White's Trucking Co. v. Kuney

104 P.2d 587, 4 Wash. 2d 623
CourtWashington Supreme Court
DecidedJuly 22, 1940
DocketNo. 28026.
StatusPublished

This text of 104 P.2d 587 (White's Trucking Co. v. Kuney) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White's Trucking Co. v. Kuney, 104 P.2d 587, 4 Wash. 2d 623 (Wash. 1940).

Opinion

Millard, J.

Plaintiff, a domestic corporation, brought this action to recover against defendant for alleged breach of a contract respecting the hire of trucks to move earth in connection with defendant’s contract with the United States for building an earth-work dam at Island Park, Idaho. The original complaint was for recovery of loss of profits on the time that plaintiff’s trucks would have been employed if they had hauled all the necessary earth for the dam. On the date the trial of the action commenced, plaintiff served an amended complaint, alleging that its contract with defendant obligated defendant to furnish four trucks and plaintiff nine; that four of plaintiff’s trucks were to have parity in hauling with defendant’s four trucks, and all remaining hauling was to be done by plaintiff’s other five trucks. A further item of recovery sought was the reasonable cost of a tool and repair shop built by plaintiff on the site of the work at Island Park, Idaho.

Defendant answered, admitting the agreement to pay the reasonable value of the repair shop but denying all other material allegations. The cause was tried to a jury,, which found that plaintiff was entitled to recovery of the amount tendered by defendant in payment for the repair shop in question. From the judgment entered on the verdict, its motion for new trial being overruled, plaintiff appealed.

Counsel for appellant contends that the motion for a new trial should have been granted on the ground of insufficiency of the evidence. Counsel, mindful of the rule that it is not an abuse of discretion to refuse a new trial for insufficiency of the evidence *625 where the testimony was in direct conflict and made questions for the jury, seeks to invoke the exception to the rule that, where the verdict of a jury is based upon the unsupported testimony of the prevailing party, and the trial court overrules a motion for new trial, and the testimony of the prevailing party is inherently improbable, in conflict with the physical facts, or disputed by documentary evidence, the appellate court will inquire into whether there has been an abuse of discretion on the part of the trial court in refusing a new trial. Voelker v. Cleveland, 168 Wash. 38, 10 P. (2d) 561.

The qualification of the rule is not applicable in the case at bar. No exception was taken by appellant to any instruction given to the jury. One of the instructions, which is in harmony with appellant’s theory as disclosed by its complaint, charged the jury that it was necessary for appellant to prove by the preponderance of the evidence (1) that respondent agreed to hire a definite number of appellant’s trucks to work on the Island Park job; (2) that hauling for the construction of the dam and dike throughout the entire project should be limited to four of respondent’s trucks and nine of appellant’s trucks; and (3) that respondent’s four trucks should have equal rights as to order of haul on the job with four of appellant’s trucks and that the remaining haul was to be done by appellant’s remaining trucks.

It is clear from the facts, summarized as follows, that the jury was warranted in finding that appellant failed to sustain the burden of proof, or, viewed in the light most favorable to appellant, that the evidence was (appellant so admits) in sharp conflict; therefore, as there is some support in the evidence for the verdict, the trial court did not err in denying the motion for a new trial:

*626 Respondent entered into a contract in 1935 with the United States to construct and complete during 1936 the Island Park, Idaho, dam, which was to be constructed of earth protected by a layer of rock. Difficulties in excavation prevented completion of the work in 1936. It was not until the year 1938 that the dam could be constructed. The hauling prior to 1938 was limited principally to construction of dikes or shoulders which were practically completed in 1936. Respondent owned ten trucks and four shovels, but did not have enough of his own trucks to do the hauling required by the contract. He entered into some kind of an agreement with appellant to supply trucks, accompanied by their drivers, to assist in the hauling. The contract of hiring was oral, but there were certain letters referring to the work to be performed. There is no question as to the definiteness of the contract, as disclosed by the testimony of witnesses and the correspondence, respecting the fact that the trucks of appellants were to work for a stipulated price per hour. The oral agreement and letters are not definite as to the number of trucks needed, with the exception that six trucks were needed to start the work. What amount of earth was to be hauled by appellant is not shown. It was to send six trucks to commence the work, and more trucks were to be placed on the job later if there were any necessity therefor. It is admitted that respondent should also have his trucks on the job. The evidence is in dispute as to whether respondent’s trucks were to have priority and appellant was to haul what respondent could not transport. From the beginning, respondent, who used ten trucks on the job, gave his own trucks priority. While appellant complained during the progress of the work that it was not permitted to do the amount of hauling contemplated by its arrangement with respondent, it does *627 not appear that the complaint was bottomed upon the claim of a breach of the arrangement alleged in the amended complaint; that is, respondent was to furnish four trucks and appellant nine, four of appellant’s trucks to have parity in hauling with respondent’s four trucks, and the remaining hauling to be done by appellant’s other five trucks. When the hauling operations ceased in 1936, appellant was paid in full, which payment was accepted without any protest for the hauling performed by it. Appellant arranged for work elsewhere for its trucks and placed them on another job. No hauling was done in 1937. The evidence is in conflict whether, when there was a resumption of operations in 1938 at Island Park, appellant desired to accept a contract for use of its trucks.

O. A. White, appellant’s vice-president and secretary-treasurer, in a discovery deposition taken subsequent to commencement of this action, testified (contrary to the theory of appellant’s amended complaint) that the agreement as to division of the work was on the basis, “. . . we would work them both 50-50 . . . the agreement was whatever was fair.” This witness endeavored to explain, when on the stand, his deposition, but it was for the jury to accept or reject the explanation and to determine whether any such arrangement as alleged in the amended complaint was made.

Appellant’s letter written May 20, 1936, to respondent, reads, so far as material, as follows:

“We should like very much to know if you are still planning on beginning hauling operations June 8th. We have three six-wheelers coming from Chicago to the job for June 8th and we can send three from here most any time.”

There is no statement in the letter or anything from which the jury would have been justified in inferring *628 there was an arrangement such as is now claimed by-appellant. ■

Respondent wrote to appellant as follows May 23, 1936:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Voelker v. Cleveland
10 P.2d 561 (Washington Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
104 P.2d 587, 4 Wash. 2d 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whites-trucking-co-v-kuney-wash-1940.