White Consolidated Industries, Inc. v. Westinghouse Electric Corporation

179 F.3d 403, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 48 ERC (BNA) 1747, 1999 U.S. App. LEXIS 10839, 1999 WL 333207
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 27, 1999
Docket98-3524
StatusPublished
Cited by17 cases

This text of 179 F.3d 403 (White Consolidated Industries, Inc. v. Westinghouse Electric Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White Consolidated Industries, Inc. v. Westinghouse Electric Corporation, 179 F.3d 403, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 48 ERC (BNA) 1747, 1999 U.S. App. LEXIS 10839, 1999 WL 333207 (6th Cir. 1999).

Opinion

CLAY, Circuit Judge.

Plaintiff-Appellant, White Consolidated Industries, Inc. (“WCI”), appeals from the order entered by the district court granting summary judgment in favor of Defendant-Appellee, Westinghouse Electric Corporation (“Westinghouse”), and denying WCI’s cross-motion for partial summary judgment, in this action for indemnity and contribution for remediation costs incurred in relation to the cleanup of a contaminated site in Edison, New Jersey. WCI brought suit against Westinghouse for indemnity under an Agreement of Purchase and Sale (“Purchase Agreement”), and contribution under the Comprehensive Environmental Response Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9607-9675 (1994), the New Jersey Spill Compensation and Control Act of 1977, N.J. Stat. Ann. § 58:10-23 (1993), and pendent state common law claims. WCI alleges that the district court erred when it determined (i) that WCI impliedly assumed future arising environmental liabilities, including CERCLA liability, under *406 the Purchase Agreement; (ii) that Westinghouse did not breach a warranty in the Purchase Agreement, as Westinghouse did not know about any contamination or liability; (iii) that WCI cannot prevail against Westinghouse for fraudulent concealment because Westinghouse was not aware of any “defect” at the time of contracting; and (iv) that summary judgment was appropriate with respect to WCI’s claims of misrepresentation, public nuisance, and strict liability for abnormally dangerous activities, although discovery had not been conducted on these issues. For the reasons set forth below, we AFFIRM the decision of the district court.

I.

The facts of this case are undisputed. Westinghouse, a corporation duly organized under the laws of Pennsylvania, owned and operated a facility in Edison, New Jersey (“Edison facility”) from at least 1951 through 1974. Westinghouse manufactured radios and televisions at the Edison facility until 1969 or 1970, when Westinghouse converted the facility for the manufacture of dehumidifiers and air conditioners. While manufacturing dehumidifiers and air conditioners, Westinghouse used trichloroethylene (“TCE”), a hazardous solvent, as a degreaser and/or cleaning agent. In 1970, TCE spilled from a ruptured 2000-gallon tank, and forced the evacuation of at least a portion of the Edison facility. Westinghouse dealt with the spill by closing off the affected areas, opening windows, and running fans, thus allowing the material to evaporate. By the next day, no contamination was observable.

WCI, a Delaware corporation with its principal office in Cleveland, Ohio, purchased Westinghouse’s major appliance manufacturing business, including the Edison facility, in 1975. The terms of the sale were set forth in the Purchase Agreement, dated December 31, 1974, and amended January 10 and February 28, 1975. In the Purchase Agreement, Westinghouse represented that “to the best of [its] knowledge and belief,” there were no “existing facts or conditions which might give rise to any claim, litigation, proceeding or investigation” and that “none of the operations conducted on the Real Properties ... presently violate any applicable [] antipollution ... requirement (under interpretations currently in effect).” (J.A. at 131, 132). Westinghouse agreed to indemnify WCI for “any and all damages and liabilities whatsoever resulting from any misrepresentation of Westinghouse.” (J.A. at 154). However, Westinghouse did not disclose to WCI the fact that there occurred a spill of TCE at the Edison Facility in 1970.

Approximately fifteen years after WCI purchased Westinghouse’s business, WCI discovered evidence of TCE contamination at the Edison facility. WCI submitted these results to the New Jersey Department of Environmental Protection (“NJDEP”) on October 10, 1991, and later entered into a Memorandum of Agreement with the NJDEP, wherein WCI agreed to implement a remedial action work plan to clean up the contaminated soil and groundwater at the Edison facility. WCI determined, through witnesses and environmental studies, that the likely source of the TCE contamination was the 1970 TCE spill that occurred when Westinghouse owned and operated the Edison facility. Consequently, WCI sent Westinghouse a letter, dated March 17, 1993, advising and demanding that Westinghouse assume liability and contribute response costs for the environmental contamination that resulted from the spill. Although Westinghouse acknowledged the occurrence of the TCE spill, Westinghouse denied that it was liable for remediation costs of the contaminated site.

WCI filed suit against Westinghouse in federal court on October 4, 1993, seeking recovery of response costs incurred in regards to the environmental cleanup at the Edison site. WCI sought declaratory, in-junctive, and compensatory relief pursuant to (i) CERCLA, 42 U.S.C. §§ 9607-9675 *407 (1994); 1 (ii) the Spill Act, N.J. Stat. Ann. § 58:10-23.11 (1993); 2 (iii) breach of contract; (iv) misrepresentation; (v) negligence; (vi) public nuisance; and (vii) strict liability for abnormally dangerous activity. Westinghouse answered the complaint and filed a counterclaim for contribution against WCI.

On September 22, 1994, WCI filed a motion for partial summary judgment based on CERCLA, the Spill Act, and breach of contract. In response, Westinghouse moved for summary judgment in its favor on all of WCI’s claims the following day. On March 19, 1998, the district court granted summary judgment to Westinghouse on WCI’s claims and denied WCI’s motion for partial summary judgment. The district court determined, in relevant part, that Westinghouse could not have known in 1975 that the TCE spill that occurred when it owned the Edison facility could give rise to liability for environmental remediation because the laws that created such potential liability, namely CERCLA and the Spill Act, did not exist at the time and were not enacted until years later. The district court further concluded that Westinghouse was entitled to rely on the unambiguous language in the assumption of liability provision, which states that WCI assumes responsibility for future liabilities. As for WCI’s breach of contract and fraudulent concealment claims, the district court determined that Westinghouse did not breach a warranty in the agreement, or fraudulently conceal a “defect,” because Westinghouse did not know about any contamination or existing environmental liabilities. WCI filed a timely notice of appeal to this Court on April 17,1998.

II.

This Court reviews de novo a district court’s grant of summary judgment. See EEOC v. Prevo’s Family Mkt., 135 F.3d 1089, 1093 (6th Cir.1998). Summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reed v. Procter & Gamble Manufacturing Co.
556 F. App'x 421 (Sixth Circuit, 2014)
Textileather Corporation v. GenCorp Inc.
697 F.3d 378 (Sixth Circuit, 2012)
Textileather Corp. v. GenCorp Inc.
709 F. Supp. 2d 597 (N.D. Ohio, 2010)
In Re Babcock & Wilcox Co.
413 B.R. 337 (E.D. Louisiana, 2009)
Ford Motor Company v. United States
378 F.3d 1314 (Federal Circuit, 2004)
Telxon Corporation v. Federal Insurance Company
309 F.3d 386 (Sixth Circuit, 2002)
Cytec Industries, Inc. v. B.F. Goodrich Co.
196 F. Supp. 2d 644 (S.D. Ohio, 2002)
Sherwin-Williams Co. v. Artra Group, Inc.
125 F. Supp. 2d 739 (D. Maryland, 2001)
Southdown v. Allen
119 F. Supp. 2d 1223 (N.D. Alabama, 2000)
Velsicol Chemical Corp. v. Reilly Industries, Inc.
67 F. Supp. 2d 893 (E.D. Tennessee, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
179 F.3d 403, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 48 ERC (BNA) 1747, 1999 U.S. App. LEXIS 10839, 1999 WL 333207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-consolidated-industries-inc-v-westinghouse-electric-corporation-ca6-1999.