Wetzel v. Rixse

1923 OK 973, 220 P. 607, 93 Okla. 216, 1923 Okla. LEXIS 394
CourtSupreme Court of Oklahoma
DecidedNovember 13, 1923
Docket12307
StatusPublished
Cited by7 cases

This text of 1923 OK 973 (Wetzel v. Rixse) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wetzel v. Rixse, 1923 OK 973, 220 P. 607, 93 Okla. 216, 1923 Okla. LEXIS 394 (Okla. 1923).

Opinion

Opinion by

FOSTER, C.

This action was commenced in the district court of Kay county, Okla., on the 24th day of October, 1919, by F. D. Rixse and Charles B. Jenkins, partners, doing business as Rixse & Jenkins, defendants in error, plaintiffs below, against Eugene Wetzel, plaintiff in error, defendant below, to recover the sum of $1,820 as damages for the alleged breach by Wetzel of a written contract. The parties will be hereinafter referred to as they appeared in the court below.

The contract referred to is as follows:

“Ponca City, Oklahoma, 6-6-1919.
“Order for Architectural Services.
“F. D. Rixse, Architect.
*217 “You are hereby authorized to prepare preliminary drawings, complete working drawings and specifications, supervise the letting of contracts and supervise the construction of a brick building located at Ponca City, Oklahoma, for which services we agree to pay SV2% of the total cost of building and permanent fixtures.
“Terms of payment to be as follows: For preliminary drawings 1% of the estimated cost of the building same to be payable when preliminary drawings are approved. 1% when contract is let or within thirty davs after plans and specifications are completed. Balance as work progresses.
“Remarks: The remainder of the 3%% tí» be made in two payments. One payment when the building is 50% done, and the balance when the building is completed.
“fSigned) Eugene Wetzel, Owner.
“Rixse & Jenkins Architects.
“By Charles B. Jenkins.”

The petition alleged that the contract had been broken by the defendant on or about the 29th day of August, 1919, in that the defendant informed plaintiffs that he would not perform the contract and repudiated the same, and in performance of the contract they prepared all the preliminary drawings, complete working drawings and all plans and specifications for the construction of a brick business building, located in Ponca City, Okla., and had at all times- been willing and able to perform all the services specified in said contract, and had been damaged in the sum of .$1,820 on account of the alleged breach of the contract by the defendant, for which they demanded judgment.

The defendant filed an answer and cross-petition in which he admitted the execution of the contract, but denied that plaintiffs had prepared or submitted to the defendants any plans which' he was able to use, in that the plans, drawings, and specifications submitted involved an encroachment of the proposed building on adjoining lots and buildings belonging to other parties on which the defendant had uo right to go, and that the plaintiffs had wholly failed to comply with any part of their said contract, and that by reason of the failure of the plaintiffs to prepare the plans and specifications according to the contract, he was .compelled to employ other architects, and was damaged on account of the delay in the construction of his building in the sum of $6,340.

The reply of plaintiffs was a general denial. The cause was tried to a jury which resulted in a verdict for the plaintiffs in the sum of $1,100. Judgment was entered upon the verdict, and the defendant brings the matter regularly on appeal to this court.

It is contended, first, that the verdict of the jury is not sustained by any evidence, and that the court erred in overruling the demurrer of the defendant to the evidence of the plaintiffs.

Second, that the court erred in giving instruction No. 3 to the jury, and in refusing to give instructions No. 1 and No. 2, requested by the defendant.

And, third, that there was error in the assessment by the jury of the amount of recovery, and that the damages were excessive and were given under the influence of passion and prejudice.

The evidence in this case, as preserved in the record before us, is very unsatisfactory on the material issues in the case. The testimony of neither the plaintiffs nor the defendant is of a clear and positive character. There was a .general disposition on the part of the witnesses to overlook the issues in the case and testify concerning irrelevant matter. There was evidence, however, that when the contract in question was executed, the defendant contemplated the “reetion of a three-story brick building and that preliminary plans were submitted by the plaintiffs involving the 'construction of such building

It is insisted, however, by the defendant that these plans were not and could not be approved by him because they involved an encroachment upon adjoining property on which he had no right to go. On the contrary, it is insisted by the plaintiffs that the defendant did not object to the plans submitted because they were not in accordance with instructions theretofore given, but solely because the-defendant found that he could not construct a three-story building for the amount of money available to put into the building, !he repudiated his contract and decided to erect a two-story building.

There is some evidence in the record tending to support both theories. There is much testimony that the defendant changed his mind frequently in regard to some feature of the proposition, and that these changing moods occasioned no little inconvenience on the part of the architects in the drawing of the plans.

It is admitted, however, as we understand it-, that the plaintiffs prepared and submitted plans involving a three-story building, and that these plans were in accordance with instructions previously given, at least so far as the height of the building was concerned.

*218 In these circumstances, we think the evidence was sufficient to take the ease to the jury and to warrant the jury in finding for the plaintiffs upon the proposition that a breach of the contract by the defendant had occurred by reason of the fact that he had discovered after he let the contract that he could not erect a three-story building for the amount of money available, if they believe^ the testimony on this proposition.

If there is testimony reasonably tending to support the verdict, the Supreme Court will not substitute its judgment for that of the jury, and the determination of questions of fact will not be disturbed on appeal. Hayslip v. Great American Insurance Company, 112 Kan. 189, 210 Pac. 188; Sand Springs R. Co. v. Smith, 84 Okla. 211, 203 Pac. 207; Garrison Coal Co. v. Semple. 82 Okla. 60, 198 Pac. 497.

As pointed out above, on account of a lack of clear and positive testimony on many of the vital issues in the case, the weight of the testimony would be governed largely by the appearance and manner of the witnesses on the stand and the jury could and did, no doubt, in weighing the testimony, give due and proper consideration to these matters. ' •'

If the trial court did not err in submitting the case to the jury, it follows that the verdict of the jury must stand, unless the jury erred in the assessment of the amount of recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seldon Construction Co. v. Dowell
1940 OK 223 (Supreme Court of Oklahoma, 1940)
Voightlander v. State Ex Rel. Barnett
1935 OK 1092 (Supreme Court of Oklahoma, 1935)
Mainard v. Fowler
1935 OK 79 (Supreme Court of Oklahoma, 1935)
Yellow Taxicab & Baggage Co. v. New
1935 OK 55 (Supreme Court of Oklahoma, 1935)
Connelly v. Loub
1934 OK 461 (Supreme Court of Oklahoma, 1934)
Mitchell v. Dadas
1934 OK 128 (Supreme Court of Oklahoma, 1934)
Swift v. Payne
1928 OK 168 (Supreme Court of Oklahoma, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
1923 OK 973, 220 P. 607, 93 Okla. 216, 1923 Okla. LEXIS 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wetzel-v-rixse-okla-1923.