 1901).

12 Ohio Cir. Dec. 425 (Wicker v. Messinger) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)