White River Levee Dist. v. McWilliams Dredging Co.

40 F.2d 873, 1930 U.S. App. LEXIS 3273
Court of Appeals for the Eighth Circuit·Decided April 16, 1930·No. Nos. 8660, 8675·Published·Cited by 9 cases

Opinion

STONE, Circuit Judge.

This is an action by the dredging company against the district for damages, arising from breach of a contract to construct a system of ditches for the district. Because of accounting features it was brought in equity. The cause was submitted to a master. The court sustained certain exceptions and overruled others to the report, and entered a decree in favor of the plaintiff for $27,381.45, with interest thereon from August 27, 1921. From such decree the defendant brings an appeal, claiming that there should be no recovery at all. The plaintiff brings a cross-appeal, claiming recovery in larger amount.

Main Appeal.

The main appeal raises the issues of the validity of the contract and of the right of the district to terminate such contract for nonperformance.

As to the right to terminate the contract, the evidence is sharply in conflict, but is sufficient to support the finding of the master, approved by the court, to the effect that there was not sufficient basis therefor. Where a finding is made by a master and approved by the trial court, this court will not reverse such action, unless it be made to appear very clearly that there was no substantial evidence upon which to base such result. There is no such showing here, and that point is resolved against the district.

The validity of the contract is attacked upon two grounds. It is claimed that each of these grounds is a necessary precedent condition to any authority on the part of the district to make such a contract. One ofl these claimed precedent conditions is that there was no plan adopted by the board for the doing of this work before the contract was let. The second alleged precedent condition is that there was no assessment of benefits covering the work before the contract was made.

Plan of Work.

The master found that no definite plan locating the proposed ditch or drain, with proper estimate of its cost, was ever adopted by the board, and that such plans were required by the act authorizing the improvement. The court found that plans in sufficient detail were prepared by the engineers of the district submitted to and used by the board of commissioners, and that these plans set out in sufficient detail the location and size of the ditches upon which to base the estimate cost and the nature of the work to be done, and that such plans were a sufficient compliance with respect to preparation and adoption of plans.

Early in 1919 the engineer of the district was working on a general drainage survey which was apparently completed shortly before December 10, 1919. Upon that date, a meeting of the board was held for the purpose of hearing and passing upon that matter, at which time “the plans and specifications as prepared were laid before the meeting and the report of Mr. Bailéy was .read by him to the board and landowners present.” The only action taken was that “the said plans and report were ordered filed with the secretary.” The .minutes of a meeting held by the board on February 24, 1920, show that it was held for the purpose of receiving bids for this work “according to the plans and specifications of consulting engineer, 0. B. Bailey, who was present at the meeting.” At that meeting the bid of the appellee was submitted and accepted. From the above, two things appear clearly: First, that there was no formal adoption of a plan for this work; second, that some sort of plan and specifications had been filed with the board and were the bases of bids and of the contract for this work. As to just what those plans and specifications were, there is a conflict in the evidence which would have justified a finding either way as to the sufficiency of such plans. This evidence appears in the testimony of J. B. Wilson, C. B. Bailey, E. E. Mashbum, and E. L. Freeman. The testimony of Bailey is abundantly sufficient to establish that Mashbum (engineer of the district) made rather detailed plans showing the location, elevations, estimates of excavation, and other data, which were embodied in a report approved by Bailey, who acted as consulting [875] and critical engineer. In fact, Bailey was employed to check and criticize Mashburn’s work in this regard and the plans represented the work of Mashburn with Bailey’s action thereon. The court was amply justified in finding that these plans were sufficient m character to meet the requirement of the statute, leaving open only the question of law as to whether a formal adoption of the plans was required by the statute. The only statutory requirement in this regard is in connection with a reassessment. This is contained in Section 3 of the Act of 1920 (Acts Ark., Ex. Sess. 1920, No. 27, p. 263), and is as follows: “When said Board shall have formed its plans for the improvement, it shall cause the assessors of the district to make a reassessment,” etc. This required that the board should determine upon a plan for the improvement. The usual way of manifesting such a determination is by a formal action incorporated in the minutes of the board. However, where a plan has been submitted to and, by the board, ordered filed, with its secretary, and is so filed, and the board thereafter advertises for bids to do the work, as outlined by such plan, and makes a contract therefor, and the contractor proceeds with the work thereunder, we think the requirements of the above statute have been substantially met.

Assessment.

Free access — add to your briefcase to read the full text and ask questions with AI

White River Levee Dist. v. McWilliams Dredging Co., 40 F.2d 873, 1930 U.S. App. LEXIS 3273 (8th Cir. 1930).

40 F.2d 873 (White River Levee Dist. v. McWilliams Dredging Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Westfed Holdings, Inc. v. United States
407 F.3d 1352 (Federal Circuit, 2005)
Haddad v. Western Contracting Co.
76 F. Supp. 987 (N.D. West Virginia, 1948)
Blair v. United States Ex Rel. Gregory-Hogan
147 F.2d 840 (Eighth Circuit, 1945)
Storley v. Armour & Co.
107 F.2d 499 (Eighth Circuit, 1939)