Whitsett Corp. v. Norbord South Carolina, Inc.
This text of Whitsett Corp. v. Norbord South Carolina, Inc. (Whitsett Corp. v. Norbord South Carolina, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
Lynn Whitsett Corporation, Appellant,
v.
Norbord South Carolina, Inc., and Callidus Technologies, Inc., Defendants, Of Which Callidus Technologies, Inc., is, Respondent.
Appeal From Laurens County
James W. Johnson, Jr., Circuit Court
Judge
Unpublished Opinion No. 2004-UP-338
Submitted March 8, 2004 Filed May
18, 2004
AFFIRMED
Joseph W. Hudgens, of Newberry, and Warner R. Wilson, Jr., of Atlanta, for Appellant.
Boyd B. Nicholson, Jr., of Greenville, for Respondents.
PER CURIAM: Lynn Whitsett Corporation brought this action against Norbord South Carolina, Inc. and Callidus Technologies, Inc. for breach of contract, foreclosure of a mechanics lien, and quantum meruit. Callidus counterclaimed for breach of contract and breach of warranties. The trial court found for Lynn Whitsett on its breach of contract claim, but concluded Callidus was entitled to an offset for delays and recovery on its breach of warranties claims. The resulting net judgment was in favor of Callidus. Lynn Whitsett appeals. We affirm. [1]
FACTS
Norbord hired Callidus as its general contractor to build a pressboard plant. Callidus subcontracted with Lynn Whitsett to install ceramic refractory materials to the walls of Norbords kilns. Lynn Whitsetts contract contained a fixed price for the installation project. However, in the event of a change in the scope of the work, the contract converted to one based on time and materials. It also stated Callidus would provide a particular type of refractory material to be used in the installation. Instead, Callidus supplied a slightly different product. Lynn Whitsett applied the ceramics using a gunning crew to spray them onto the kiln walls and a casting crew to pour the material into prepared forms. Delays arose when the refractory material did not set up properly with the result that the entire application process took fifteen weeks instead of the eight weeks stated in the contract.
Lynn Whitsett claimed it was owed $84,472.20 under the contract because the application required significant extra labor. When Callidus refused to pay, Lynn Whitsett brought this action. Callidus filed a bond to discharge the mechanics lien and agreed to indemnify Norbord for any amounts due Lynn Whitsett.
Lynn Whitsett amended its complaint to argue the scope of its work had been increased because Callidus supplied a different refractory material than had been proposed in the contract. Lynn Whitsett claimed this change converted the contract from one with a fixed price to one based on time and materials. Callidus counterclaimed alleging breach of express and implied warranties based on faulty workmanship.
The trial court agreed with Lynn Whitsett that the contract was converted from a lump sum payment to one based on time and materials with a balance due of $272,498.60. However, the court determined Lynn Whitsett was responsible for four weeks of delays and gave Callidus a substantial setoff of $179,307.12. The court also found Lynn Whitsett breached implied and express warranties and set damages at $114,342.79, finally awarding judgment for Callidus in the amount of $21,151.31. Based on these findings, the court concluded Callidus prevailed in the mechanics lien action and awarded attorneys fees in the amount of $71,714.41.
DISCUSSION
An action for breach of contract seeking money damages is an action at law. Sterling Dev. Co. v. Collins, 309 S.C. 237, 240, 421 S.E.2d 402, 404 (1992). An action to foreclose a mechanics lien is also an action at law. Adams v. B & D, Inc., 297 S.C. 416, 420, 377 S.E.2d 315, 317 (1989). In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports those findings. Townes Assocs. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).
I. Four-Week Delay
Lynn Whitsett contends the trial court erred by granting Callidus a set-off after determining Lynn Whitsett was responsible for a four-week delay in completing its work. Lynn Whitsett claims there is no evidence in the record to support the trial courts conclusion, and maintains Callidus caused the delays by supplying substitute refractory materials and by failing to properly prepare and install items prior to the application of the ceramics. We disagree.
On appeal, this court cannot weigh conflicting evidence in a law case. Only if there is no conflicting evidence may we find error as a matter of law. Hibernian Socy v. Thomas, 282 S.C. 465, 469, 319 S.E.2d 339, 342 (Ct. App. 1984). Although the record contains evidence that Callidus may have been responsible for some delays, it also contains evidence that Lynn Whitsett caused the four-week delay. In a letter to Callidus with the heading Subject: Explanation for extra work invoice, beneath a subsection marked Other problems that caused delays or additional work: a Lynn Whitsett representative wrote:
It was never Lynn Whitsetts intention to cast the SCC in any other method but to pump them. This was an oversight on my part when I read the SK-1 sheet that you sent me before starting of this job that stated that Kricon 28 would be used. I assumed after other conversations that I had with you and Elton, that pumping of the SCC was the only cost effective way of installation. This will require an additional four weeks of work to do this in the manner that you want it, one bucket at a time. Again, this was not quoted that way.
(Emphasis added.)
When questioned about the letter during cross examination, the representative admitted his oversight caused the delay. Accordingly, we conclude there was evidence to support the trial courts finding that Lynn Whitsett was responsible for four weeks of the delay and the corresponding award of a set-off in favor of Callidus.
II. Calculating the Set-off Amount
Lynn Whitsett further contends the amount of the set-off is unsupported by the evidence. We disagree.
The evidence supporting a damages award should be such that the court can determine the amount with reasonable certainty or accuracy. See Gray v.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Whitsett Corp. v. Norbord South Carolina, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitsett-corp-v-norbord-south-carolina-inc-scctapp-2004.