Whedon v. Lancaster County

114 N.W. 1102, 80 Neb. 682, 1908 Neb. LEXIS 44
CourtNebraska Supreme Court
DecidedFebruary 6, 1908
DocketNo. 15,348
StatusPublished
Cited by8 cases

This text of 114 N.W. 1102 (Whedon v. Lancaster County) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whedon v. Lancaster County, 114 N.W. 1102, 80 Neb. 682, 1908 Neb. LEXIS 44 (Neb. 1908).

Opinion

Calkins, C.

Under the provisions of the act of 1905 (Comp. St. 1905, ch. 78, secs.-83-85p) the county board of Lancaster county [683]*683on April 26,1906, entered into a contract with one Charles G-. Sheeley for the construction of all bridges that might be required to be built in said county within the period of one year from that date. After the completion of a large number of bridges under this contract the county board, on the 5th day of January, 1907, entered upon the record of its proceedings of that day that the contract in question “is hereby canceled by mutual consent,” and on the same day caused to be' indorsed upon the contract itself the words “this contract is hereby canceled by mutual consent,” which indorsement was signed by the chairman of the board and by the agent of. the contractor. Following this action the board, after advertising for 'bids and finding that the proposal of the defendant, the Nebraska Construction Company, was the lowest and best bid, awarded to it a contract for building all bridges that might be required to be built in the said county during the term of one year from the 1st day of March, 1907. It appears that the prices of both material and labor had advanced between the date of the execution of the contract of Ajjril 26, 1906, and the cancelation of the same, and that the cost to the county under the new contract would be much greater for the same kind of work than under the contract made in 1906. On the 2d day of March, 1907, the plaintiff, a taxpayer and landowner of Lancaster county, brought this action against the county board and the Nebraska Construction Company to enjoin them from proceeding under the new contract, upon the ground that the said board was without power to terminate the contract of 1906, and that in so doing its members Avere actuated bv improper and corrupt motives. The court beloAv granted the injunction prayed for, and from its judgment this appeal is brought.

1. It appears that, when this suit was brought the members of the county board and the county attorney did not agree as to the policy which should be adopted in defending the same; and the county board, acting in pursuance of the provision of the statute authorizing it to employ addi[684]*684tional counsel when requested so to do by petition signed by ten freeholders (Comp. St. 1905, ch. 7, sec. 18), designated other counsel to conduct the defense of this cause. Thereupon the county attorney intervened on behalf of the county in a petition in which he practically joined the plaintiff in the charges made by him and in demanding the relief prayed for. When the case came to this court, it was upon the appeal of the defendant, the Nebraska Construction Company. The county board afterwards filed a separate appeal, which the county attorney moved to dismiss. This was denied, and a motion for a rehearing of this order was submitted with the main case upon the argument. The case having been submitted, it is unnecessary to determine whether the appeal of the county board was authorized or properly made. Under the provisions of the statute of 1908 (code, sec. 681a), we are practically required to hear de novo all appeals from decrees in equity cases, and to render or direct the rendition of such judgment as in our opinion the court below should have -entered. The question presented by the appeal of the defendant, the Nebraska Construction Company, cannot be determined without determining the question raised by the appeal of the county board. If the Nebraska Construction Company had dismissed its appeal before the submission of the case, then the question might have arisen; but, as the case now stands, it is not involved.

2. The excuse of the county board for terminating a confessedly advantageous contract nearly four months before its expiration was that the season’s work was practica1^ over, and that the board desired to let the contract for the ensuing year at a date early enough to enable the new contractor to prepare himself for beginning work in the spring. This end might have been attained by negotiating for the new contract before the expiration of the old one.' This suggestion is met by the statement that a former county attorney had advised the board that it was better to cancel an existing contract before advertising for new proposals, and that the board believed it to be neces[685]*685.«ary to terminate the old contract before it could take ,slops for the making of a new one. It is also suggested that the price of material was rapidly advancing, and that the board believed more favorable prices could be secured by an (airly letting of the contract.. The district court exonerated the members of the county board from any intentional wrongdoing; and, in the view we take of the powers of the county board, it is not necessary for us to determine whether the excuses presented by it for its action are sufficient to overcome the inference that would naturally arise from its conduct unexplained. The action of the board in terminating the contract of April 26, 1906, on January 5, 1907, was by it denominated a cancelation, and it has been so spoken of in the argument of counsel. We regard the use of the term cancelation as inaccurate and likely to be misleading. To cancel is to annul and destroy. The cancelation of a contract necessarily implies a waiver of all the. rights thereunder by the parties. If, after a breach by one of the parties, they agree to cancel it, that is a waiver of any cause of action growing out of the original breach. Dreifus, Block & Co. v. Columbian Exposition Salvage Co., 194 Pa. St. 475, 75 Am. St. Rep. 704. The contract had been in force for some 9 months, and a large amount of work had been performed under it. It is plain that the parties did not intend to cancel the contract in the true sense of that word. What they meant to do, and what they did do, if it was within the scope of the power of the county board, was to change the contract with respect to its duration. The question presented by the record is not whether a county board may cancel a contract of this character, but whether it can change the period of duration of the yearly contracts provided for by the act of 1905 (Comp. St. 1905, ch. 78, sec. 84). It is argued that the unmaking of a contract is within the. power which made it, and is equally effectual. This is true when applied to natural persons, and it may be true when applied to corporate officers having a general power* to contract; but, when the power to contract is granted to public. [686]*686officers with accompanying restrictions and limitations as to tbe manner in which it is to be exercised, the power must be exercised within the limits of these restrictions. In the statute Avhich we are considering, the board is authorized to make yearly contracts for all bridges to be built within their respective counties for the period of one year, at a specified sum per lineal foot for the superstructure, and at a specified sum per foot, board measure, for" the wood material used in the substructure of such bridges. Having chosen to proceed under this power, the board has accepted the limitations imposed by the statute. The period for which it may make this contract has been fixed by the statute, and all bridges built Avithin the period must be built under this contract. The county board may not let the contract for a greater period, nor for a less, than is prescribed by the statute. This is not only conceded by the defendants, but is insisted upon in their argument. To make a contract for a year, and terminate it at the end of 8 or 9 months, would be to do indirectly what the board might not do directly, and this cannot be permitted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No. (2001)
Nebraska Attorney General Reports, 2001
Friedman v. City of Chicago
30 N.E.2d 36 (Illinois Supreme Court, 1940)
Corning v. Patton
182 So. 39 (Supreme Court of Alabama, 1938)
Sommer v. International Harvester Co. of America
193 S.E. 476 (Court of Appeals of Georgia, 1937)
Walter-Wallingford Coal Co. v. A. Himes Coal Co.
194 N.W. 493 (Michigan Supreme Court, 1923)
Reichert v. Russell Motor Car Co.
186 Iowa 437 (Supreme Court of Iowa, 1919)
Nelson v. City of Florence
144 N.W. 791 (Nebraska Supreme Court, 1913)
Sheibley v. Fales
116 N.W. 1035 (Nebraska Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
114 N.W. 1102, 80 Neb. 682, 1908 Neb. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whedon-v-lancaster-county-neb-1908.