White Construction Co., Inc. v. Commonwealth

418 N.E.2d 357, 11 Mass. App. Ct. 640, 1981 Mass. App. LEXIS 1012
CourtMassachusetts Appeals Court
DecidedMarch 31, 1981
StatusPublished
Cited by24 cases

This text of 418 N.E.2d 357 (White Construction Co., Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White Construction Co., Inc. v. Commonwealth, 418 N.E.2d 357, 11 Mass. App. Ct. 640, 1981 Mass. App. LEXIS 1012 (Mass. Ct. App. 1981).

Opinion

*641 Kass, J.

Article XIII of the standard form of agreement employed — and drafted — by the Commonwealth in 1966 to hire architectural services conferred upon the architect an unconditional release of all liability, including design errors, before construction on the project involved even began. Because the language of Article XIII effectively nullifies the statutory mandate of G. L. c. 7, § 30C, as appearing in St. 1953, c. 612, § 5, and § 30E, as amended by St. 1962, c. 757, § 27, 3 we do not give the text literal effect and reverse the judgments below.

Procedurally, the White Construction Co., Inc. (White), case began with a complaint under G. L. c. 258 against the Commonwealth in which White alleged, among other things, that the plans and specifications for the Science Classroom-Dining Hall Building at the State College in Lowell were so “fundamentally defective and inadequate” as to result in extra construction costs for which White, as the general contractor on the job, demanded compensation. The Commonwealth brought a third-party complaint 4 against Desmond & Lord, Inc., the architectural firm which drew the plans and specifications for the Lowell State College job. Desmond & Lord moved for summary judgment on the third-party complaint. That motion was allowed and, upon a determination by the judge that there was no just reason for delay, 5 judgment entered for Desmond & Lord.

In the companion case, the Commonwealth sought damages from Desmond & Lord and from various contractors who constructed buildings at the Cape Cod Community *642 College. 6 Desmond & Lord brought Sepp Firnkas Engineering, Inc., a consulting structural engineering firm, into the case by third-party complaint. The form of contract which the Commonwealth used to employ Desmond & Lord in this case was identical to that involved in the White case. A different Superior Court judge allowed a motion for summary judgment in favor of Desmond & Lord and Sepp Firnkas because he felt bound by the summary judgment action taken by the judge in the earlier case. As between the same parties, the Commonwealth and Desmond & Lord, the same issue had come up, was essential to the judgment and was adjudicated. The second judge, therefore, believed his decision governed by the prior adjudication. Boyd v. Jamaica Plain Co-op. Bank, 7 Mass. App. Ct. 153, 155 (1979). Restatement (Second) of Judgments § 68 (Tent. Draft No. 4, 1977). Compare Rudow v. Fogel, 376 Mass. 587, 591-592 (1978). However, the second judge expressed “grave reservations concerning the substantive propriety of this result” and reported his interlocutory order 7 allowing the motions for summary judgment to this court under Mass.R.Civ.P. 64, 365 Mass. 831 (1974). 8 The two cases were then consolidated for argument.

What is striking about these cases is the manner in which the Commonwealth has run upon its own sword. As we have noted, the Commonwealth drafted the instrument to govern the terms of all architectural services which it was engaging at that time. Indeed, the record discloses an uncontroverted affidavit by the president of Desmond & Lord *643 that “[t]here was no negotiation or discussion as to the terms and conditions of the [cjontract, and it was given to Desmond & Lord, Inc. for signature after it had been prepared by plaintiff.” The section of the contract now in controversy, Article XIII, appears as an entirely separate provision (i.e., it is not a subsection or subparagraph) captioned “Release and Discharge.” Its full text is as follows:

“ARTICLE XIII. Release and Discharge.
Payment to the Designer by the Commonwealth pursuant to Paragraph 6 of ARTICLE XI above and acceptance of such payment by the Designer, shall release and forever discharge the Commonwealth and the Designer, respectively, from all claims, demands, and liabilities of every nature, whether in law or equity, asserted by either against the other and arising from or in any way connected with the Project, unless: (1) simultaneously with such acceptance the Designer shall advise the Commonwealth in writing of any such claim, demand, or liability asserted by the Designer against the Commonwealth; and (2) within six (6) months thereafter the Designer shall have taken action to enforce the same.”

Paragraph 6 of Article XI provides that the architect shall be paid seventy-five percent of his fee “upon award of the Construction Contract,” less all payments previously made. 9 Thus, by the literal terms of the contract, the architect is released from liability with all his supervisory work still to be done (those functions are discussed infra) and the correctness of his plans and specifications still to be tested.

In an effort to avoid the stark clarity of the language of Article XIII, the Commonwealth offers an affidavit by its *644 Director of the Bureau of Building Construction that neither he nor his predecessors (the affidavit is undated but was filed in court on December 27, 1979) interpreted Article XIII to release the designer when a project proceeded to construction; i.e., the release provision was to operate only in cases where the Commonwealth abandoned, during the design stage, the project for which the architect was drawing plans. A release, however, which is unequivocal in its terms cannot be explained by parol evidence. Radovsky v. Wexler, 273 Mass. 254, 258 (1930). If any exclusion from the scope of the release were intended, it would have to be stated. Schuster v. Baskin, 354 Mass. 137, 140 (1968). Gaudette v. Kelly, 7 Mass. App. Ct. 100, 104-105 (1979).

Deciding that the language of Article XIII means what it says does not, however, end the inquiry if the release provision in this public contract is not compatible with requirements of public law. The provisions of G. L. c. 7, §§ 30C and 30E, 10 entered the statutory scheme upon a recommendation (and proposed text) which appeared in the Eleventh Report of the Special Commission on the Structure of the State Government, 1953 House Doc. No. 2575. That report said that: cumbersome change order procedures in the system then governing State construction projects caused delay and consequent expense (id. at 7); and inadequate inspection resulted in losses to the Commonwealth (id. at 8). It foresaw benefits from more systematic and exacting inspections (id. at 12); and laid stress on the importance of inspection during the construction phase (id. at 25-26).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northside Recycling, Inc. v. City Council of Salem
119 N.E.3d 355 (Massachusetts Appeals Court, 2018)
Cameron Painting, Inc. v. University of Massachusetts
983 N.E.2d 1210 (Massachusetts Appeals Court, 2013)
Boston Housing Authority v. National Conference of Firemen & Oilers, Local 3
935 N.E.2d 1260 (Massachusetts Supreme Judicial Court, 2010)
Lowell Housing Authority v. PSC International, Inc.
692 F. Supp. 2d 180 (D. Massachusetts, 2010)
Southbridge Associates II, LLC v. Town of Southbridge
21 Mass. L. Rptr. 31 (Massachusetts Superior Court, 2006)
Doyle v. Commonwealth
830 N.E.2d 1074 (Massachusetts Supreme Judicial Court, 2005)
J.E. Pierce Apothecary, Inc. v. Harvard Pilgrim Health Care, Inc.
365 F. Supp. 2d 119 (D. Massachusetts, 2005)
Gordon v. Millivision Holdings, LLC
19 Mass. L. Rptr. 61 (Massachusetts Superior Court, 2005)
Travelers Casualty & Surety Co. of America v. Long Bay Management Co.
14 Mass. L. Rptr. 255 (Massachusetts Superior Court, 2001)
Dagastino v. Commissioner of Correction
754 N.E.2d 150 (Massachusetts Appeals Court, 2001)
MacLean v. State Board of Retirement
733 N.E.2d 1053 (Massachusetts Supreme Judicial Court, 2000)
Subaru of Wakefield, Inc. v. Subaru of New England, Inc.
10 Mass. L. Rptr. 525 (Massachusetts Superior Court, 1999)
Marlborough Savings Bank v. City of Marlborough
697 N.E.2d 143 (Massachusetts Appeals Court, 1998)
Kelleigh v. Algonquin Gas Transmission Co.
6 Mass. L. Rptr. 208 (Massachusetts Superior Court, 1996)
Industrial Sewing Services, Inc. v. Commonwealth
5 Mass. L. Rptr. 474 (Massachusetts Superior Court, 1996)
Venus Drywall, Inc. v. Kullman Industries, Inc.
5 Mass. L. Rptr. 70 (Massachusetts Superior Court, 1996)
R-1 Associates, Inc. v. Goldberg-Zoino & Associates, Inc.
4 Mass. L. Rptr. 219 (Massachusetts Superior Court, 1995)
City of Boston v. Back Bay Cultural Ass'n
635 N.E.2d 1175 (Massachusetts Supreme Judicial Court, 1994)
Boston v. BACK BAY CULTURAL ASSOCIATION, INC.
635 N.E.2d 1175 (Massachusetts Supreme Judicial Court, 1994)
Lovering v. Beaudette
572 N.E.2d 591 (Massachusetts Appeals Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
418 N.E.2d 357, 11 Mass. App. Ct. 640, 1981 Mass. App. LEXIS 1012, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-construction-co-inc-v-commonwealth-massappct-1981.