Whalen v. Ford Motor Credit Co.

475 F. Supp. 537
CourtDistrict Court, D. Maryland
DecidedAugust 15, 1979
DocketCiv. B-75-1792
StatusPublished

This text of 475 F. Supp. 537 (Whalen v. Ford Motor Credit Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whalen v. Ford Motor Credit Co., 475 F. Supp. 537 (D. Md. 1979).

Opinion

MEMORANDUM AND ORDER

BLAIR, District Judge.

This is an action arising out of the issuance of a loan commitment for a condominium project in Towson, Maryland. The plaintiffs are the owners, Towson Associates Limited Partnership and its general partner, Cornelius Whalen, and the general contractor for the project, Robert Whalen Co., Inc. The defendant is Ford Motor Credit Company (Ford Credit). In substance, the plaintiffs allege that Ford Credit breached its contractual obligations under the loan commitment by refusing to provide without justification the required funding when due. Jurisdiction is founded upon 28 U.S.C. § 1332, diversity of citizenship. Ford Credit has moved for summary judgment, contending that plaintiffs have no standing to bring this cause of action and that the financing commitment expired by its terms when the condition precedent that the building be completed was not satisfied. The plaintiffs have also moved for summary judgment on the ground that Ford Credit was bound to honor the commitment when the required architect’s certificate of completion was issued. These motions have been well-briefed by both sides, and no hearing is necessary for their resolution. Local Rule 6.

I. Factual Background.

Towson Associates developed a condominium project in Towson, Maryland known as the “Towson Center.” The project is a 28-story building containing approximately 240 units. Ford Credit issued a commitment in February 1973 to Towson Associates to lend it $9,750,000 for a period of two years after completion of the project. During this two-year period, Towson Associates planned on completing the sale of condominium units to the public. In exchange for the commitment, Towson Associates paid Ford Credit $195,000 and also obligated itself to pay a release fee of 1% upon the sale of each unit. Under the terms of the commitment, Ford Credit was required to advance the funds as long as the building was completed by the expiration date, March 1, 1975. Pursuant to an amendment to the commitment, the expiration date was extended to September 1,1975 in consideration of an additional fee of $48,750 which was paid by Towson Associates to Ford Credit.

*539 In May 1973, Equibank, a national banking association, issued a construction commitment to Towson Associates, also in the amount of $9,750,000, to provide funds for the construction of the project. On August 28, 1973, the construction loan closing was held. At that time, Towson Associates, with Ford Credit’s approval, assigned to Equibank the Ford Credit commitment; this was done to provide Equibank with additional security for the construction loan it had made to Towson Associates. Also on August 28,1973, Ford Credit issued a letter which has been referred to by the parties as a buy-sell agreement. Under the terms of this agreement, Ford Credit agreed to purchase from Equibank the loan in the maximum amount of $9,750,000 provided that the construction loan documents were assigned to Ford Credit and that Towson Associates complied with all the terms of the Ford Credit commitment, including completion of construction by September 1, 1975. In short, Equibank financed the construction of the project, and Ford Credit agreed to provide the financing thereafter by purchasing the loan from Equibank if certain conditions were met.

On September 2, 1975, when the parties intended to close the purchase by Ford Credit of Equibank’s loan to Towson Associates, Equibank tendered to Ford Credit the documents required under the buy-sell agreement and asked Ford Credit to provide the funding in accordance with its commitment and the buy-sell agreement. Ford Credit, however, inspected the building and determined that it was incomplete. It therefore took the position that the condition precedent to funding, completion of the building, was not satisfied, and it did not advance the $9,750,000.

The plaintiffs allege that the commitment and other relevant documents were fully complied with on their part, and, in particular, that construction was completed in accordance with the terms of the commitment. They have brought this action for breach of contract. Ford Credit’s motion for summary judgment, is premised on two grounds: (1) that plaintiffs have no standing to bring this suit, since they assigned away their cause of action when the Ford Credit commitment was assigned to Equibank, and (2) that Ford Credit had no obligation to provide funding since the building was not completed. The plaintiffs as well have moved for summary judgment, contending that Ford Credit as a matter of law was required to provide funding under its commitment on September 2, 1975.

II. Standing.

Ford Credit’s position on this issue is straightforward. It argues that its obligation to lend money arises only out of the February 14,1973 loan commitment and not out of any other document. Any claim for an alleged breach of the obligation to provide funding can only be made by the party to whom the obligation is owed. The commitment was originally issued to Towson Associates; however, since Equibank wanted added security, it had Towson Associates assign the commitment to it. Accordingly, Ford Credit contends that Towson Associates has no remaining rights under the commitment and therefore cannot bring this action alleging a breach of an obligation created only by that commitment. 1

The court disagrees with this analysis. In determining the intention of the parties to this transaction, the court should construe together all the related documents concerning this financing scheme. Rocks v. Brosius, 241 Md. 612, 217 A.2d 531, 545 (1966). It is apparent to the court in doing so that Towson Associates does have standing to bring an action arising out of an alleged breach of Ford Credit’s obligation to provide funding. Ford Credit’s argument ignores the purpose of the transaction as a whole — to finance Towson Associates’ efforts to develop the project.

If the Ford Credit commitment had not been assigned to Equibank and if no buy-sell agreement had been executed, at the completion of construction Ford Credit *540 would have been obligated to provide the necessary financing to Towson Associates, assuming compliance with the terms of the commitment. Towson Associates would then have used those funds to pay Equibank the money it was owed .under the construction loan. Under the system envisioned by the parties in this case, instead of Ford Credit providing the funds to Towson Associates and Towson Associates reimbursing Equibank with those funds, Ford Credit would transmit the amount of the loan directly to Equibank who would assign the loan and related documents to Ford Credit. This procedure accomplished the same goal in a more efficient fashion; its purpose was to effect the loan to Towson Associates while affording each party with adequate safeguards in the event of a failure to perform by another party.

Construing all the related documents together, the court does not agree with Ford Credit that Towson Associates has no rights against Ford Credit in the event of its failure to lend the funds as required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul at Chase Corp. v. Manufacturers Life Insurance
278 A.2d 12 (Court of Appeals of Maryland, 1971)
Della Ratta, Inc. v. American Better Community Developers, Inc.
380 A.2d 627 (Court of Special Appeals of Maryland, 1977)
Selective Builders, Inc. v. Hudson City Savings Bank
349 A.2d 564 (New Jersey Superior Court App Division, 1975)
Rocks v. Brosius
217 A.2d 531 (Court of Appeals of Maryland, 1966)
Spates v. Spates
296 A.2d 581 (Court of Appeals of Maryland, 1972)
Carter v. Connecticut Mutual Life Insurance
404 U.S. 857 (Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
475 F. Supp. 537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whalen-v-ford-motor-credit-co-mdd-1979.