LUSK, J.

These are two actions (consolidated for trial in the circuit court and here) commenced by the plaintiff, William W. Wheatley, to recover the reasonable value of services alleged to have been rendered by him for the defendants. In the one case, the defendants are Carl M. Halvorson, Inc., an Oregon corporation, and H. Halvorson, Inc., a Washington corporation. In the other, the sole defendant is Halvorson Contracting Corporation, an Oregon corporation, hereinafter called the “Contracting Company.” Plaintiff recovered judgments in both cases, and the defendants have appealed.

In the case against the two defendants, the services are alleged to have been rendered during the years 1950, 1951 and 1952. The plaintiff is a bookkeeper who became an employee of Carl M. Halvorson, Inc., a contracting firm, in 1947 at a salary of $75.00 a week for a 40-hour week plus $15.00 a month travel expense allowance, and continued in such capacity until May, 1953. During the years 1950 to 1953, that corporation and H. Halvorson, Inc., were engaged as joint adventurers in the construction of a radar station at Condon, Oregon, for the United States Army. The plaintiff’s claim is for services rendered to the joint adventure.

In the case against the Contracting Company, the services are alleged to have been rendered by the [398]*398plaintiff to that corporation during the years 1949-1953, both inclusive. This corporation was organized about 1949 by the owners of Carl M. Halvorson, Inc., for the purpose of holding title to some of the equipment used by the latter and which was rented by it from the Contracting Company.

All the services for which the plaintiff claims compensation in both cases were rendered by him in the office of Carl M. Halvorson, Inc., and the Contracting Company at 218 Builders Exchange Building, Portland, Oregon, and all were of the same general character as those which he was employed to render.

Defendants in both cases assign as error the court’s denial of their motions for a directed verdict. We are of the opinion that the question is controlled by our decision in Wheatley v. Halvorson, 213 Or 228, 323 P2d 49. There the same plaintiff sued to recover the reasonable value of services rendered to Carl M. Halvorson, Inc., H. Halvorson, Inc., and Halvorson Construction Company, Inc., a Washington corporation, and a co-partnership composed of. two individuals. The services were alleged to have been rendered during the years 1951, 1952, and 1953. The three corporations, two of which are defendants in one of the cases now before us, and the co-partners, who were members of the Halvorson family, were sued as members of a joint adventure engaged in construction of the Tecolote Tunnel. The jury returned a verdict for the plaintiff against Carl M. Halvorson, Inc., alone. This court, in an opinion by Mr. Justice Brand, reversed for two reasons. First, the liability, if any, of partners or joint adventurers being joint not several, the judgment must be for or against all of them (a question not here involved). Second, the law presumes that all the services ren[399]*399dered by an employee, during the period for which he is employed, of a nature similar to those required of him in the course of Ms regular duties are paid for by his salary, and to overcome this presumption he must show an express agreement for extra services. The evidence showed the similarity of the services, and there was no such express agreement. We concluded: “Under the circumstances of tMs case, we hold that in the absence of an express agreement therefor, plaintiff was not entitled to extra compensation.”

There is no difference of substance between the present cases and the former case. These are likewise actions on implied contracts and no express agreement for extra services is shown. The testimony as to the terms of plaintiff’s employment, Ms duties thereunder, the nature of the services, the failure of the plaintiff as bookkeeper to enter on the books any charges for extra services, his failure to make a claim therefor until approximately two months after his employment had terminated, the generous bonuses he received from his employer—all is of the same general character as in the previous case. The only factual difference is that the Contracting Company was not a joint adventurer with the other corporations, but a mere adjunct of Carl M. Halvorson, Inc., organized for tax purposes—a difference not material upon the question of the plaintiff’s right to extra compensation.

The circuit court erred in denying the motions for directed verdicts, and the judgments are reversed.

Norman B. Kobin and Leo Levenson, Portland, for the petition. Paul Gferhardt, Portland, contra. Before Lusk, Presiding Justice, and Rossman, Warner and Sloan, Justices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wheatley v. Carl Halvorson, Inc.
323 P.2d 49 (Oregon Supreme Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
333 P.2d 739, 215 Or. 396, 1958 Ore. LEXIS 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheatley-v-carl-m-halvorson-inc-or-1958.