White v. Rhijn, No. Cv 00 0438540 S (Sep. 26, 2001)

2001 Conn. Super. Ct. 13091
CourtConnecticut Superior Court
DecidedSeptember 26, 2001
DocketNos. CV 00 0438540 S, CV 00 0441224 S
StatusUnpublished

This text of 2001 Conn. Super. Ct. 13091 (White v. Rhijn, No. Cv 00 0438540 S (Sep. 26, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Rhijn, No. Cv 00 0438540 S (Sep. 26, 2001), 2001 Conn. Super. Ct. 13091 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
STATEMENT OF THE CASE The above captioned cases were consolidated for trial and arise out of a construction contract under which Barry White was to construct a one family residence for Robert Van Rhijn and Dorothyann Van Rhijn on property they owned in Middletown.

The contract was executed on August 16, 1999 with a contract price of $324,600. The completion date was originally agreed upon as March 1, 2000 but the owners agreed to an extension to May 1, 2000.

The owners paid an advance of $32,460 on August 25, 1999 and though mechanic's lien waivers were required under the contract, White did not obtain any until after he had received and exhausted the first progress payment.

When the second progress payment inspection approached, the owners found work had not progressed as they all had agreed it would. The inspection was rescheduled to March 3, 2000 and the owners applied to the CT Page 13092 lender for the payment.

While this was being processed, a subcontractor called the owners to complain that he had not been paid. They soon learned of other unpaid subcontractors and one, A.H. Harris, filed a mechanic's lien.

The owners then stopped payment on a check for a change order and told their lender not to disburse funds premised on the March 3, 2000 inspection.

White then obtained lien waivers dated March 8, 9, and 10. The waivers did not represent all the suppliers and subcontractors who had money due. The owners then pressed White for an accounting of the funds advanced to date and the parties actually sat down with counsel on March 14 in an attempt to resolve the issues.

This attempt failed and the project slowed perceptibly. White then walked off the project and notified the owners of that fact on March 27, 2000.

After the parties parted company, White brought suit against the property owners in a three count complaint. Counts two and three were dismissed at trial and only the first count, sounding in breach of contract survives.

The property owners suit against the Whites is in thirteen counts. The first twelve counts deal with the contract, while Barbara White, wife of the builder, is joined in the last count with an allegation that the conveyance of the husband's interest in the family residence to his wife was fraudulent.

Trial started on April 19, 2001 and suffered several interruptions including one caused by the Whites filing a petition in bankruptcy court. After that court removed the automatic stay, trial resumed on June 15, 2001. Briefs followed on July 2.

DISCUSSION
I
The Case of Barry White vs. Robert and Dorothyann Van Rhijn

The allegations by Barry White are that the owners willfully breached the contract by:

"(a) refusing to timely schedule the second inspection CT Page 13093 by the defendant's construction lender, which was a prerequisite to a disbursement; (b) refusing to disburse the second draw upon completion of the required inspection; (c) seeking to offset the second payment with baseless claims relating to the construction site; (d) refusing to acknowledge the agreement of the parties that the plaintiff was to pay himself for work actually performed by him on the defendant's resident; and (e) insisting that full reimbursement for the cost of windows supplied by the defendants was to be taken from the second draw rather than only the percentage allowed by the construction lender, with the balance to be reimbursed at the end of the project."

The evidence as to the circumstances surrounding the second disbursement refutes the allegations in paragraphs a, b, and c above.

Though the bank inspection scheduled for February 29, 2000 was cancelled by Mr. Van Rhijn, because the agreed upon "milestones" in the construction had not been reached, he immediately rescheduled an inspection for March 3, 2000, three days later.

While he argues that the inspection report (Exhibit NN) indicates that 46.5% of the total for specific items had been completed, White overlooks the fact that the report noted incomplete work for which payment should not be made — masonry, for example. Other work had not even begun.

Nevertheless, the second disbursement was being processed when on March 7 a subcontractor called the owners and advised them he was owed money dating back to before the first disbursement. He threatened to file a mechanic's lien. In fact, other subcontractors had not been paid and one, A.H. Harris, filed a lien on the same day.

Apparently, at this time, White began to collect lien waivers, but the first progress disbursement was made and accepted by White on his promise to give waivers to the owners. These were not delivered as promised.

White's handling of these waivers is of particular significance because the contract for the construction (Exhibit D) contains this language:

"No payment of any portion of the purchase price will be due unless approved by Owner's construction lender and Contractor represents that it has reviewed lender's general conditions for disbursement and accepts said conditions as part of this agreement, CT Page 13094 specifically including, but not limited to, mechanic's lien waivers and completion requirements. Owner agrees to provide Contractor with a ten percent (10%) advance of first draw for materials and Contractor shall provide Owner with suitable waivers and invoices at the time of said payment. 10% advance shall be due and payable upon execution of this agreement. Contractor will not begin work until 10% advance is paid."

Exhibit D, Addendum ¶ 11.

Notwithstanding this language and the schedule of disbursements which he agreed to, White testified at trial that he entered into separate "arrangements" with his suppliers and major subcontractors by which he agreed to pay for labor and materials provided in the early phases of the contract with the proceeds of the later progress payments.

These "arrangements" were not revealed to the owners and they had no idea of their potential exposure to the filing and foreclosure of mechanic's liens.

The arguments advanced by White to justify this procedure and to suggest he was not obligated to obtain waivers lack support in the evidence, in the normal construction business practices and common sense.

The claim that White was only legally obligated to "consider" A.H. Harris at the time prior to his leaving the project (February 28 through March 27, 2000) is a glaring example of his lack of understanding of what his practices had created. (White brief, page 8).

White's claims in paragraph d are specious and inaccurate at best. Nor does he specify how the owners' "refusal to acknowledge the agreement of the parties that the plaintiff was to pay himself. . . ." served to breach the contract.

In fact, White drew quite liberally from the owners' payment and substantial expenditures were made for his general use. The court has examined the computation of the owners and agrees with the figure of $48,277.36 "for purposes other than his direct costs for material and labor" on this project. (See, Van Rhijn brief, page 13).

Finally, in support of paragraph e, the plaintiff White indulges in some speculation about what he could have done if the second progress payment had been made and the window credits were applied as he felt they should have been. CT Page 13095

This disbursement has been discussed above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kilduff v. Adams, Inc.
593 A.2d 478 (Supreme Court of Connecticut, 1991)
Beverly Hills Concepts, Inc. v. Schatz & Schatz, Ribicoff & Kotkin
717 A.2d 724 (Supreme Court of Connecticut, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 13091, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-rhijn-no-cv-00-0438540-s-sep-26-2001-connsuperct-2001.