Whitney Co. v. Church

101 A. 329, 91 Conn. 684, 1917 Conn. LEXIS 71
CourtSupreme Court of Connecticut
DecidedJune 14, 1917
StatusPublished
Cited by3 cases

This text of 101 A. 329 (Whitney Co. v. Church) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitney Co. v. Church, 101 A. 329, 91 Conn. 684, 1917 Conn. LEXIS 71 (Colo. 1917).

Opinion

*686 Shumway, J.

The controversy between the parties arose out of a building contract in which The Whitney Company was contractor and Alfred W. Church was the owner of the building.

The cause was submitted to arbitration under a rule of court. The arbitrators having made an award, returned the same to the Superior Court. The defendants moved the court to accept the award and render judgment thereon as provided in § 957 of the General Statutes. To the acceptance of the award the plaintiff remonstrated, alleging that the arbitrators “misconducted themselves in such manner as to evince partiality toward the defendants and prejudice against the plaintiff,”—specifying, as such misconduct, that the arbitrators called before them in secret session a witness who had testified in behalf of the defendants and examined the witness in the absence and without the consent of the plaintiff or its counsel; that the arbitrators addressed a letter to one of the defendants and received from him an answer, “containing matter of an evidential nature”; and that one of the arbitrators made an inquiry of a 'certain contractor as to the construction, as understood by contractors, of a clause in the building contract, the subject of this action. The remonstrant further alleged that the arbitrators departed from the principles announced by them as governing their hearing, and specifying as such departure certain rulings upon the admission and rejection of evidence, as well as making erroneous rulings as to the legal interpretation of the building contract between the parties, and that the arbitrators made an award upon matters not in any way submitted to them. The Superior Court overruled the remonstrance, accepted the award, and rendered judgment for the defendants to recover of the plaintiff, The Whitney Company, $5,200.21 damages. The plaintiff appealed from the judgment, *687 and at the plaintiff’s request the court made an extended finding, setting out in detail the proceedings before the arbitrators.

The matters contained in the third paragraph of the remonstrance in the Superior Court raise the most important question in the case, and it was justly so regarded by that court. The allegations in the paragraph named are, in substance, that the arbitrators refused “to admit and consider proper, competent and relevant testimony” offered by the contractor as to the value of certain items claimed by the plaintiff to be extra work. The clause in the contract covering the “extra work” that might be required in carrying out the contract, is as follows: “Should any alterations be required in the work shown or described by the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architect, and the sum herein agreed to be paid for the work according to the original specifications shall be increased or diminished as the case may be. In case such valuation is not agreed to, the contractor shall proceed with the alteration, upon the written order of the architect, and the valuation of the work added or omitted shall be referred to three (3) arbitrators (no one of whom shall have been personally connected with the work to which these presents refer), to be appointed as follows: one by each of the parties to this contract, and the third by the two thus chosen, the decision of any two of them shall be final and binding upon both parties.”

The Whitney Company contended before the arbitrators, that under this clause in the contract the valuation placed upon this “extra work” by the architect was conclusive. This claim of the Whitney Company was properly overruled by the arbitrators, and they informed counsel, or the parties, that they, the *688 arbitrators, would expect the plaintiff to offer some evidence tending to prove that the items of “extra work were of the value in respect to time and material as indicated in their statement of claim,” and this while the Whitney Company was presenting its evidence. The position taken by the arbitrators and the ruling upon the question was repeatedly called to the attention of plaintiff’s counsel, but he closed the testimony for the plaintiff without offering the evidence indicated. The defendants having offered evidence of the value of the “extra work” as part of their case, the plaintiff asked to be allowed to again open the evidence as to the value of “extra work.” The defendants objected and the arbitrators sustained them; the arbitrators ruling that it was not rebuttal testimony.

By this ruling of the arbitrators, the plaintiff was deprived of no right. It had full opportunity to prove its case, but preferred to rest upon its claim that the valuation of the architect was conclusive upon the defendants. Although the ruling of the arbitrators might have been thought to be erroneous, it was the plaintiff’s duty to abide by and comply with the ruling and conduct his case in accordance therewith, or take his chances of losing all right to produce the evidence if the rulings of the arbitrators should be finally sustained. The ruling of the arbitrators was correct, and if the plaintiff had lost some substantial right it could not complain, for it had full opportunity to prove its case if it had seen fit to do so. But this ruling affected but few items in the plaintiff’s claim, and these not in any substantial manner unless the claims of the plaintiff had been fully sustained.

Referring now to the claimed misconduct of the arbitrators in writing a letter to one of the defendants without the knowledge or consent of the plaintiff, *689 it appears that this letter was written after the defendant had testified, and in his reply to the letter he reiterated in substance his testimony before the arbitrators. Notwithstanding the letter and the testimony, the arbitrators awarded to the plaintiff the full amount of the item as claimed by the plaintiff to which the communication referred.

One Conklin had testified before the arbitrators as to the value of certain plumbing work, and in his testimony had submitted figures showing the value of the work. These figures were received with the plaintiff’s consent. This testimony was under discussion in private session, and one of the arbitrators claimed there was an error in Conklin’s figures. One of the arbitrators happened to meet Conklin in the building where they were conferring and called his attention to the claimed mistake. Conklin admitted there was a mistake. The amount awarded by the arbitrators was $156.50 less than the figures submitted by Conklin, and to that amount were more favorable to the plaintiff.

The finding shows that there was a controversy over the doors which the plaintiff furnished for the building. The specifications required they should be one and one-half inches thick. The defendants claimed they should be allowed the expense of putting in doors one and one-half inches thick. The plaintiff claimed that there was a trade custom to the effect that specifications calling for doors one and one-half inches in thickness meant a door one and three-eighths inches thick. The arbitrators decided against the claim of the plaintiff. After the arbitrators had decided this question in this manner, one of the arbitrators met a contractor, one Mr. Bottomley, and asked him if there was such a trade custom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liggett v. Torrington Building Co.
158 A. 917 (Supreme Court of Connecticut, 1932)
Webb v. Emerson-Brantingham Implement Co.
227 S.W. 499 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
101 A. 329, 91 Conn. 684, 1917 Conn. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitney-co-v-church-conn-1917.