Whitestone Construction Corp. v. Yuanda USA Corporation

CourtDistrict Court, S.D. New York
DecidedNovember 9, 2021
Docket1:20-cv-01006
StatusUnknown

This text of Whitestone Construction Corp. v. Yuanda USA Corporation (Whitestone Construction Corp. v. Yuanda USA Corporation) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitestone Construction Corp. v. Yuanda USA Corporation, (S.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT DOC #: _________________ SOUTHERN DISTRICT OF NEW YORK DATE FILED: 11/9/2021 ------------------------------------------------------------------X WHITESTONE CONSTRUCTION CORP., : : Plaintiff, : -against- : 1:20-cv-1006-GHW : YUANDA USA CORPORATION, : MEMORANDUM OPINION : AND ORDER Defendant. : ------------------------------------------------------------------ X GREGORY H. WOODS, United States District Judge: I. INTRODUCTION Defendant Yuanda USA Corporation (“Yuanda”) designed and installed a curtain wall system for a new academic building on the New York City College of Technology’s Brooklyn campus (the “Project”) pursuant to a purchase order (the “Purchase Order”) with Plaintiff Whitestone Construction Corporation (“Whitestone”). After its installation, the Project’s architects issued new design criteria because the original curtain wall designs failed to properly account for the movement of the building. As a result, Whitestone and Yuanda worked to remediate the curtain wall system to comply with the new design specifications. The parties now dispute whether Yuanda was contractually obligated to perform that remedial work. Presently before the Court are the parties’ cross motions for summary judgment. Whitestone claims that Yuanda breached the Purchase Order by failing to replace or remediate the curtain wall. Yuanda disagrees, asserting that it was under no obligation to remediate the wall, and that regardless, the work it did toward the remediation was sufficient to satisfy the terms of the Purchase Order. Because Yuanda was not obligated to remediate the WT-3 Clerestory System under the unambiguous terms of the Purchase Order, Yuanda’s motion for summary judgment is granted in part and denied part, and Whitestone’s motion for summary judgment is denied. II. BACKGROUND a. The Project Begins In March 2010, F.J. Sciame Construction Co. Inc. (“Sciame”) and the City University Construction Fund (“City University”) contracted for Sciame to construct a new academic building in downtown Brooklyn (the “Project”). See Dkt. No. 128-12 (the “Prime Contract”); Dkt. No. 121- 28, Deposition of Steven Grzic (“Grzic Dep”) 17:22-18:14. Sciame, in turn, subcontracted with Whitestone to construct the exterior building envelope for the Project. Dkt. No. 128-13 (the “Sciame Subcontract”). As part of that work, on October 24, 2013, Whitestone entered into the Purchase Order with Yuanda, which required, among other things, that Yuanda design, furnish, and

install a curtainwall system, referred to as the “WT-3 Clerestory System,” for the building. See generally, Dkt. No. 128-15 (the “Purchase Order”). Yuanda began the process of submitting shop drawings for the WT-3 Clerestory System for the approval of Sciame, its design team (the “Design Team”), and its project architect (the “Project Architect”). Dkt. No. 136 (“Yuanda Resp. to 56.1 Statement”) ¶¶ 33–36. When the Project Architect returned the relevant WT-3 Clerestory System submittal, it bore the notation “MCN” which meant only minor corrections were needed. Yuanda Resp. to 56.1 Statement ¶¶ 37–40; Dkt. 128-17. That notation gave Yuanda license to proceed with fabrication and installation of the required materials “without risk of having to make changes to the installed work without additional compensation.” Yuanda Resp. to 56.1 Statement ¶¶ 37–40; Dkt. 128-17. Yuanda fabricated and delivered the WT-3 Clerestory System in accordance with the approved shop drawings. Yuanda Resp. to 56.1 Statement ¶ 43; Dkt. No. 121-27, Deposition of

James Dearth (“Dearth Dep.”), 64:22-66:7; Dkt. No. 121-28, Grzic Dep. 107:10–22. Whitestone then installed the WT-3 Clerestory System in late 2016. Yuanda Resp. to 56.1 Statement ¶¶ 44–48; Dearth Dep. 32:19–33:4. Whitestone and Yuanda agree that, at the time of installation, Yuanda’s design and fabrication of the WT-3 Clerestory System conformed to the Project’s requirements and design specifications. Yuanda Resp. to 56.1 Statement ¶¶ 46–48. b. Sciame Issues New Design Criteria. In January 2017, the Design Team provided Sciame and Whitestone with information about the building’s expected roof deflection. Yuanda Resp. to 56.1 ¶ 50; Dearth Dep. 98:9–100:16, 111:10–114:7. That information impacted the design of the WT-3 Clerestory System. Yuanda Resp. to 56.1 ¶ 50; Dearth Dep. 98:9–100:16, 111:10–114:7. After receiving that information, Sciame issued a request for information (“RFI #1130”) to the Project’s engineer. Yuanda Resp. to 56.1 Statement ¶ 51–53; Dkt. No. 128-18. On or about January 30, 2017, the Project’s engineer issued to

new design criteria for the already-installed WT-3 Clerestory System, which Sciame passed along to Whitestone. Yuanda Resp. to 56.1 Statement ¶ 56; Dkt. No. 133 (“Second Grzic Decl.”) ¶ 37. On November 27, 2018, Whitestone submitted to Sciame a Proposed Change Order (“PCO- 098”) that included the costs to modify the WT-3 Clerestory System to accommodate the newly disclosed design criteria. Dearth Dep., 95:20-96:3; Dkt. No. 128-21; Yuanda Resp. to 56.1 Statement ¶ 64. Sciame rejected PCO-098, asserting that the changes to WT-3 Clerestory System were “remedial work, and not a design change warranting a change order to Whitestone.”1 Dkt. No. 128-22. Whitestone disputed Sciame’s rejection by submitting a Notice of Dispute to Sciame on May 3, 2019. Dkt. No. 121-8. Whitestone reiterated its position that the modifications to the WT-3 Clerestory were “new design criteria.” Yuanda Resp. to 56.1 Statement ¶ 72; Dkt. No. 128-24. In a description of the dispute, Whitestone again reiterated that “Whitestone’s and Yuanda’s respective

1 Yuanda claims that the email containing Sciame’s rejection, Dkt. No. 128–19, is inadmissible hearsay. Yuanda Resp. to 56.1 Statement ¶ 67. It is well established that “[i]n ruling on a motion for summary judgment, the district court may rely on ‘any material that would be admissible at a trial.’” Lyons v. Lancer Ins. Co., 681 F.3d 50, 57 (2d Cir. 2012) (quoting Major League Baseball Properties, Inc. v. Salvino, Inc., 542 F.3d 290, 309 (2d Cir. 2008)). Here, however, the Court does not consider the contents of the letter for the truth of the matter asserted—i.e., whether the work was, in fact, “remedial” and “not a design change.” Rather, the Court considers the email only to the extent that it demonstrates Sciame’s stated reasons for the rejection of the Purchase Order. installed WT-3 clerestory work is compliant” with the initial drawings and the original contract documents. Dkt. No. 128-25 at 1. The description of dispute also contained Yuanda’s commentary—Yuanda took the position that neither Whitestone nor Yuanda should bear responsibility for the alterations to the WT-3 Clerestory System because the “architect didn’t issue the new design criteria . . . [until] Jan 30, 2017,” after the WT-3 Clerestory System had been installed. Id. at 2–3. In 2019, Whitestone brought an action against Sciame in New York State Court claiming that Sciame had refused to engage in the dispute resolution process mandated by the Sciame Subcontract. That litigation is ongoing. Dkt. No. 133 (“Second Grzic Decl.”) ¶ 53 n.4.

c. Yuanda and Whitestone Dispute Obligations to Remedy WT-3 Clerestory System On June 24, 2019, Whitestone sent a letter to Yuanda stating that “Sciame has rejected as non-conforming Yuanda’s fabrication of the WT-3 Clerestory structural components.” Dkt. No. 128-26 (the “June 24, 2019 Letter”) at 1. It continued, “Sciame has directed Whitestone to perform the field modification as depicted in Whitestone’s PCO-098 without compensation by the end of August 2019.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lockheed Martin Corp. v. Retail Holdings, N.V.
639 F.3d 63 (Second Circuit, 2011)
Johnson v. Nextel Communications, Inc.
660 F.3d 131 (Second Circuit, 2011)
Terry v. Ashcroft
336 F.3d 128 (Second Circuit, 2003)
Johnson v. Killian
680 F.3d 234 (Second Circuit, 2012)
Lyons v. Lancer Insurance
681 F.3d 50 (Second Circuit, 2012)
Hicks v. Baines
593 F.3d 159 (Second Circuit, 2010)
JA Apparel Corp. v. Abboud
568 F.3d 390 (Second Circuit, 2009)
Kass v. Kass
696 N.E.2d 174 (New York Court of Appeals, 1998)
Greenfield v. Philles Records, Inc.
780 N.E.2d 166 (New York Court of Appeals, 2002)
Federated Mutual Insurance v. Woodstock '99, LLC
140 F. Supp. 2d 225 (N.D. New York, 2001)
Paul M. Ellington v. EMI Music, Inc.
21 N.E.3d 1000 (New York Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Whitestone Construction Corp. v. Yuanda USA Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitestone-construction-corp-v-yuanda-usa-corporation-nysd-2021.