Whitlock Construction, Inc. v. South Big Horn County Water Supply Joint Powers Board

2002 WY 36, 41 P.3d 1261, 2002 Wyo. LEXIS 37, 2002 WL 341467
CourtWyoming Supreme Court
DecidedMarch 6, 2002
Docket00-45
StatusPublished
Cited by14 cases

This text of 2002 WY 36 (Whitlock Construction, Inc. v. South Big Horn County Water Supply Joint Powers Board) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitlock Construction, Inc. v. South Big Horn County Water Supply Joint Powers Board, 2002 WY 36, 41 P.3d 1261, 2002 Wyo. LEXIS 37, 2002 WL 341467 (Wyo. 2002).

Opinion

LEHMAN, Chief Justice.

[T1] This is an appeal from a district court order dismissing Whitlock Construetion's claims based upon the finding that no binding contract existed between Whitlock and the South Big Horn County Water Supply Joint Powers Board (JPB). We hold that a contract did exist between Whitlock and the JPB but affirm the order dismissing the claims on the ground that performance under the contract never became due because a necessary condition to performance did not oceur.

ISSUES

[12] Whitlock states the issues as follow:

1. Whether the actions of the appellee WWDC and their representative, Roy Pri- or are in violation of competitive bidding requirements and should be declared arbitrary and capricious, without authority or discretion and not otherwise in accordance with relevant law.
2, Whether actions of the appellee Joint Powers Board in rescinding its award of a public construction contract to appellant and then awarding the same contract to a bidder which the Joint Powers Board previously rejected as an unresponsive bidder violates contract law and competitive bidding requirements and should be declared arbitrary and capricious, without legal authority or discretion, and not otherwise in accordance with relevant law.
3. Whether the trial court erred in granting defendants' motion for summary judgment by failing to find that a contract was formed between the appellee JPB and appellant when the JPB unconditionally accepted appellant's bid (offer) which contained a promissory condition that the JPB would use its best efforts to seek funding agency concurrence with the contract award to appellant, but the JPB failed to reasonably seek concurrence from the funding agency.

We discern the following issues for our review:

1. Whether the JPB breached its contract by rescinding the award to Whitlock after the funding agencies did not concur.
2. Whether the JPB breached the implied covenant of good faith and fair dealing by not obtaining the concurrence of the funding agencies.
3. Whether the JPB abused its discretion or acted arbitrarily and capriciously in rescinding the award to Whitlock and awarding the project to Larry's.
4. Whether the WWDC or Prior committed an abuse of discretion or acted unlawfully in not concurring in the award to Whitlock and concurring in the award to Larry's, Inc.

FACTS

[13] Whitlock Construction is located in Powell, Wyoming and is engaged in the busi *1264 ness of installing underground utilities. The South Big Horn County Water Supply Joint Powers Board (JPB) was established to oversee installation of a municipal water line from two artesian wells near Manderson, Wyoming to provide domestic water supply to the residents of Manderson, Basin, and South Big Horn County Water Districts. The Wyoming Water Development Commission (WWDC) is an agency of the State of Wyoming and was one of the primary funding agencies for the installation project. 1 Roy Prior was employed by the WWDC as a water development engineer.

[1 4] -In May of 1997, the JPB published a notice of advertisement for bids in the local newspaper for the purpose of soliciting competitive sealed bids for the construction of one phase of the water line. In preparation for submitting a bid on the project, Whitlock obtained the project manual, bid specifications, and plans. The project manual provided to all of the bidders on the project contained the following provision:

Contract Approval.
1.2 Concurrence by the FmHA State Director or designee in the award of the CONTRACT is required before it is effective and the "FmHA Concurrence" (Section 15), shall be attached and made a part of the Agreement.

The project manual also contained a concurrence form which stated:

This CONTRACT shall not be effective unless and until concurred in by the State Director of the Farmers Home Administration, U.S. Department of Agriculture or a delegated representative.

[T5] Whitlock does not dispute that these provisions were contained in the documents it received prior to submitting a bid. Whit-lock also does not dispute that it reviewed the documents before submitting its bid. The notice of claim filed by Whitlock with the State pursuant to the Wyoming Governmental Claims Act acknowledges the "bid and contractual requirement that the State and Federal governmental agencies involved are required to concur at the bid selection."

[T6] After reviewing the project documents, Whitlock prepared and submitted a bid. Four other bids were submitted by other entities. One of those bids, submitted by Larry's Inc., was lower than Whitlock's bid. The project engineer analyzed and evaluated the bids and submitted a report to the JPB in which he noted problems with the low bid submitted by Larry's.

[17] - On July 15, 1997, at a special meeting of the JPB, the project engineer's report was discussed, and the JPB voted unanimously to accept the Whitlock bid. Whitlock was notified of the JPB action by telephone later that same evening. The parties apparently are in agreement that the requirement of agency concurrence was not mentioned during the telephone call.

[T8] After the special meeting, on July 16, the JPB's attorney sent a letter to the JPB stating, among other things, that the minutes of the July 15 meeting should be amended to reflect that acceptance of Whit-lock's bid was contingent upon agency approval. At a regular meeting of the JPB on August 6, a motion was made and passed to amend the July 15 minutes. The July 15 minutes contained in the record state:

Following a discussion on the Bid Analysis for the Basin Area Water Supply Project bid letting Mel Reid made a motion to accept the bid of Whitlock Construction as recommended by Joint Powers Board Attorney Robert Gish and Graham, Dietz and Associates. Lloyd Franks seconded and the motion carried with unanimous vote.
Phil Julliard made a motion to authorize Chairman Joyce to sign the Notice of Award to Whitlock Construction when the bid has received concurrence from the funding agencies,. Seconded by Lloyd Franks and carried unanimously.

(Emphasis added.) The italicized language was added by amendment.

*1265 [19] On July 16, 1997, the attorney for the JPB also wrote a letter to the RUS and WWDC setting forth the reasons for the JPB's decision not to accept the low bid submitted by Larry's, Inc. The RUS and WWDC asked for more information and, on July 22, the project engineer forwarded another letter to them.

[110] Upon reviewing the information provided, Prior, on behalf of the WWDC, notified the JPB that WWDC did not concur with the award to Whitlock because Larry's, Inc. was the low bidder and it had not been demonstrated to WWDC's satisfaction that Larry's was not a responsible bidder. The next day, RUS notified the JPB that it also did not concur in the award to Whitlock.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bear Peak Resources, LLC v. Peak Powder River Resources, LLC
2017 WY 124 (Wyoming Supreme Court, 2017)
Denbury Onshore, LLC v. Christensen
101 F. Supp. 3d 1147 (D. Wyoming, 2015)
Martinez v. Rocky Mountain Bank
540 F. App'x 846 (Tenth Circuit, 2013)
White v. Shane Edeburn Construction, LLC
2012 WY 118 (Wyoming Supreme Court, 2012)
Fish Creek Capital, LLC v. Wells Fargo Bank, N.A.
485 F. App'x 924 (Tenth Circuit, 2012)
M & M Auto Outlet v. Hill Investment Corp.
2010 WY 56 (Wyoming Supreme Court, 2010)
Ultra Resources, Inc. v. Hartman
2010 WY 36 (Wyoming Supreme Court, 2010)
Grommet v. Newman
2009 WY 150 (Wyoming Supreme Court, 2009)
Elworthy v. Hawkeye-Security Insurance
166 F. App'x 353 (Tenth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2002 WY 36, 41 P.3d 1261, 2002 Wyo. LEXIS 37, 2002 WL 341467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitlock-construction-inc-v-south-big-horn-county-water-supply-joint-wyo-2002.