Wheaton v. Berg

52 N.W. 926, 50 Minn. 525, 1892 Minn. LEXIS 353
CourtSupreme Court of Minnesota
DecidedJuly 15, 1892
StatusPublished
Cited by14 cases

This text of 52 N.W. 926 (Wheaton v. Berg) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheaton v. Berg, 52 N.W. 926, 50 Minn. 525, 1892 Minn. LEXIS 353 (Mich. 1892).

Opinions

Dickinson, J.

This is an action to have established and enforced a mechanic’s lien upon a lot of land owned by the defendant Nilson, but which he had contracted to sell to the defendant Berg. Berg interposed no defense. The numerous defendants, other than Berg and Nilson, also asserted claims for mechanics’ liens upon the property, which they sought to have adjudged and enforced in this action. These various lien claims having been sustained by the decision of the [530]*530court, and judgment having been directed for the enforcement of the same (with some exceptions hereafter specified) by sale of the property, including the interest of Nilson therein, he moved for a new trial, which was refused, and he alone prosecutes this appeal from the order refusing a new trial.

The defendants Andrew Moe and the Pineville Lumber Company not appearing in opposition to the appellant’s motion that the order appealed from be reversed as to them, the motion should be granted, and the order for judgment, so far as it involves the charging of the amount of the recovery of those two defendants as a lien upon the real estate, and the enforcement of such lien by sale, is reversed. It will hence be unnecessary to consider some assignments of error which relate merely to the claims of these parties, and to the manner in which they were directed to be enforced.

The other defendants, as to whom a like motion was made, having appeared by Messrs. Reed & Kerr, the attorneys for the other respondents, and asked that íhe case as to them be considered upon the briefs submitted in behalf of the other respondents, this is allowed, and the motion to reverse, as for their default, is denied.

The appellant, Nilson, the owner of the lot in question, entered into a written contract with Berg for the sale of it to him, on the 29th of August, 1889. The contract provided that the entire purchase price ($1,575) should be paid on or before ninety clays thereafter. It was expressly provided in the written contract that all improvements on the premises, or which might be made thereon, should become the absolute property of the vendor, and held as additional security for the payment of the purchase price, and should be forfeited by the purchaser in case of his failure to comply with the conditions of the agreement.

Under this contract Berg went into possession, and commenced the erection of a dwelling house on the premises. It was found as a fact by the court that he purchased the lot for that purpose, and that the appellant knew this when he contracted to sell; that the appellant knew that the house was being constructed from the time when building operations were commenced; and that he never made any objection thereto. While, from the evidence, it might be doubted [531]*531whether Nilson knew anything about the building operations until after the foundation was completed, it is conceded that at' that stage of the work, some time in September, he did know that the building was being constructed. As by this decision the lien upon the appellants’ estate will be sustained only for material and labor supplied subsequent to October 1st, it is unnecessary to consider whether the court erred in finding that Nilson had knowledge of the improvement from the commencement of the building operations.

It further appeared from the evidence that in the latter part of November of the same year, at the expiration of the time within which the purchase price was agreed to be paid, Nilson agreed to extend the time of payment to the 14th day of December, and a new contract was executed to that effect, by the terms of which the specified time of payment was made an essential part of the agreement. The purchase price was never paid, and on the 14th of February, 1890, after all the materials and labor had been contributed for which liens are claimed, except as to some part of two of the claims, the appellant gave notice to Berg, and to the lien claimants, that the contract of sale would be forfeited, unless the purchase price should be paid before the 15th day of March.

No notice was ever served or posted by the appellant, such as is prescribed by Laws 1889, ch. 200, § 5.

The claim of the plaintiff Wheaton, Beynolds & Co. is for lumber purchased from them by Berg and furnished for this building between the 4th of October and the 3d of December, pursuant to a verbal contract which the court found, to have been made after October 1, 1889: It appears from the evidence that the agreement for the sale of the greater part of this was made before October 1st, although none of the material was delivered until after that date. It is hence claimed, on the authority of O’Neil v. St. Olaf’s School, 26 Minn. 329, (4 N. W. Rep. 47,) that the lien law of 1889, which took effect October 1st of that year, is not available to the lien claimant. But we hold otherwise, for the reason that, the verbal agreement being within the statute of frauds, it only became effectual and enforceable as a contract by the delivery after October 1st. Hence the finding of the court as to the time of the agreement is in accordance with [532]*532the legal effect of the transaction, and the law of 1889 is applicable.

The defendants Frank F. and Noble G. Thompson, (Thompson Bros.;) Standard Menomonie Brick Company; Frank P. Nicoll, as assignee of J. P. Gray; Adam Gilles, August Anderson, and F. L. Whitcomb, (Twin City Sidewalk & Pavement Company;) P. O. Simonson; the Farnham Marble & Mantel Company; J. S. Cusick; Ole Johnson; Ole Skjolberg; Robert Thompson; and C. F. Warn— severally furnished material or did labor for the construction of the building under contract with Berg, during various periods between the 1st day of October, 1889, and the 17th day of April, 1890.

The mere fact that one of the defendants (Warn) was not brought in as a party, nor his claim interposed by answer, until after the commencement of the trial, constitutes no ground for a reversal. It is immaterial when be was joined as a party, unless the appellant was prejudiced by being unprepared to meet the claim thus presented; and the settled case does not show surprise, or that opportunity was sought to produce other evidence. Section 10 of the lien law makes liberal provision for the addition of new parties at any time before final judgment, and even after judgment; and the court would, of course, upon the bringing in of a new party, allow, upon application therefor, such opportunity as might be reasonable for adverse parties to meet the claims of any such new parties.

A general objection to the calling of the defendant Berg as a witness for cross-examination under the statute (Laws 1885, ch. 193) was overruled. Whether the statutory rule allowing such'a course of examination was applicable we need not consider; for the nature of the examination of the witness was not such as to make this a matter of any practical importance.

The point is made that the answers of the defendants Skjolberg and Warn do not state facts sufficient to constitute a cause of action. The defect specified is that the answers were framed with a view of showing a right of lien under section é of the statute, but that there is no allegation that the contract of sale (between Nilson and Berg) had been forfeited, so as to bring’ the case within the terms of that section. This objection cannot avail the appellant, for he by his answer has evidently intended to set forth the fact of the forfeiture of [533]*533the contract, thereby supplying the alleged defect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Master Asphalt Co. v. Voss Construction Co.
535 N.W.2d 349 (Supreme Court of Minnesota, 1995)
Albuquerque Lumber Co. v. Montevista Co.
38 P.2d 77 (New Mexico Supreme Court, 1934)
Couture v. Hennessy
208 N.W. 545 (Supreme Court of Minnesota, 1926)
Ruedlinger v. Fisher
200 N.W. 299 (Supreme Court of Minnesota, 1924)
Fauser v. McElroy
195 N.W. 786 (Supreme Court of Minnesota, 1923)
Henning v. McAdam
193 N.W. 124 (Supreme Court of Minnesota, 1923)
Berglund & Peterson v. Abram
182 N.W. 624 (Supreme Court of Minnesota, 1921)
Minneapolis Plumbing Co. v. Arcade Investment Co.
145 N.W. 37 (Supreme Court of Minnesota, 1914)
Stewart v. Talbott
146 P. 771 (Supreme Court of Colorado, 1913)
Christianson v. Hughes
122 N.W. 384 (North Dakota Supreme Court, 1909)
Title Guarantee Co. v. Wrenn
56 P. 271 (Oregon Supreme Court, 1899)
Congdon v. Cook
56 N.W. 253 (Supreme Court of Minnesota, 1893)
Sandberg v. Palm
54 N.W. 1109 (Supreme Court of Minnesota, 1893)
McCausland v. West Duluth Land Co.
53 N.W. 464 (Supreme Court of Minnesota, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
52 N.W. 926, 50 Minn. 525, 1892 Minn. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheaton-v-berg-minn-1892.