White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc.

CourtDistrict Court, E.D. Virginia
DecidedJune 22, 2020
Docket3:17-cv-00355
StatusUnknown

This text of White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc. (White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc., (E.D. Va. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Richmond Division WHITE OAK POWER CONSTRUCTORS, Plaintiff, V. Civil Action No. 3:17-cv-00355-JAG MITSUBISHI HITACHI POWER SYSTEMS AMERICAS, INC., Defendant. OPINION In 2013, Mitsubishi Hitachi Power Systems Americas, Inc., agreed to provide certain materials to Old Dominion Electric Cooperative to build a natural gas power plant in Maryland. Under the parties’ contract—called the Equipment Purchase Agreement (“EPA”)—Mitsubishi promised to provide two gas turbines, associated generators, and related components for the power plant project. The EPA contained several liquidated damages provisions under which Mitsubishi would pay Old Dominion for delays in document deliveries, equipment deliveries, and substantial completion. On June 2, 2014, Old Dominion entered into an Engineer, Procure, and Construct Contract with White Oak Power Constructors to build the plant. That same day, Old Dominion, Mitsubishi, and White Oak entered into an Assignment, Assumption, and Consent Agreement, which transferred most of Old Dominion’s rights to White Oak. In essence, therefore, the EPA became a contract between White Oak and Mitsubishi. Mitsubishi and White Oak encountered various issues and delays throughout the course of the contract. On May 9, 2017, White Oak filed this lawsuit against Mitsubishi, alleging breach of contract and seeking, in part, liquidated damages. Mitsubishi intends to introduce evidence of White Oak’s actual damages to challenge the enforceability of the EPA’s liquidated damages

provisions. Mitsubishi contends that Virginia law precludes White Oak from enforcing several of the provisions because the damages resulting from the alleged delays far exceed the amount of the actual damages White Oak suffered. White Oak has moved for partial summary judgment on the enforceability of the liquidated damages provisions, asserting that Mitsubishi has waived its right to challenge the provisions and, in any event, that Virginia law precludes Mitsubishi from challenging the provisions based on White Oak’s actual damages measured after contract formation. Because Virginia law requires courts to assess the enforceability of liquidated damages provisions based on the actual damages anticipated at the time of contract formation, the Court will grant White Oak’s partial motion for summary judgment. I. BACKGROUND A, Liquidated Damages Provisions The EPA contains three liquidated damages provisions: (1) Late Document Delivery Liquidated Damages, (2) Late Equipment Delivery Liquidated Damages, and (3) Late Substantial Completion Liquidated Damages. The Court will summarize each provision in turn. 1. Late Document Delivery Liguidated Damages Section 3 of the EPA governs the document delivery requirements. Section 3.2, the Late Document Delivery Liquidated Damages provision, provides that “[White Oak] will suffer losses if certain documents . . . are not delivered to [White Oak] by or on the scheduled dates . . . set forth in the Document Delivery Schedule.” (Dk. No. 287, at 18.) The EPA, therefore, explains that [Mitsubishi] will be liable for, and will pay to [White Oak], as liquidated damages and not as a penalty, an amount equal to one thousand Dollars ($1,000) per Day for each Day that the delivery of a separately identifiable document constituting a Key

Document is delayed beyond the specified delivery dates therefor (“Late Document Delivery Liquidated Damages”). (id.) The EPA further provides that [t]his sum represents a reasonable endeavor by the Parties to estimate a fair and reasonable compensation for the foreseeable losses and expenses [White Oak] will incur as a result of late delivery of Key Documents (including losses relating to schedule delays, costs to regain schedule, and lost profits from schedule unable to be regained) and shall be [White Oak’s] sole remedy and [Mitsubishi’s] sole liability for late delivery of Key Documents. The Late Document Delivery Liguidated Damages shall be applicable and payable regardless of the actual losses and expenses incurred by [White Oak] in the event of [Mitsubishi's] failure to submit Key Documents beyond the specified delivery dates. .. . [Mitsubishi’s] liability for Late Document Delivery Liquidated Damages shall not exceed, in the aggregate, an amount equal to two percent (2%) of the Contract Price. (id. (emphasis added).) 2. Late Equipment Delivery Liquidated Damages Section 6 of the EPA sets forth guaranteed delivery dates for each of the gas turbine components. Section 6.2.1, the Late Equipment Delivery Liquidated Damages provision, provides that, [i]f the Delivery of any component of a Unit is delayed past the Guaranteed Delivery Date therefor, [White Oak] will suffer large financial losses due to, among other things, resulting costs of accelerating installation work to regain lost schedule, and loss of revenue due to the delayed availability of generation capacity of the Facility. (id. at 22.) Thus, if Mitsubishi does not deliver any of the components of the turbine units by the guaranteed delivery date, Mitsubishi shall be liable to [White Oak] and shall pay, as liquidated damages... : Days of Delay Days 1-15: thirty thousand Dollars ($30,000) per Day Days 16-30: forty thousand Dollars ($40,000) per Day Days 31 onwards: _ fifty thousand Dollars ($50,000) per Day

(id.) The provision limits the damages to $100,000 per day and 15 percent of the contract price “in the aggregate.” (/d.) In § 6.2.2(d), [t]he Parties acknowledge and agree that the Late Equipment Delivery Liquidated Damages are reasonable liquidated damages (and are not a penalty), considering the resulting costs of accelerating installation work to regain lost schedule and loss of revenue to [White Oak] due to the delayed availability of generation capacity of the Facility and other losses that [White Oak] will sustain in the event of delayed delivery of components of the Units. The Parties agree that such fixed amounts are a fair and reasonable estimate of such losses as [White Oak] may reasonably anticipate from such delays and... shall be [White Oak’s] sole remedy and [Mitsubishi’s] sole liability for late delivery of components of the Units, and... that the Late Equipment Delivery Liquidated Damages shall be applicable regardless of the actual losses sustained by [White Oak] in the event of any such delays. (/d. at 23 (emphasis added).) 3. Late Substantial Completion Liguidated Damages Section 8 of the EPA governs substantial and final completion of the project. Section 8.2.1, the Late Substantial Completion Liquidated Damages provision, provides that if, due in whole or in part to deficiencies, faults or defects in a Unit or the actions or omissions of [Mitsubishi] or its Personnel, Substantial Completion has not been achieved by the Guaranteed Substantial Completion Date, then [Mitsubishi] will pay to [White Oak] the following amounts (“Late Substantial Completion Liquidated Damages”) for each Day after the Guaranteed Substantial Completion Date that Substantial Completion is not achieved due in whole or in part to deficiencies, faults[,] or defects in a Unit or the actions or omissions of [Mitsubishi] or its Personnel: fifty thousand Dollars ($50,000) per Day, for Days 1-30, and one hundred fifty thousand Dollars ($150,000) per Day for Days 31 and onward. (id. at 33.) The provision limits the Late Substantial Completion Liquidated Damages to 15 percent of the contract price. The parties agreed that the Late Substantial Completion Liquidated Damages are reasonable liquidated damages (and are not a penalty), considering the losses and expenses (including without limitation loss of revenues) that [White Oak] will incur if Substantial Completion is delayed beyond the Guaranteed Substantial Completion Date. The Parties agree that such fixed amounts are a fair and reasonable estimate of such

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Doral Bank PR v. Federal Home Loan Mortgage Corp.
477 F. App'x 31 (Fourth Circuit, 2012)
Boots, Inc. v. Prempal Singh
649 S.E.2d 695 (Supreme Court of Virginia, 2007)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
512 S.E.2d 811 (Supreme Court of Virginia, 1999)
O'BRIAN v. Langley School
507 S.E.2d 363 (Supreme Court of Virginia, 1998)
Brooks v. Bankson
445 S.E.2d 473 (Supreme Court of Virginia, 1994)
Taylor v. Sanders
353 S.E.2d 745 (Supreme Court of Virginia, 1987)
Babcock & Wilcox Co. v. Areva NP, Inc.
788 S.E.2d 237 (Supreme Court of Virginia, 2016)
Ameritech Construction Corp. v. Cummings
66 Va. Cir. 328 (Winchester County Circuit Court, 2005)
Bel-Aire, Inc. v. RB Trexlertown, L.L.C.
68 Va. Cir. 108 (Virginia Beach County Circuit Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-oak-power-constructors-v-mitsubishi-hitachi-power-systems-americas-vaed-2020.