Whitney Nat. Bank v. Poydras Ctr. Assoc.
This text of 557 So. 2d 422 (Whitney Nat. Bank v. Poydras Ctr. Assoc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
WHITNEY NATIONAL BANK OF NEW ORLEANS
v.
POYDRAS CENTER ASSOCIATES, a Louisiana Joint Venture and HCB Contractors, a Texas General Partnership.
Court of Appeal of Louisiana, Fourth Circuit.
*423 Jerry A. Brown, Kathryn Lichtenberg, New Orleans, for plaintiff/appellee.
Danny G. Shaw, David J. Krebs, New Orleans, for defendants/appellants.
Before CIACCIO, WILLIAMS and BECKER, JJ.
BECKER, Judge.
Defendant, Poydras Center Associates, appeals the trial court's finding that an oral contract existed between itself and plaintiff, Whitney National Bank. Plaintiff sued to recover damages it allegedly incurred when defendant, Poydras Center Associates (PCA), breached its duties under the alleged oral contract. Whitney National Bank has answered the appeal seeking an increase in damages.
On January 17, 1986, plaintiff Whitney National Bank filed suit against Poydras Center Associates, a Joint Venture, and HCB Contractors seeking recovery of damages in tort and breach of contract. Whitney National Bank is the owner of a seven story building at the corner of Camp Street and Poydras Street. The ground floor is used by Whitney as a branch bank. The other floors are leased to tenants. Poydras Center Associates owns the adjoining property on which it constructed a twenty seven story office building. HCB was the general contractor on the construction job.
Whitney's cause of action against HCB was based in tort, seeking recovery for damages which it incurred during the construction of PCA's building. Whitney sued PCA in tort and contract, alleging that an oral contract existed whereby Whitney would release a five foot servitude which existed over PCA's property provided PCA paid for all expenses incurred so that the two buildings could abut.
After trial on the merits, the trial court rendered judgment in favor of Whitney against both HCB and Poydras Center Associates. The trial court found that plaintiff had incurred $33,857.15 in damages as a result of the actual construction work. The trial court further found that an oral contract did exist between Whitney and Poydras Center Associates, and that Whitney suffered damages in the amount of *424 $40,400.00 from PCA's breach of the contract.
Poydras Center Associates and HCB each filed a motion for new trial which was denied by the trial court. HCB elected not to appeal and satisfied the portion of the judgment relating to tort damages.
On appeal, Poydras Center Associates assigns five specifications of error:
(1) The trial court erred as a matter of law in holding that the elements of consent and contractual object had been satisfied and that there was a contract between Whitney and Poydras Center Associates;
(2) The trial court committed manifest error in awarding plaintiff $27,400.00 for modification of its fire escape;
(3) The trial court committed manifest error in awarding Whitney $9,500.00 for modification of its air conditioning system;
(4) The trial court committed manifest error in awarding Whitney $3,500.00 for relocation of its emergency electrical service; and
(5) The trial court erred in holding that interest should run from date of judicial demand rather than date of judgment.
In its answer to the appeal, Whitney argues that the damages for modification of the air conditioning system should be increased to $37,115.00, and the damages for modification to the fire escape be increased to one-half of the entire cost borne by Whitney. Whitney further contends that the trial court erred in not ruling that legal interest was to run from the date PCA was in active violation of the contract. In the alternative, Whitney argues legal interest should run from the date of demand, November 30, 1981.
The subject matter of this lawsuit arises out of Poydras Center Associates' attempt to remedy a problem engendered by its plan to construct a twenty-seven story office building on land that was burdened by a five foot servitude in favor of Whitney. The mistake, when discovered by PCA, which could not have been corrected without extensive redesign, would have resulted in a substantial impact on both the cost of the new building as well as the construction schedule. Therefore, PCA approached Whitney to permit PCA's new office building to abut the southern face of Whitney's building.
Commencing in the summer of 1980, negotiations, the exchange of correspondence, and meetings between PCA and Whitney all occurred. The significance of these activities is hotly contested by the parties. PCA contends that the communications between Whitney and PCA amounted to nothing more than preliminary negotiations. However, Whitney argues that representations made, communications exchanged and actions undertaken by the parties gave rise to contractual obligations that were eventually breached by PCA.
The trial court, after a trial on the merits, found that an oral contract did exist between Whitney and PCA, and that the contract was indeed breached by PCA. The court specifically found that PCA "induced plaintiff to expend funds or otherwise to obligate itself to others." The trial court, in its reasons for judgment, stated that, in finding a contract existed, it relied upon "the clear, pointed and convincing testimony of plaintiff's Building Manager, Guy Ponti" and "the clear and unambiguous language of a letter from the Poydras Center representative, James M. Caswell, transmitted as an enclosure in a letter from Leon S. Cahn (Poydras Center's attorney) to Andrew Zengel (Whitney's attorney), to wit:
`Please be advised that we will pay all cost, of any nature incurred regarding the closing of the alley between Whitney National Bank and our property ...'."
A contract is defined as "an agreement, by which one person obligates himself to another, to give, to do or permit, or not to do something, expressed or implied by such agreement." LSA-C.C. article 1761. For a valid contract to exist, there must be (1) parties legally capable of contracting; (2) their consent legally given; (3) a certain object, which forms the matter of agreement; and (4) a lawful purpose. LSA-C.C. article 1779; Morphy, Makofsky & Masson, Inc. v. Canal Place 2000, 538 So.2d 569 (La.1989). A contract can be express *425 or implied in fact. An implied in fact contract is one which rests upon consent implied from facts and circumstances showing mutual intention to contract. Morphy, supra; V-8 Taxi Cab Service, Inc. v. Hayes, 322 So.2d 442 (La.App. 4th Cir. 1975). Such implied in fact contracts are not different in their legal effect from express, written agreements. Comment, Actio De In Rem Verso in Louisiana: Minyard v. Curtis Products, Inc., 43 Tul.L. Rev. 263, 298 (1969).
Defendant, PCA, contends that the trial court erred when it found that the elements of consent and contractual obligation had been satisfied. The element of consent is an issue of fact, Strecker v. Credico Financial, Inc., 444 So.2d 783 (La. App. 4th Cir.1984), and absent manifest error, we may not disturb the trial court's findings on the existence of consent. Arceneaux v. Domingue, 365 So.2d 1330 (La. 1978); Canter v. Koehring Co., 283 So.2d 716 (La.1973).
The trial court relied heavily upon the letter of James Caswell to his attorney, and upon the repeated silence and inaction of PCA's representative to the correspondence of Whitney concerning the ongoing modifications to the Whitney building.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
557 So. 2d 422, 1990 WL 6340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitney-nat-bank-v-poydras-ctr-assoc-lactapp-1990.