Wichita Mill & Elevator Co. v. Liberal Elevator Co.

243 F. 99, 155 C.C.A. 629, 1917 U.S. App. LEXIS 2090
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 10, 1917
DocketNo. 4776
StatusPublished
Cited by2 cases

This text of 243 F. 99 (Wichita Mill & Elevator Co. v. Liberal Elevator Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wichita Mill & Elevator Co. v. Liberal Elevator Co., 243 F. 99, 155 C.C.A. 629, 1917 U.S. App. LEXIS 2090 (8th Cir. 1917).

Opinion

STONE, Circuit Judge.

Damage for Breach of Cpntract. A writ of error based on alleged right of larger recovery by plaintiff below from judgment in its favor for $986.97. Tried to the court on stipulation of facts and brief undisputed oral testimony.

The Contract. July 14, 1914, Lhe Liberal Elevator Company of Hutchinson, Kan., sold to the Wichita Mill & Elevator Company, of Wichita Falls, Tex., 25,000 bushels of wheat to be delivered f. o. b. Galveston, Tex., during that month subject to the following rule of the Kansas Grain Dealers’ Association:

“Elite 7. Incomplete Shipments. "When the seller finds he will not be able to complete a contract within the agreed limit, it shall be his duty to so advise Hie buyer by mail, telephone, or telegraph, whereupon it shall he the duty of the buyer to at once elect either to buy in or cancel the deficit, or to extend the contract to cover said deficit. Should the seller fail to notify the buyer of his, the seller’s, inability to complete a contract for shipment, as in this rule above provided, the said contract shall remain in force unless and until completed, extended, bought in, or canceled.”

The Breach. After shipping 7,055 bushels, the seller, on July 29th, informed the buyer of its inability to complete its contract in July because oí a railway embargo*. No further deliveries were* made,' and after an extended correspondence the buyer on September 3d, being refused further performance, bought in the deficit at Galveston. The suit is for the expense and price difference in buying in this deficit. Recovery was allowed by the court below on the basis of a breach on August 10th and measure of damage as of that date. The buyer claims breach on September 3d and measure of damage as of that date.

The Railway Bmbargo. Before stating the position of the parties, it will be useful to' dear away a false issue which has been presented by both sides. While it lias its importance as a circumstance in the consideration of other points in the case, the railway embargo* as a defense is not an issue in this court. It was determined by the trial court to be no defense, and no other conclusion could sustain the judgment below. The determination on that point was in favor of plaintiff, and the case is here solely on its writ of error.

The Controversy. The dispute is solely as to whether the breach and measure of damage is to be taken as of August 10th or as of September 3d. It hinges on the rights of the parties under rule 7, supra, and the dealings between them from July 29th to September 3d (revealed in correspondence) as controlled by that rule. Under rule 7 the defaulting seller could not cancel the contract; the buyer could. The buyer never exercised its right to cancel under the contract, for, although negotiations for cancellation were under way at various times, they were without results. When these negotiations failed, the seller on August 10th demanded disposition orders for the grain, whereupon the buyer attempted to extend the contract. The seller refused to recognize this extension. If the extension was binding, the buyer’s contention is correct; if not, that of the seller must prevail.

Was the contract extended by the buyer, so that it was in force upon September 3d? The buyer contends it was. The seller contests this [102]*102because, as it claims, (a) the original contract was replaced by a new contract; (b) whatever right of extension existed, either under the original or under the new contract, was not exercised seasonably; (c) any such right was not exercised properly, because the extension was indefinite as to time.

[1] (a) New Contract. The theory of the seller is that on August 2d the buyer requested that the wheat be held for a few days, to which it (seller) acceded, and from this arose a new contract. As it will be necessary, in considering the subsequent points in this case, to set' out the correspondence (August 2d to August 8th) relied upon by the seller to sustain this contention, it will not be duplicated here. That correspondence shows this situation: When it began, the time for delivery under the original contract was two days past; the seller had assured the buyer five days earlier that it would be prevented by a railway embargo from shipping until August 2d, but would get the wheat out as soon as the railroads would receive it; the duration of the embargo after that date seems to have been uncertain, or at'least unknown to these parties; between the above dates the embargo continued, so that the seller could not have shipped; during the same period there was a con gestión at Galveston, so that the buyer did not desire shipment; that under these circumstances the buyer, in two wires reaching the seller on the same day, requested, first, that shipments be temporarily held up, and, second, that sale be canceled; that on the day of such receipt the seller wired and wrote buyer, in its wire ignoring the request to delay and stating it had the wheat to “apply on sales as soon as embargo is raised,” and in its letter barely acknowledging such request and saying, in confirming its wire, that it had the wheat “ready to apply as soon as the Galveston embargo is raised,” and “would very much prefer to deliver this wheat to you as soon as it is possible for us to do so”; that on August 4th the bufeV again wired request for delay and offer for cancellation at stated price; that to this the seller replied, again ignoring, beyond bare acknowledgment, the request to delay, and saying it had the wheat stored in its elevator “ready to ship any time, consequently would not feel like giving you any money to cancel this sale”; that at no time did the seller in its correspondence ever refer to such request for delay, except to simply acknowledge its receipt. This reveals no acceptance of the offer, if such it was, to delay. Nor can the fact that the seller did delay be of any force in this connection, for such delay was caused by its absolute inability to ship, and not by its compliance with the buyer’s request. There was no new contract.

[2] (b) Seasonable Extension of Contract. The buyer was notified at Wichita Kails, Tex., by letter mailed at Hutchinson, Kan., July 29th, that the seller would be unable to complete its contract within the contract time. No extension by the buyer under the contract (rule 7) was attempted until August 10th and 11th. Had the right of extension expired before that time ? Rule 7 provided that, upon notification from the seller of his inability to complete contract within time limit, it (buyer) should “at once elect to buy in or cancel the deficit, or to extend the contract to cover said deficit.” Was this election exercised “at once” within the meaning of the contract?

“At once” does not mean instantaneously, but with reasonable ex[103]*103pedition under all of the circumstances. 5 C. J. 1439, and citations; Fidelity & Deposit Co. v. Courtney, 186 U. S. 342, 22 Sup. Ct. 833, 46 D. Ed. 1193; Empire State Surety Co. v. Northwest Lumber Co., 203 Fed. 417, 121 C. C. A. 527 (9th C. C. A.). Each case must necessarily rest largely upon its own facts; therefore authorities are usually of little aid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennett v. Hatfield
222 P. 61 (Supreme Court of Kansas, 1924)
Strong v. Thurston
191 P. 575 (Supreme Court of Kansas, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
243 F. 99, 155 C.C.A. 629, 1917 U.S. App. LEXIS 2090, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wichita-mill-elevator-co-v-liberal-elevator-co-ca8-1917.