Whistler v. Hyder

879 P.2d 214, 129 Or. App. 344, 1994 Ore. App. LEXIS 1169
CourtCourt of Appeals of Oregon
DecidedAugust 3, 1994
Docket92-0701; CA A80214
StatusPublished
Cited by7 cases

This text of 879 P.2d 214 (Whistler v. Hyder) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whistler v. Hyder, 879 P.2d 214, 129 Or. App. 344, 1994 Ore. App. LEXIS 1169 (Or. Ct. App. 1994).

Opinion

*346 EDMONDS, J.

Defendant Munson 1 appeals from a declaratory judgment in favor of plaintiffs that set aside defendant’s declaration of forfeiture and reinstated the parties’ land sale contract. Plaintiffs cross-appeal, assigning error to the trial court’s finding that they were in default under the land sale contract and to the award of attorney fees and costs to defendant. We review de novo. ORS 19.125(3); see also U.S. Nat’l Bank v. Caldwell, 60 Or App 639, 641, 655 P2d 180 (1982), rev den 294 Or 536 (1983). Because we hold that the trial court erred in finding that plaintiffs were in default under the terms of the land sale contract, we affirm on the appeal and reverse on the cross-appeal.

In January, 1990, plaintiffs entered into a land sale contract with Tod and Kathie Brostrom for the purchase of approximately 76 acres of land on which there was a house, three ponds and a dam. The agreement provides that “purchaser takes the properly and the improvements thereon in the condition existing at the time of this agreement, and in their present condition, ‘AS IS.’ ” Sometime after the purchase, the Brostrom’s assigned their seller’s interest to David Dixon. On December 30,1991, Dixon’s attorney wrote a letter to plaintiffs notifying them that Dixon considered them to be in breach of the contract, because allegedly, they had failed to make timely installment payments, they had failed to make the tax payments when due, they had failed to provide proof of insurance, they had failed to maintain the dam in proper condition by allowing the spillway to become overgrown, and they had failed to maintain the house in good condition by not correcting a pest infestation. Plaintiffs denied that they were in breach of the contract.

In January, 1992, Dixon’s attorney notified plaintiffs that they were in default, because they had failed to correct the problems that were referred to in his earlier letter, and that he was initiating forfeiture proceedings. He attached a copy of a notice of default, which he had filed with the county clerk on January 31,1992. See ORS 93.910; ORS 93.915. The *347 notice said that plaintiffs were in default in the particulars mentioned in the first letter, with the exception of the allegation that plaintiffs had failed to make timely installment payments. The notice gave plaintiffs 60 days to cure the defaults. Sometime after the notice was filed, Dixon assigned his interest in the property to defendant. On February 19, 1992, plaintiffs’ attorney wrote a letter to Dixon’s attorney, stating that all of the taxes had been paid and that the damage to the dam was caused by and would be fixed by the Water District. Attached to the letter was proof of insurance.

On May 8, 1992, defendant filed with the clerk and served on plaintiffs a declaration of forfeiture pursuant to ORS 93.930. It averred that plaintiffs had failed to cure the defaults relating to the maintenance of the dam and the house. Shortly thereafter, plaintiffs filed the complaint in this case, seeking a declaratory judgment that they were not in default. They sought injunctive relief to prevent defendant from taking any further action pursuant to the declaration of forfeiture. The matter went to trial, and the trial court found that plaintiffs were in default regarding their obligation to maintain the dam and the house, because they had not completed the repairs to those improvements within 60 days of the notice of default. However, the court also found that no waste to the premises had occurred. It held that the 60-day time period in which to cure the defaults was unreasonable because of the nature and extent of the required repairs. It concluded:

“[I]t is equitable and not contrary to the purposes of ORS 93.905 to 93.940, to declare that the rights of the Plaintiffs under the contract are not forfeited by the declaration of forfeiture made by Defendant Munson. This Court further concludes however, that Plaintiffs shall pay the costs and expenses, including limited attorney fees, as provided by ORS 93.920.”

On appeal, defendant argues that the trial court did not have the statutory authority to refuse to enforce the declaration of forfeiture in the light of its finding that plaintiffs were in default. The predicate to defendant’s argument is that plaintiffs were in default and, therefore, we address plaintiffs’ cross-appeal first. Plaintiffs argue that, because the court found that no waste had been committed on the property, it wrongfully concluded that plaintiffs were in *348 default and erred in awarding attorney fees and costs to defendant.

The contract provides, in pertinent part:

“Commencing with the possession date and thereafter at all times during the term of this contract, [plaintiffs] shall[,] with respect to the property[,] do the following:
“1. Keep all improvements now existing or which shall hereafter be placed on the property in good condition and repair and not permit any waste or removal thereof.
“Time is of the essence of this contract. A default shall occur if:
“1. [Plaintiffs fail] to make any payment within 30 days after it is due; but [defendant] shall not be obligated to give notice to [plaintiffs] to constitute a default under this subparagraph, or
“2. [Plaintiffs fail] to perform any other obligation imposed by this contract and [do] not correct or commence correction of such failure within 30 days after receipt of written notice from [defendant] specifying the manner in which [plaintiffs are] in default.” (Emphasis supplied.)

The provisions in the contract about maintaining the condition of the improvements are in the conjunctive. The first requirement is that plaintiffs keep all improvements existing at the time of the contract “in good condition and repair.” The second provision requires plaintiffs not to permit any waste or removal of the improvements. It is apparent from the context of the language that the provisions are intended to maintain the condition of the improvements so that defendant will be restored to property that has retained its value in the event of a forfeiture. The law imposes a duty of good faith and fair dealing in contracts to facilitate performance and enforcement in a manner that is consistent with the terms of the contract and that effectuates the reasonable contractual expectations of the parties. See Pacific First Bank v. New Morgan Park Corp., 319 Or 342, 876 P2d 761 (1994); Sheets v. Knight,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graydog Internet, Inc. v. Giller
381 P.3d 903 (Multnomah County Circuit Court, Oregon, 2016)
Ross Dress for Less, Inc. v. Makarios-Oregon, LLC
180 F. Supp. 3d 745 (D. Oregon, 2016)
Grants Pass Imaging & Diagnostic Center, LLC v. Marchini
346 P.3d 644 (Court of Appeals of Oregon, 2015)
Safeco Insurance v. Masood
330 P.3d 61 (Court of Appeals of Oregon, 2014)
Blunier v. Staggs
279 P.3d 826 (Court of Appeals of Oregon, 2012)
Mountain High Homeowners Ass'n v. J. L. Ward Co.
209 P.3d 347 (Court of Appeals of Oregon, 2009)
Schlabach v. Tollenaar
98 P.3d 1154 (Court of Appeals of Oregon, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
879 P.2d 214, 129 Or. App. 344, 1994 Ore. App. LEXIS 1169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whistler-v-hyder-orctapp-1994.